HomeMy WebLinkAboutGeorge Harvey Construction/CO4/ENG/Cool Creek Trails/inc 5,645 Contract No:R -29657 Change Order No.: 004
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -29657 Letting Date:02/09/2011
District:GREENFIELD DISTRICT AE:Goldner, Rob PE /S:Surber, Rob Status:Draft
Change Order Information Change Order No.: 004 EWA: Y or Force Acct: N
Date Generated: 00 /00 /0000 Date Approved: 00 /00 /0000
Reason Code: CHANGED COND, Materials Related
Description: Floor Beam modification due to lenght
Original Contract Amount 583,765.77
Current Change Order Amount 5,645.00 Percent: 0.967
Total Previous Approved Changes 5,465.00 Percent: 0.936
Total Change To -Date 11,110.00 Percent: 1.903
Modified Contract Amount 594,875.77
Time Extension Information iCg•
Date Initiated 00 /00 /0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00 /00 /0000 or SS Calendar/Work Days 0
SP Date 00/00 /0000 or SP Days
(SS Standard Specification, SP Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 0 SP Days Value 0.00
Previous Time Approved SS Days by AE: DCE: SCE: DDCM:
SS Days SP Days Value
Revised Contract Time SS Completion Date 00 /00 /0000 or SS Calendar/Work Days 0
SS Date 00 /00 /0000 or SP Days 0
4s
i Nattit*D .�s
R DOGS ti
V) ti
Cr
J
Contract No:R -29657 Change Order No.: 004
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE: DCE: SCE: DDCM:
($perChangeOrder) LE$ 250K-) LE$750K- LE$2M— GT$2M
(Days per Contract) (50 SS days 100 SS days 200 SS Days (GT 200 SS days)
Verbal Approval Required? Y N If Y, by Date Issued
Total Change To- Date >5 Y N If Y Copy to Program Budget Manager
Scope /Design Recommendation Y N If Y, Referred to Project Manager(PM)
Required?
Date to PM Date Returned
Approval Authority Concurs with PM? Y N If Y, Concurrence by Date
If N,Resolution: Approved Disapproved
Resolved by Date
LPA Signatures Required? Y N If Y, Date to LPA Date Returned
FHWA Signatures Required? Y N If Y, Date to FHWA Date Returned
Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer Date
Comments:
I
Contract No:R -29657 INDIANA Date:05/05/2011
Change Order No:004 Department of Transportation Page: 3
Contract: R -29657
Project: 0600390 State:0600390
Change Order Nbr: 004
Change Order Description: Floor Beam modification due to lenght
Reason Code: CHANGED COND, Materials Related
CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change
0087 0600390 0087 711 -51038 LS 5,645.000 1.000 C Amount$ 5,645.00
Item Description: STRUCTURAL STEEL
Supplemental Descriptionl: Floor beams have to be field modified due to being to long.
Supplemental Description2:
Total Value for Change Order 004 5,645.00
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
The floor beams on the bridge are longer than shown on plans. The correction of cutting the beams was the cheaper of the two options to
eliminate the issue.
Change Order Explanation for Specific Line Item
N..
It Is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order Is hereby acknowledged.
Contractor. Signed By:
Date:
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract No:R -29657 INDIANA Date:05/05/2011
Change Order No:004 Department of Transportation Page: 4
HN Hf Hf
APPROVED FOR LOCAL PUBLIC AGENCY
Gin/ ati4i ,Jr e. s(1///
(SIGNATURE) (TITLE) (DATE
(SIGNATURE) (TITLE) (DATE)
SUBMITTED FOR CONSIDERATION
PENS
1N 1N11N111fifrlMHHHNNfiiNHHNNeH�ll kl NfIIHYNHININH�HMNM11iN1N11fYf1 fN
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level Name of Approver Date Status
George R. Harvey Son, Inc.
964 N. SR 39 Danville IN. 46122
317345.5169 Fax 317.745.2733
April 26, 2011
Rob Surber
Project Supervisor
Butler, Faiiman Seufert J L
4.-
Contract: R- 29657 -A ..5/ I
Re: Floor Beam Length
Rob,
The center to center of the two trusses does not match the Plans. We have figured the
center line to center line of the trusses to be 17' 3 -3/4 Plans show 15'10".
There are two options we can due to correct this. One is to widen the abutments and add
another stringer and decking. The other is to cut the floor beams to a length to get the
Plan center to center of trusses correct.
6 We have done a cost analysis of the two options. The cutting of the floor beams will be
4 E edesign of the abutment a deck is about $7,346.00. See the attached
computation sheet.
Please let us know which direction to take so we can order the structural steel and stare
on the floor beams if that is the direction you want to take.
If you have any questions, please contact me at 317.745.5169 or
dickharvey@a.sbcglobal.net.
Cordially,
7,/t- 7,
---4 -1/ J
Richard A. Harvey
An Equal Opportunity Employer
Z9 57 Ca,./-
Sloe..- E 4 F�,� 8 s c» re lAss
4 6,2 S G. Le at: X ONE. fiat fmJ
O£ 9p-04-54e-4-1
24 tv.,4 -cit_ wir
u-. 9 Ax-r 15 44.11
S sAi,a7 12 ,xj SW J e .Tw -3, /0 /364-c,i
Lwr 4 B nS SA-v,/ o,t. PI-as c«.-rrEL Z0e,
[_4B. 2m Z 44.1 G -r X 4- s //zo BJeE. R t�.TS
L at3oQ i r+ a,j k 8) 70 SGa
3(Qo
_...P.e N_•o .3U e q. 2 403 0...
S w 147 -4 N- 1?!- f-.-a- ai
Gu /a e Kam,:.. Zy ,-a_ V 7d 4 75
7 to l /0 e 7 7 00
;0-,„,F,... -4 3
ADD 5"1 e{, t2 P.04- 4, e Z 5,6 4 5
5
s �a soo° z zlz
o sib. 227 Z
p �a /54 81 zz-9 r� Z Zo9-
16 6#` S► 3 Z it i 5
y 90- 1_1 Z
I oce�4-S im. Gl�ss`p: 415)1- a LC y
-4./.1- i
I ....._„...1....„-- lOr 4 l ,744 V656
Z
b 4. ptw 0VVM1,C.
X 1 za Sal
Z Z7° 3 —.5;_0.46,
29657 -4 5/2 //7
S/ken .1 r -a,2 BE441
T p 5 t4D e 'r o f 1 T r LG?72_ 5 E c ∎A1s L 00 2.6s d r TO WE 4'
ii
CuT e_xisrl.54 geae..4.&1 4 X 4- Z%Qc_T3 ?km /lop„a-
L ur rr_. ,a C..wiirroNI 4 4
Deus.. 14-oc. b,s 14 r
Botts to &A.
C.Lcr reylsi IL. FLto LAsoi. Z uze-10 14a
a as Z5
Lu t' N-01.4.4. t tJ )UST k. 4 5CA A,s 4 EA, LA r Z ill. e 7D
iv 24a- 645 p Zs
M-OLE 14 &A.. LA-koe 411-Q e_70 Zik,
srts
8otr% 16 LA /6 Ego /4,0
4 O Qz o
s 6�-
Follow up issues Page 1 of 1
Follow up issues
Littlejohn, David W [dlittlejohn @carmel.in.gov]
Sent Friday, April 29, 2011 1:55 PM
To: Robert Surber
Attachments: C0_2_Greyhound_trail.pdf (57 KB) bridge_deck_and_curb.pdf (109 KB) DSCN1494.JPG (401 KB) DSCN1499.JPG (385 KB)
retaning_wall conf.pdf (268 KB)
Rob,
I was able to meet with Mike M and discuss the project after our meeting. Attached is a signed CO. We are also comfortable with
the most recent proposal for the traffic maintenance.
I confirmed the bridge deck colors and have attached a scan of the approved colors for the deck and curb (the deck color is the
"Dark Gray" and the curb is the only gray that was provided in their samples). If you need more detail on these, please let me
know. If you need to pick them up, I can leave them at our front office.
For the trusses, we agreed that the best option is cutting the floor beams and are comfortable moving ahead with the quoted
price.
For the retaining walls, I have attached a couple of pictures of the walls that were built for the Hagan Burke Trail. I think it is best
to keep the walls similar to the existing wall. The closest fit that I saw in the brochure Harvey provided was the Allan Block AB
Classic Champagne wall. I attached a scan of the page for your reference.
I think that covers everything we discussed this morning, but if I missed something or you need anything else please feel free to
contact me.
I will be out of the office until Thursday, the
David Littlejohn, AICP
Alternative Transportation Coordinator
Department of Community Services
City of Carmel
One Civic Sq
Carmel, IN 46032
(317) 571 -2306
A Please consider the environment before printing this e-mail
https //bfsnt6.bfsengr.com/owa/ ?ae= Item &t IPM. Note& id= RgAAAAAtiGCV xsgkQ41fDRhPmMenBwCYK... 5/5/2011