HomeMy WebLinkAbout_Geotechnical Engineering Addendum 2011 1207.pdfNAP
December 7, 2011
PATRIOT ENGINEERING
and Environmental, Inc.
Engineering Value for Project Success
Consulting Environmental, Geotechnical
and Materials Engineers
Janelle Wood
Carmel Land Holding, LLC
222 West Colinas Boulevard, Suite 2100
Irving, Texas 75039
Re: Geotechnical Engineering Addendum Letter
The Barrington of Carmel (Formerly Mayflower Communities)
Guilford Road and 116th Street
Carmel, Indiana
Patriot Project No. 1-08-0647
Dear Janelle:
Based on review comments recently submitted to Patriot Engineering and
Environmental, Inc. (Patriot) for the above referenced project, we understand that
additional recommendations are needed for the above referenced project (Report dated
July 28, 2008). We now understand that a portion of the southwest wing of the building
will be over an existing pond that is to be backfilled. Additionally, we understand a
below grade parking structure is now to be located under the northwest portion of the
building.
Pond Backfill (Near Borings B-14, B-17, B-18, and B-21)
Recommendations were provided in our original report to aid in the design and
construction of the proposed facility, as well as the adjacent parking and roadway areas.
However, prior to construction, there are some initial construction concerns due to an
existing pond that is currently located within a portion of the west wing of the facility.
This pond will need to be completely drained of water and all soft and/or loose soils or
sediments must be properly removed prior to the backfilling of the pond. Upon
completion of the dewatering and removal of unsuitable soils, the pond should be
backfilled with well -compacted suitable structural fill material (See Section 5.3
"Structural Fill and Fill Placement Control" of our original report).
It should be noted that some limited settlement of new fill could possibly occur,
particularly in the areas of the deepest fill placement. Therefore to reduce any
potential post construction settlement of the facility, the grade raise fill (structural
backfill material) should be placed and given adequate time to settle prior to
construction. In order to determine when settlement has reached an acceptable level,
we recommend the implementation of a settlement monitoring program.
6330 East 751h Street, Suite 216, Indianapolis, Indiana 46250
(317) 576-8058 • (317) 576-1965 FAX • www.patrioteng.com
Offices in Indianapolis, Evansville, Fort Wayne, Lafayette, and Terre Haute, IN,
Louisville, KY, Dayton / Cincinnati, OH and Nashville, TN.
The Barrington of Carmel Carmel Land Holding, LLC
Carmel, Indiana Patriot Project No.: 1-08-0647
Below Grade Parkinq Structure
Foundations
The proposed parking structure is to be located beneath the northeast portion of the
facility (Borings B-3, B-5, B-6, B-7, and B-10). We assume that this below grade
structure will bear at a depth of approximately 10 to 12 feet below the existing ground
surface.
The below grade parking structure can be supported on spread footings bearing on the
stiff to very stiff sandy clays, or on new well -compacted structural fill overlying the same.
However, some undercutting of soft or unsuitable soils may be required at some
locations. These footings should be proportioned using a net allowable soil bearing
pressure not exceeding 3,000 pounds per square foot (psf) for column footings or 2,500
psf for strip (wall) footings. For proper performance at the recommended bearing
pressure, foundations must be constructed in compliance with the recommendations for
footing excavation inspection that are discussed in Section 5.0 "Construction
Considerations" of our original report; which indicates careful field control during
construction by Patriot to confirm that the exposed material is capable of supporting the
design bearing pressure and minimize the post construction settlement potential.
In using the above net allowable soil bearing pressures, the weight of the foundation and
backfill over the foundation need not be considered. Hence, only loads applied at or
above the minimum finished grade adjacent to the footing need to be used for
dimensioning the foundations.
We estimate that the total foundation settlement should not exceed approximately 1 inch
and that differential settlement should not exceed about % inch. Careful field control
during construction is necessary to minimize the actual settlement that will occur.
Groundwater Considerations
Groundwater was encountered at varying depths during our original field activities. Due
to this, it is possible that significant dewatering will be necessary during the excavation
and construction of the below grade parking structure. We recommend that the
groundwater table be lowered to a minimum of 3 feet below the bottom of the
excavation.
Page 2
The Barrington of Carmel Carmel Land Holding, LLC
Carmel, Indiana Patriot Project No.: 1-08-0647
We recommend that a perimeter drainage system be provided around the below grade
walls (outside of the footings) and an underslab drainage system be installed beneath
the entire below grade parking area. These drains may flow by gravity to a sump or to a
storm sewer (if possible). The perimeter drain should consist of a 6 inch slotted,
corrugated pipe surrounded by at least 6 inches of INDOT No. 5 stone. The stone
should be completely wrapped in a drainage geotextile consisting of Mirafi 140N or
an equivalent, in order to keep the stone clean or avoid clogging of the drainage layer
with silt and sand. In addition, the zone adjacent to the below grade walls should be
backfilled with a minimum 2 feet wide zone of free draining granular material (less
than 3% by weight passing the No. 200 sieve) to prevent the buildup of hydrostatic
pressure behind walls. Above this free draining material, a 2 feet thick clay fill should
be compacted at the surface to prevent surface water infiltration. The clay fill should
be compacted to a minimum 90% of the maximum Modified Proctor dry density
(ASTM D-1557).
The below grade slab should be underlain by a 9-inch layer of open -graded INDOT
No. 5 stone that will serve as a drainage blanket beneath the entire basement area.
We recommend that a system of perforated drain pipes, which could drain by gravity to
an outlet or sump pit, be installed at a maximum spacing of 50 foot on centers into the
granular fill. The basement drains consist of 4 inch slotted corrugated pipes surrounded
by at least 6 inches of No. 5 stone. The stone should be completely wrapped in a
drainage geotextile consisting of Mirafi 140N or equivalent. The drain tiles may be flat
lying or sloped to allow for gravity flow into the sump pits. The underslab drainage
layer should not extend under the basement walls in order to limit the water seepage to
only that come through the basement slab area. The underslab drainage and the
perimeter drainage should be independent of each other. It will be necessary to place a
geotextile fabric separator between the subgrade and the gravel drainage layer to
prevent clogging of the drainage layers.
Lateral Earth Pressures
The magnitude of the lateral earth pressure is dependent on the method of backfill
placement, the type of backfill soil, drainage provisions and whether or not the wall is
permitted to yield during and/or after placement of the backfill. When a wall is held
rigidly against horizontal movement, the lateral pressure against the wall is greater
than the "active" earth pressure that is typically used in the design of free-standing
retaining walls. Therefore, rigid walls should be designed for higher "at -rest"
pressures (using an at -rest lateral earth pressure coefficient, KO), while yielding walls
can be designed for active pressures (using an active lateral earth pressure
coefficient, Ka).
Page 3
The Barrington of Carmel Carmel Land Holding, LLC
Carmel, Indiana Patriot Project No.: 1-08-0647
The below grade parking structure walls proposed for the project site are expected to
be rigid walls. Therefore, provided a clean well -graded granular material is used
for backfill, a total soil unit weight (yt) of 125 pcf, an at -rest lateral earth pressure
coefficient (Ko) of 0.45, an active lateral earth pressure coefficient (Ka) of 0.30, and a
passive lateral earth pressure coefficient (Kp) of 3.4 can be used for calculating the
lateral earth pressures. An equivalent fluid active pressure of 38 psf per foot of wall
height is recommended for design purposes in conditions where the top of the wall is
allowed to yield during backfilling. However, if the top of the wall will be fixed, an
equivalent fluid at -rest pressure of 57 psf per foot of wall height is recommended for
design purposes. This equivalent fluid pressure would increase linearly from zero (0)
psf at the ground surface, to a maximum at the base of the wall.
When calculating passive earth pressure, the upper 3 feet of soil should be
neglected. Note also that the wall must move laterally about 0.04H (where H equals
the wall height) in order for passive earth pressures to be fully developed. In most
cases, passive earth pressures behind walls should not be considered.
If hydrostatic pressure due to water build-up against the wall is anticipated, the
equivalent fluid pressure method will be changed for the soil. Rather, the lateral earth
pressure should be computed using a total soil unit weight of 125 pcf above the
highest anticipated water level, and a buoyant soil unit weight of 63 pcf below the
highest anticipated water level. The earth pressure coefficient indicated above should
be used above and below the water level to compute the lateral earth pressure. The
hydrostatic pressure should be computed using the highest anticipated water level.
The lateral earth pressure and hydrostatic pressure should be added to obtain the
total lateral pressure on the wall.
It has been assumed that the static weight per axle of equipment utilized for the
compaction of the backfill materials adjacent to the below -grade wall will not exceed
2 tons per axle for non -vibratory equipment and 1 ton per axle for vibratory
equipment. All heavy equipment, including compaction equipment heavier than
recommended above, should not be allowed closer to the wall (horizontal distance)
than the vertical distance from the backfill surface to the bottom of the wall.
The shear resistance against base sliding can be computed by multiplying the
minimum normal force on the base of the footing times a coefficient of friction of 0.3.
Lateral earth pressures can be computed as discussed above. A minimum factor of
safety of 1.5 is recommended for sliding stability.
Page 4
The Barrington of Carmel Carmel Land Holding, LLC
Carmel, Indiana Patriot Project No.: 1-08-0647
Summary of Lateral Earth Design Pressures
Soil Unit
Weight
g (Yt)
(pcf)
At -Rest
Coefficient
(Ko)
Active
Coefficient
(Ka)
Passive
Coefficient
(Kp)
Coefficient
of Friction
Minimum
Factor of
Safety
125
0.45
0.30
3.4
0.3
1.5
We appreciate the opportunity to provide this Geotechnical Engineering Addendum
Letter. If you have any questions regarding this letter, please do not hesitate to contact
our office.
Respectfully submitted,
Patriot Engineering and Environmental, Inc.
fit�lo
Eric Wenz 7
Geotechnical Engineer
William D. Dubois, P.E.
President
',,j III iflII�11.,
\ 1� LJAf�fi
-A 4 -
60018167 ; a -
= o STATE OF I� -
�O
��-•rNp pt�PS' � .
Page 5