HomeMy WebLinkAboutA Letter of Determination 10-18-11October 18, 2011
City of Carmel
Department of Community Services
Mr. Tony Barbee Mr. Robert Potakar
PulteGroup. Traditions on the Monon HOA
11590 N. Meridian Street Smoky Row
Suite 530 Carmel, IN 46032
Carmel, IN 46032
Re: Traditions on the Monon Zoning and quality construction issues.
Dear Mr. Barbee and Mr. Potokar:
This letter is to inform you of a determination made by the Director of Community Services,
pursuant to the authority granted in Section 29.04 of the Carmel Zoning Ordinance, on the above
referenced matter. I have reviewed in detail the issues surrounding each complaint raised in the
"Traditions on the Monon Defects List" dated of August 29, 2011. After careful review and
analysis, including consultation with DOCS staff, Department of Engineering personnel, and
outside experts, I conclude the following:
1. Banked Parking Area.
A new parking area was constructed by PulteGroup (Pulte) in response to a complaint by the
Traditions HOA (HOA), per their previously submitted "Transition Report" of August 2010,
and subsequent action by the City of Carmel. This parking area was constructed in a location
and of a configuration consistent with the Development Plan for the project. The HOA has
identified in the HOA "Defects List" (Attachment A) four complaints to this parking lot
construction, as follows:
The parking area is not curbed
The parking area needs light pole
The parking areas drainage design should require an overflow curb
The parking area guard rail needs painted
Determination:
A. The parking lot was constructed without curbing pursuant to the Carmel Zoning
Ordinance requirements. It is determined that the developer shall install approximately
one hundred sixty (160) feet of curb along the sides of the eastern part of the lot,
according to the standards of the Department of Engineering.
B. The installation of a light for this area, while helpful for safety and security, is not a
requirement of City ordinances or of the PUD, and shall not be required.
C. The installation of an additional overflow curb adjacent to the retaining wall will not
result in an improvement to the drainage design and shall not be required.
Division of Planning Zoning One Civic Square Carmel, IN 46032 317 571 2417
Michael P. Hollibaugh, Director
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 2
D. The guard rail design must be completed, including installation of additional segments of
missing rail material, approximately eight (8) boards. An additional coating of black
paint shall be applied to the railing already in existence, with additional paint required for
the newer sections.
Upon completion of the above, the surety in place to ensure proper parking lot installation will
be released
2. Streets and Curbs
A lengthy list of pavement defects was presented by the HOA in the Traditions on the Monon
Transition Report of August 2010. While a number of the defects listed have been repaired
by the developer, there are nine items identified in the HOA "Defects List" of 8/29/11. Since
that list was issued, the Department has found seven items which remain incomplete or
unresolved:
Street Curb cracks 20
Bldg 15 No concrete curb on road end 36 feet
9th Street NW West end north side no curb 114 feet
l l th Street NW East end no curb 45 feet
Monon Lane East end no concrete curb 66 feet
Monon Lane No street name sign has been installed
Bldg 7 Finish asphalt top coat missing
Bldg 14, 15 Finish asphalt top coat missing
Determination:
A. The presence of 20 remaining cracks in the curbing has been identified and categorized as
to their severity by the City Engineer. The repair of those cracks is essential to the
longevity of the improvement, and for proper conveyance of storm water. The repair of
all curbs with cracks rated as "category 2, 3, 4, and 5" shall be required according to the
standards of the Carmel Department of Engineering.
B. The HOA identified that "finish asphalt top coat is missing from the areas around
Building 7, on 3 Ave. NW, and from the private drive servicing Buildings 14 15.
Finish asphalt has been installed throughout the project, including the areas identified by
the HOA. The addition of more pavement in the area of Building 7 will likely have a
negative effect on drainage in this area, and shall not be required.
However, it is observed that the concrete drives for Building 7 have been installed with a
finished grade approximately 1" above finished pavement, creating a problem for
maintenance, current and future.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 3
In order to repair this, the driveway pad to each unit in Building 7 shall be reinstalled so
the concrete is flush with the asphalt pavement of the drive lane. This shall be in the form
of an entirely new driveway or a pad renovation by saw cutting and removal of the
existing concrete drive in the location of the mid -point control joint and new pour to
proper elevation.
New concrete driveways shall be poured to be flush with the existing finish asphalt,
consistent with other areas throughout the project.
A similar issue occurs in the area of Building 14 15, where the offset between the
concrete drive and top of asphalt is a maintenance problem and not consistent with the
standard for the property. This is especially evident at Building 14 where the joint
between asphalt and the concrete driveway holds sufficient moisture for moss to grow.
This area shall be repaired by the builder either through milling of existing asphalt and
the laying of new asphalt to the level of the drive, or through the reconstruction of
driveways, as detailed for Building 7.
C. The HOA identified the need to install curbs at the ends of drive lanes in four locations. It
is determined that the pavement design in those areas is per the approved plan for the
project, that the installation of curbs will have a detrimental effect on the conveyance of
storm water in those areas and shall not be required.
However, in the four identified locations the pavement/turf transition, i.e. the edge
between asphalt and turf, shall be improved by establishing a uniform clean, defined edge
of pavement, and through the careful establishment of turf in those areas, including:
proper soil preparation, removal of stones from the soil; placement of additional top soil
as may be required; seed application and mulching with clean straw.
3. Landscaping and Grounds
A lengthy list of grounds and landscaping issues was presented by the HOA in the
"Traditions on the Monon Transition Report" of August 2010 (Attachment B). While a
number of the issues identified previously by the HOA have been fixed by the developer,
there were nine items identified in the HOA "Defects List" of 8/29/11. Since that list was
issued, there are six HOA items which remain unresolved.
Bldg 21 Sod missing Southwest corner by road
11 street NW Sod missing east end
All Grounds remove all plastic utility warning posts, white, yellow
North Retaining wall back fill with soil and sod 114 ft. x 8 ft.
New East Retaining Wall Insufficient adhesive on cap row
Monon entry sidewalk needs fill dirt on sides
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 4
Determination:
A. The missing sod in the area adjacent to Building 21was primarily a result of construction
for the overflow parking. Since completion of that construction the irrigation to that area
has been restored and the grass has begun to grow in. It is determined this area, between
Building 7 and Building 20, shall require a comprehensive re- seeding effort by the Pulte
including proper soil preparation, seeding and straw mulch application. This shall occur
following installation of curbing for the new parking area.
B. Other areas throughout the project that shall require a comprehensive re- seeding include:
the area surrounding the new parking lot adjacent to Building 9;
the common area in SE corner of traffic circle (between Buildings 14 and 15);
the lawn area along the eastern side of the subdivision, especially in the common area
east of Building 14;
the end area between Building 16 and 17;
the end area between Building 18 and Building 23.
C. Sod replacement was attempted by Pulte during the summer months in areas where mail
boxes were installed and areas where metal fencing was erected. It is determined that
replacement sod shall be installed by Pulte in areas where it was previously installed and
failed during the dry summer months.
D. Portions of the North Retaining Wall were reconstructed to correct outward shifting. The
HOA Defects List identifies "back fill and sod issues" which, upon inspection, are
unidentifiable and shall not require repair by Pulte.
E. Portions of the East Retaining Wall were reconstructed to correct outward shifting. The
HOA Defects List indentifies insufficient adhesive on the wall's cap row. Our inspection
found at least one cap stone has been removed and left unattached, showing a minimum
amount of adhesive used to complete this repair. Other stones were found to be loose and
easily moved.
The east wall cap row stones shall be repaired by Pulte, including a pre repair inspection
by City and Pulte, and cap stones re- adhered by Pulte per manufacturer's specifications.
F. The HOA has requested the area immediately adjacent to their Monon Greenway egress
walk be filled by Pulte, citing a safety issue. The egress walk is currently a seven foot
wide concrete walk with drainage tile. The filling of the Monon egress point, already
initiated by the HOA, shall not be a requirement of Pulte.
Fill dirt by the HOA must be removed by the HOA, or its installation approved by the
City Engineer and the Parks Department.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 5
4. Landscape Audit.
A separate landscape audit has been conducted by the Department of Community Services
beginning in November 2010, updated over the course of spring and summer 2011, and
finalized in October 2011. The DOCS audit was used to compare with a similar audit
performed by the Tradition HOA, dated August 2011. Full Landscape inspection reports can
be found in Appendix C.
A. Driveway landscaping Inspection report:
Species to match rest
of budding
Determination (Driveway plantings):
Replacement by Pulte of missing and dead driveway plant material for all buildings.
Replanting or replacement by Pulte of material noted as improperly installed.
Missing- Dead /Installed Improperly (II)
Building 1
3 grass
1 yew
Building 2
2 arborvitae
4 yew (3 11)
Building 3
2 arborvitae 6 grass
2 yew
Building 4
1 grass
1 yew
Building 5
4 grass
1 yew
Building 6
3 grass
Building 7
Building 8
4 grass
3 yew (3 II)
Building 9
3 grass
Building 10
2 yew (1 II)
Building 11
4 grass
Building 12
Building 13
3 arborvitae
1 bayberry
Building 14
2 arborvitae 2 grass
Building 15
2 arborvitae
Building 16
Building 17
2 arborvitae 1 grass
Building 18
1 yew (1 II)
Building 19
1 grass
1 yew
Building 20
2 grass
_Building 21
Building 22
1 yew
Building 23
TOTALS
13 arborvitae (M -D) 34 grass (M -D)
17 yew(9 M -D)(8 II) /1 bayberry(1 M -D) i
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 5
4. Landscape Audit.
A separate landscape audit has been conducted by the Department of Community Services
beginning in November 2010, updated over the course of spring and summer 2011, and
finalized in October 2011. The DOCS audit was used to compare with a similar audit
performed by the Tradition HOA, dated August 2011. Full Landscape inspection reports can
be found in Appendix C.
A. Driveway landscaping Inspection report:
Species to match rest
of budding
Determination (Driveway plantings):
Replacement by Pulte of missing and dead driveway plant material for all buildings.
Replanting or replacement by Pulte of material noted as improperly installed.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 6
B. Foundation landscaping Inspection report:
Building 13 2 yew; 1 spirea; 1 weigela
Building 14 2 holly; 4 boxwood; 1 burning bush
Building 15 —1 boxwood; 1 burning bush; 1 spirea; 1 maiden grass; 1 day lily
Building 16 3 yews; 3 spirea
Building 17 —1 weigela; 2 maiden grass
Building 23 —1 burning bush; 1 bayberry
Building 7 —1 barberry
Building 11 2 barberry
Building 20 —1 boxwood; 1 euonymus; 1 buming bush; 1 spirea
Determination:
Replacement by Pulte of missing and dead plant material installed with construction in 2009
or later; Buildings 23, 17, 16, 15, 14, and 13.
Replacement by Pulte of missing and dead plant material installed with buildings
constructed without irrigation system: Buildings 7, 11, and 20.
C. Common Area Inspection report:
NE Corner (bldg. 23 and 18)
1 crab apple
4 arborvitae
Funeral Home Parking area (bldg. 17 and 16)
5 arborvitae
C.A. SE Corner 3rd Ave and 10 Street (bldgs 14 and 15)
1 crab apple
Center Green north half (bldgs 11 and 7)
2 red maple
Building 8 (east facade, south corners)
1 oak
SE Corner (by Duke substation)
6 arborvitae (top of wall)
2 arborvitae (foot of wall)
Determination:
Replacement by Pulte of dead common area plant material noted above.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 7
D. Tree mulch.
It has been reported by the HOA and observed by DOCS that most shade trees and
ornamental trees have been over mulched, creating a problem described as "volcano
mulch which builds up a high level of mulch around the trunk, which encourages
insects and moisture related maladies.
The practice occurred while the HOA was operated by the developer, and has continued
under the management of the residents. The cost for repair is estimated to be twenty
dollars ($20) per tree.
Determination:
The cost for repair of 110 trees shall be split equally between the HOA and Pulte, amounting
to $1100 each.
E. Mulch bed restoration.
There are many areas across the property where drainage improvements were made at the
HOA's request, involving the removal of black corrugated drainage pipe was removed
from the gutter /downspout drainage system, then replaced with river stone and
downspout troughs.
Across the property are the remnants of this pipe removal which were left unfinished, in
many cases creating erosion channels, but, in general the result is an eight or ten inch
channel which needs to be backfilled and mulched.
Determination:
Pulte shall restore all mulch bed areas where the repair need exists, with a level of detail
indicating care for a quality outcome.
Upon completion of Landscape items A E above, the surety in place to ensure proper landscape
installation will be released.
5. Irrigation System.
A separate Irrigation System audit was conducted by the Department of Community Services
over the course of summer 2011, and finalized in October 2011. The DOCS audit utilized
the August walk -thru; the HOA report titled "Traditions on the Monon Irrigation Repair List"
(the List), personal field observation, the as -built irrigation plan prepared by Irrigation
Design Source for Pulte and general assistance from Automatic Irrigation, Fishers, Indiana.
The List submitted by the HOA following the August walk -thru detailed offered thirty-six
(36) specific recommendations for improvements to each of the forty -three (43) zones in the
system. The List was subsequently reviewed by Pulte who responded by resolving eighteen
(18) of the recommended changes, and concluding that many of the actions were HOA
responsibility, or not required by the PUD.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 8
The PUD ordinance for Traditions does not provide precise design specifications for an
irrigation system, nor does it require a plan submittal from which an objective evaluation can
be made.
The irrigation system audit is complicated by as -built plan which accounts for only forty (40)
zones of the forty -three (43) zones, and does not indicate the recent updates from the parking
construction, and/or subsequent resulting irrigation adjustments.
It is apparent from field inspection and review of the as -built plan the installed irrigation
system provides coverage to the vast majority of the property, including lawn areas and
landscape beds.
There are foundations plantings for buildings 7, 11 and 20 where irrigation conduit exists but
irrigation hardware was not provided. This is in contrast to a community standard for
landscaping foundation areas found at all other buildings within the property.
It is generally observed that the opportunity is without a location where a garden hose may be
used to water common area plants in parts of the property without irrigation, such as along
the eastern edge of the property where a number of plants have been lost likely to drought.
The neighborhood also appears to be challenged by a conflict between pet ownership and
availability of greenspace on the property. There are many areas where the turf and
shrubbery have been damaged by animal urine, as well as areas where animal feces had not
been cleaned. This HOA management issue conflicts with proper landscape maintenance
and degrades the positive effects from the irrigation system, in some cases obfuscates the
system effects completely, and in general undermines efforts to improve the quality of the
landscape.
Determination:
A. Irrigation system shall be installed by Pulte for foundation planting bed, Buildings 7, 11
and 20.
B. The Irrigation As -Built drawing shall be updated by Pulte to include the over -flow
parking areas, the irrigation adjustments, and missing zones, 41, 42 and 43.
C. The irrigation plan may need to be amended, following review of the updated Irrigation
As -built plan to ensure a high level of coverage in the amended areas noted above.
Upon completion of Irrigation System items A C above, the surety in place to ensure a proper
irrigation system installation will be released.
The Director's determinations in this letter may be appealed to the Carmel Board of
Zoning Appeals by you or any other interested party pursuant to Chapter 30.0 of the
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 9
Carmel Zoning Ordinance. Such appeals must be filed within thirty (30) days of issuance
of this letter or the determinations are fmal.
If you have any questions, or wish to discuss this matter further, please do not hesitate to contact
me at 571 -2422.
Very truly yours,
Michael Hollib
Attachments:
Copy:
Site map with building numbers
Attachment A Traditions HOA "Defects List"
Attachment B Traditions Transition Report Summary List of Issues
Attachment C Pulte Inspection Items Response Status
Attachment D DOCS Landscape inspection reports
Attachment E Irrigation Plan "Defects List"
DOCS photo documentation
Mayor James Brainard
John Molitor
Douglas C. Haney