January 7, 2013
Mr. Gary R. Duncan
City of Carmel
Department of Engineering
One Civic Square
Carmel, Indiana 46032
Re: The Bridges Commercial Block, Phase I - Comment Review
Project No. 201001114
Dear Mr. Duncan:
Thank you for the review of the proposed project. Below are your review comments that were received on
November 30, 2012, as well as the review comments that were received from your office on November 19,
2012, followed by our firm's response in italics.
CONSTRUCTION DRAWING REVIEW COMMENTS
1. Please omit Sheets LS100- LS101, Landscape Plan; and Sheet LT100, Site Lighting from construction
sets to be submitted for review by this department. The Department of Engineering does not have
approval authority over landscape plans or photometric plans. Please remove the titles for the
Landscape Plan, Landscape Details, and Site Lighting from the Sheet Index.
The landscaping and lighting plans have been omitted from the plan set.
2. Will this development be platted?
No, this development will not be platted.
3. Please only show the City's future road improvements as "existing" on C100 and C200 • C500. Please
remove all existing conditions from these sheets.
The City's future road improvements have been incorporated into the plans as an existing condition as
directed.
4. Please align the entrance on Springmill Road with the opposing approved entrance for the LDS
Temple on Springmill Road.
The entrance on Springmill Road has been aligned with opposing approved entrance for the LDS
Temple.
7260 Shadeland Station Indianapolis, IN 46256 -3957 TEL 317.547.5580 FAX 317.543.0270 mow structurepoint.com Q
AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 2
5. A straight arrow should be shown for through traffic across Springmill Road at the Springmill Road entrance.
A straight arrow has been shown for through traffic across Springmill Road at the Springmill Road entrance.
6. There were two private roundabouts shown in this portion of the concept plan approved in the PUD, along the
north -south road. Are these roundabouts required by the PUD?
No, these roundabouts were only conceptual in nature and are not required by the PUD.
7. Why are curbs not shown for the southern portions of this project? Is this for future parking lot expansions?
Curbs are not shown for future expansions of the parking lot.
8. Is the north entrance on Illinois Street consistent with what is approved in the PUD?
Yes, the northern Illinois Street entrance is consistent with the approved entrance in the PUD.
9. The southern private roads intersection should be changed to have a more generous curve, allowing for better
site distance at this intersection.
The intersection has been revised to show a larger radius on the north /south road. The stop bar has also been
moved closer to the intersection that allows for better site distance.
10. Please indicate the existing and proposed right -of -ways on Illinois Street.
The existing and proposed right -of -ways have been labeled on Illinois Street.
11. What are the plans for the construction of the multi- access path, along Springmill Road and Illinois Street, to
the southern entrances for this project?
The multi -use paths along Springmill Road and Illinois Street will be built once the rest of the development is
constructed.
12. Please label the line -types in the legends.
The line -types have been labeled in the legends. If they are not labeled in the legends, they are labeled in plan
view due to the limited number of line - types.
13. Why are curbs not shown around the CVS Pharmacy? City standards require curbing in all parking areas,
except when disallowed for storm water quality treatment.
The tenant prefers not to curb the sidewalk along the frontage of the store to allow for better maneuverability
for customers with shopping carts. However, the landscape islands around the building and parking lot is
curbed and wheel stops are being provided along the flush sidewalk.
14. On C200, the note for the entrance on 116th Sheet refers to Landscape Plans. Details for this entrance were not
included on the Landscape Plans. Please submit details for this entrance with the construction plan set.
An architectural rendering of the bridge and water feature has been provided with this submittal. Contours
have also been provided in the plan set for the water features.
201001114
AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 3
15. All four entrances to the site from the public right -of -way shall be City Standard concrete Commercial
Driveways.
The Illinois Street and Springmill Road entrances that are being constructed as a part of this project have
been specified as the City Standard Concrete Commercial Driveways. However, the entrance from 116th
Street is being constructed as a portion of the 116th Street Roundabout project and specifies this entrance to be
asphalt.
16. The maximum allowable commercial driveway width is 30 -feet. Please change the southern entrances per this
standard.
The southern entrances have not been modified to a maximum width of 30 feet because they require dedicated
left turn lanes.
17. Please indicate the removal of curb to the nearest joint for the construction of the two entrances on Illinois
Street.
The demolition plan has been revised to specify that the curb shall be removed to the nearest joint for the two
entrances on Illinois Street.
18. Please label the curb return radii for the Springmill entrance.
The curb radii have been labeled on the Springmill Road Entrance on Sheet C201 and C202.
19. Please indicate the milling and resurfacing of the entire width of Springmill across the limits of the auxiliary
lanes on Springmill.
The plans have been revised to show that half of Springmill Road is to be milled and resurfaced across the
limits of the auxiliary lanes on Springmill Road. It is understood that the other half of the road will be milled
and resurfaced as a part of the LDS Temple entrance construction.
20. On C202:
a. Acceleration/Deceleration Dimension Plan: Please indicate the 3 -foot shoulder made of #73
at a 6 -inch depth.
The 3-foot shoulder made of #73 stone at a 6 -inch depth has been indicated.
b. Acceleration/Deceleration Dimension Plan: Please indicate the subsurface drain, including
the connection to the storm sewer system.
The subsurface drain has been shown and it has been specified that the end shall be capped
and marked for future connection to the future storm sewer system.
c. Please indicate the lane markings on Springmill Road, including the double yellow
centerline, solid white lane line, and edge markings.
The lane markings have been indicated as directed.
d. An end section is needed for the pipe under Springmill Road, south of this entrance.
201001114
AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 4
The pipe south of the Springmill Road entrance that runs under Springmill Road has been
specified to be extended as required and an end section to be provided.
e. Please provide more information regarding the grading and drainage along Springmill Road
at this entrance, along the auxiliary lanes. Is a swale being installed or will this area sheet flow
into the site?
For this phase of the development, the drainage along Springmill will continue to sheet flow
onto the site as it currently does.
f. Auxiliary Lane Cross Section: Please indicate the stone is #73.
The Auxiliary Lane Cross Section has been revised to indicate the stone is No. 73.
g. Auxiliary Lane Cross Section: Please label the cross slope.
The cross slope has been labeled on the Auxiliary Lane Cross Section.
21. All pavement markings in the right -of -way shall be thermoplastic.
All pavement markings within the right -of -way have been specified as thermoplastic.
22. Please show the proposed power poles on Springmill on C300 and C301.
The latest known locations of the power poles that are being relocated by Duke Energy have been shown on
the Utility Plan.
23. Sheet C300:
a. Please include storm and sanitary in the legend.
The storm and sanitary sewer line -type has been shown in the legend.
b. Are the sprinkler control valves west of CVS located within the right -of -way?
The existing sprinkler control valves west of CVS are located within the right -of -way. It is
unclear what irrigation system these valves serve.
c. Are the pipes shown under Springmill and 116th Streets existing or proposed? Are these
being accommodated into the site?
The pipes that currently exist are shown on Sheet C101 -C102 are existing. However, the
pipes shown on the other plan sheets are the proposed pipes for the 116th Street Roundabout.
Once the 116th Street project is complete, no offsite drainage will be directed toward the site.
The pipes that cross Springmill Road will continue to drain through the site.
d. Please show the existing subsurface drain under the curb along Illinois Street.
The existing subsurface drain under the curb along Illinois Street has been indicated as an
approximate location.
201001114
AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 5
24. Please indicate the flow directions along the swale, through the site, directing all drainage from this project to
the south and the invert elevations of the culverts along the swale.
The flow directions and invert elevations of the culverts on the southern portion of the project have been
indicated on Grading Plan.
25. Please provide the MFPG and MLAG for the proposed buildings. The MFPG and the MLAG shall be a
minimum of 2 feet above the 100 year flood elevation of the detention facility and I foot above the local
flooding with the inlets plugged.
The MFPG and MLAG for the proposed buildings have been indicated on the Grading Plan.
26. Please indicate the on -site flood routing. The flood route shall be based on all inlets plugged during a 100 -yr
rain event.
The on -site flood routing has been indicated on the Grading Plan.
27. Please provide a drainage summary, as required per the Stormwater Technical Standards 102.02 xi.m.
A drainage summary has been provided on the Grading Plan.
28. On C400 -C401, please include contours for the southern portion of this project.
Contours have been provided for the southern portion of the project.
29. On C402, a note refers to a previously approved detention pond and mass grading plan. The Engineering
Department has no record of this being approved or constructed. In order for this project to progress, all
downstream stormwater facilities shall be constructed.
This comment has been duly noted and the Mass Grading Plans have been revised and resubmitted in order to
obtain approval.
30. Landscape mounds were previously planned along Springmill Road, to the south. When will these be
constructed? Please indicate on the plans
The landscape berms will be constructed at the time of construction of the first building within the Office and
Residential Use Block per the PUD.
31. Please include a Maintenance of Traffic Plan for work within the right -of -way on the Thoroughfare Plan
roads.
Maintenance of Traffic Plan for the work within the right -of -way has been provided.
32. The Stop Sign Detail on C700 must meet the MUTCD standards.
A note has been provided on the detail that indicates that all stop signs shall comply with the MUTCD
standards.
33. Inclusion of City Standard Drawing 10 -32 is not necessary.
This detail has been provided for the auxiliary lane construction along Springmill Road.
201001114
AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 6
34. Please include the City Standard Drawing for Commercial Driveways.
The City Standard Drawing for Commercial Driveways has been included in the plans.
35. Improvements at the 116th Street and US31 intersection were committed by the developer as a part of the
PUD approval. What is the trigger for these improvements?
The traffic study indicates that this phase of the development does not trigger the need for intersection
improvements at 116th Street and US 31.
36. General Comments
a. This project is subject to the City's Storm Water Management and Storm Water Quality
Ordinances.
This comment has been duly noted and no action is required.
b. Please add the following note to the drawings: "IF IT WILL BE NECESSARY TO
RELOCATE EXISTING UTILITIES, THE EXPENSE OF SUCH RELOCATION SHALL
BE THE RESPONSIBILITY OF THE DEVELOPER. ALL UTILITY POLES SHALL BE
LOCATED WITHIN ONE FOOT OF THE PROPOSED RIGHT -OF -WAY.
The note above has been added to the plans as indicated.
37. All swales on site must have subsurface pipe installed. Pipe to conform to requirements of Storm Water
Technical Standards Manual and shall be double wall, Hancor H1 -Q pipe or equivalent.
A variance was granted for the Mass Grading plans to allow for temporary swales to be constructed without
requiring subsurface drains. The swales that are depicted are temporary and are similar in nature to the
swales that will be constructed for the Mass Grading phase of the project, therefore no subsurface drains have
been provided.
GENERAL INFORMATION
38. These comments represent the Department of Engineering's first review of the development plans for this
project.
39. We request that all responses to our comments be provided in writing and be accompanied by a drawing
reflecting the requested revisions. Failure to provide written responses may result in the delay of the review
process.
40. It is critical that this office be made aware of all modifications made on the plans being resubmitted,
particularly if any such changes are considered "new" or fall outside of our previous reviews. Please provide
revised plans including all revisions. Please notify us of any changes and specifically state any changes,
including changes resulting from Plan Commission, BZA or other committee meetings.
41. We have engaged Crossroad Engineers, PC to review all drainage plans and drainage calculations submitted
to this office for review. If you have not already done so, please provide a set of drainage plans and
calculations to their office for review. We will share Crossroad's comments as they are received.
42. Final drawings will not be approved for construction until:
201001114
AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 7
a. All Engineering Department and Utility Department and Hamilton County Surveyor issues
have been resolved.
b. All bonds and performance guarantees are posted.
c. All Board of Public Works and Safety approvals and any other governing agency approvals
(if required) are obtained.
d. All off -site easements necessary to install utilities to serve the development are secured.
e. SWPPP is approved.
f. All fees are paid.
43. The Department reserves the right to provide additional comments based upon subsequent reviews.
44. An approved Storm Water Management Permit is required prior to commencing any earth disturbing activity.
Please contact Mr. John Thomas regarding storm water quality requirements.
45. An approved right -of -way permit is required prior to commencing any work in the public right -of -way and for
construction equipment access from the City's right -of -way.
46. If it will be necessary to relocate existing utilities, the costs for such relocation shall be borne solely by the
developer. Any utility poles requiring relocation shall be relocated to within one foot of the outside edge of the
proposed right -of -way.
47. The Department requires that the construction drawings be developed in accordance with the City of Carmel
digital submission standards and that all required submittals for primary plat, secondary plat, and construction
drawings be made. The digital files must be submitted to the Department of Engineering prior to the approval
of the construction plans. Please contact the City GIS Department for the requirements.
48. Jurisdictions:
a. The project site is located within current City of Carmel Corporate Limits.
b. Perimeter Street and Right -of -Way -City of Carmel (Illinois Street, Spring Mill Road, I 16th
Street)
c. Water -City of Cannel Utilities
d. Sanitary Sewers -City of Cannel Utilities
e. Storm Sewers /Drainage -City of Carmel
f. Legal Drains - Hamilton County Surveyor's Office.
49. Drawings submitted for approval:
a. The design engineer must certify all drawings submitted for final approval
b. This office will require 9 sets of drawings for approval after all issues have been resolved.
The drawings will be stamped as approved and signed by the City Engineer and by Carmel
201001114
AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 8
Utilities. The Owner will receive 3 sets, one of which must be maintained on the construction
site at all times. If this project is subject to review and approval by the Hamilton County
Surveyor's Office, a total of II sets will be required for final approval.
50. Carmel Utilities will provide separate reviews of this project for water issues. Please assure that copies of all
drawings are sent to: Paul Pace Paul Arnone Carmel Utilities Distribution Carmel Utilities Collection
51. Carmel Utilities subscribes to "Holey Moley" who should be contacted directly for all water main locations.
52. The following items will be sent electronically upon request regarding this correspondence and project:
a. Project Approval Checklist
b. Performance/Maintenance Guarantees
c. Utility Jurisdictions /Right of Way Permits
d. Availability (acreage) Fees
53. A schedule for Board of Public Works and Safety meeting dates and agenda deadlines will be sent
electronically for your use upon request. Please use the Engineering Department deadlines for submissions to
the Board.
54. Any submission to the Board requires prior approval by the Carmel Clay Plan Commission and/or the Board
of Zoning Appeals (if applicable) and completion of review by the Technical Advisory Committee. All
written requests to be placed on the Board's agenda must include the appropriate Docket Number and the date
(or dates) of approval by the Plan Commission and/or the Board of Zoning Appeals (if applicable).
55. Water Availability and Sanitary Sewer approval from the Board will be required. This is an EDU approval
based upon the proposed use of the site. Reference Items #33 to #35 below for additional details /explanations.
Please note that if an entryway or other irrigation system is planned for this development, additional Water
Availability Approval from the Board will be required and additional Water Connection Fees will be assessed
based upon the size and usage of the system as determined by the Director of Carmel Utilities.
Comment Nos.38 through 55 have been duly noted.
56. Commercial Curb Cut Approval. Please provide 8.5 x 11 exhibits with the request for approval. Provide all
pertinent information including lane widths, overall width, radii, lane markings, location of opposing drives or
streets, relationship to the location of previous curb cut, etc.
A Commercial Curb Cut Approval will be applied for following this submittal.
57. Temporary Construction Entrance Approval. It appears the construction entrance is planned at the location of
a permanent curb cut. Therefore Board approval is not required.
58. The installation of any permanent, privately owned and/or maintained improvement (signs. decorative street
signs, walls, streetlights, etc.) within dedicated right of way or dedicated easements requires the execution of a
Consent to Encroach Agreement between the Owner and the City of Cannel. Such agreements are executed by
the Board of Public Works and Safety. The City Engineer may approve irrigation system agreements.
59. Secondary Plat approval if applicable. All performance guarantees must be posted prior to submission of
secondary plats for Board of Public Works and Safety approval.
201001114
0 AMERICAN STRUCTUREPOINT, INC.
City of Carmel
January 7, 2013
Page 9
60. Dedication of right -of -way if not platted. This is based upon the City of Carmel 20 -Year Thoroughfare Plan
requirements. Dedication documents are available upon request. Please be advised that all Right -of -Way
Dedications must be accompanied by a Sales Disclosure Agreement completed by the owner for the property
being dedicated to the City. The dedication document cannot be recorded without a completed Sales
Disclosure. The form is available upon request.
61. Any open pavement cuts of City right -of -way will require Carmel Board of Public Works and Safety
approval.
Comment Nos. 57 through 61 have been duly noted.
BONDING REQUIREMENTS
62. Please contact Mr. Dave Barnes to review performance guarantee requirements. Please contact Mr. John
Duffy to review water and sanitary sewer bonding requirements.
63. The amount of the Performance Guarantee is based upon a certified Engineer's Estimate for 100% of the cost
of labor and materials to construct the individual improvements, to be provided by the design engineer. Please
provide detailed Engineer's Estimates for each improvement including quantities, unit costs, pipe sizes, and
materials, etc.
64. Upon completion and release of individual Performance Guarantees, a three -year Maintenance Guarantee will
be required (see Street Sign comments above). The Maintenance Guarantee amount is based upon 15% of the
Performance amount for Streets and Curbs and 10% of the Performance amount for all other improvements.
65. Performance Guarantees may be Performance or Subdivision Bonds or Irrevocable Letters of Credit.
66. Please reference the available enclosures for more detailed explanation of our procedures.
Comment Nos. 62 through 66 have been duly noted.
RIGHT OF WAY PERMIT AND BONDING
67. Any work in the dedicated right -of -way will require an approved Right -of -Way Permit and a License &
Permit Bond.
68. The bond amount is determined by our Right -of -Way Manager. However, if the work is included in the scope
of work of a required and posted Performance Guarantee, the Performance Guarantee may be used to satisfy
the bond requirements of the Right -of -Way Permit.
69. Please contact our Right -of -Way Manager, Fred Glaser, to arrange right -of -way permitting and bonding.
Comment Nos. 67 through 69 have been duly noted.
AVAILABILITY AND CONNECTION FEES
70. We defer to Carmel Utilities regarding this issue.
71. If an entryway or overall site irrigation system is planned for this development, additional Water Connection
Fees will be assessed based upon the size and usage of the system and upon the recommendations of the
Director of Carmel Utilities.
201001114
+1 AMERICAN STRUCTUREPOINT, INC,
City of Carmel
January 7, 2013
Page 10
72. These fees are required to be paid prior to final approval of construction plans by Engineering and prior to
issuance of building permits by Building Codes Services. Please confirm these fees and calculations with
Cannel Utilities.
Comment Nos. 70 through 72 have been duly noted.
If you have any questions, please feel free to contact our office at (317) 547 -5580, or reach me by email at
ataylor @structurepoint.com.
Very truly yours,
American Structurepoint, Inc.
Andrew R. Taylor, EI, CFM, LEED AP
Project Engineer
ART :alo