HomeMy WebLinkAboutFirst Group Eng/ENG/Addl Serv 2/$22000/Strutural Replacement Williams Creek ■
Firct Group Engineering, Inc.
Engineering-2013
Appropriation 4211-4462300; P.0. 1126575
Contract Not To Exceed 522,000.00
Q op
ADDITIONAL SERVICES AMENDMENT TO � �o
AGREEMENT FOR PURCHASE OF GOODS AND SERVICES
THIS AMENDMENT TO THE GOODS AND SERVICES AGREEMENT ("Agreement") entered into by and
between the City of Carmel and First Group Engineering, Inc. (the "Vendor), as City Contract dated October 11,
2011 shall amend the terms of the Agreement by adding the additional services to be provided by Vendor consistent
with the Scope of Work attached hereto and incorporated herein as Exhibit "A". Furthermore, the terms of the
Agreement shall be amended to include the E-verify requirement as stated in Indiana Code § 22-5-1.7 et seq., which
is attached hereto and incorporated herein as Exhibit "B", as well as the required E-verify Affidavit, attached hereto
and incorporated herein as Exhibit "C". Also, pursuant to I.C. § 5-22-16.5, Vendor shall certify that in signing this
document, it does not engage in investment activities within the Country of Iran. The terms and conditions of the
Agreement shall not otherwise be affected by this Additional Services Amendment and shall remain in full force and
effect.
IN WITNESS WHEREOF, the parties hereto have made and executed this Amendment as follows:
CITY OF CARMEL, INDIANA First Group Engineering, Inc.
by and through its Board of Public
Works and Safety
By By:
l n
James Brainard, Presiding Officer Authorized Signature
Date:
/, ��'nn15 (�)- �6h
U/�� • �. Printed Name
Mary Ann :urke, Member /�
Date: ,3— 6 — /3 d2.4
Title
•„
Lori S. Watsor, ember FID/TIN: 35-1693178
Date: -37r0 I t -a,
Last Four of SSN if Sole Proprietor:
ATTEST:
•,� ( 1 Date: — 7 — t 3
Al it :116,.
pia Cordray, IAMC, irk-Treasurer
Date: /3
�lV...},y.ll,l(Y11GY-.Jnm'IAWuEl�ullVinlS,,..((iW.S.�J10.f11:0.(ll:l'EN flNEE0.M4-AYT,E�'"3011�11 Y..\f�
RS - pe p C
CITY 40F UATNIEL
January 30. 2013 JAMES BR INA D, MAYOR
Mr. Chuck Sims
First Group Engineering Inc.
5925 Lakeside Blvd.
Indianapolis, IN 46278
RE: Additional Service Amendment#2, PO #26575
Dear Mr. Sims:
As we discussed, the City of Carmel has a need for additional professional services and pursuant to our current
contract with First Group, dated October 11, 2011. I have requested and received from you the proposed scope of
services and fee estimates for the following work task:
Additional Service Amendment#2— Structure Replacement over Tributary of Williams Creek at
Spring Mill Rd,South of 106'"Street
Engineering Services, Design Supplement
Not to Exceed: $22,000.00
Per our contract procedural requirements, I hereby approve these Additional Professional Services estimates,and
request that the Board of Public Works ratify the above referenced Contract Amendment.
PLEASE NOTE
Please be advised that "Additional Services" performed on City contracts must be billed separately from the original
contract and other additional services. More importantly,the invoice must reference the appropriate Additional
Service#and P.O. if shown above. Invoices received without the Additional Service#referenced will be returned
for proper identification. Thank you for your continued assistance in providing the City of Cannel with your
professional, quality services. If you should have any questions, please give me a call.
Sincerely,
Michael T. McBride, P.E.
City Engineer
wit
Rc�€.��ld approved by:
DEPARTMENT (Jr ENGINEERING C. Engelki g
ONE Civic SQUARE} CARMEL, IN 46032 OFFICE 317.571.2441 FAN 31757p�4�yor ofAdministra ton
EMAIL engineeringi2(cannel.in.gov
•
Consulting Engineers
s
!Y" 5925 Lakeside Blvd.
II Indianapolis,IN 46278
a�l"W )1610€„1:, PFax ((17) 290-9549
Fax (317) 290-9560
ENGINEERING. INC.
6949 Kennedy Avenue
January 16, 2013 unu F
Hammond, IN 46323
Phone(219) 844-6752
Fax(219)844-6795
Mike McBride P.E. City/Traffic Engineer
City of Cannel
One Civic Square
Carmel, Indiana 46032
Re: Scope of Services and Fee Proposal for realignment and hydraulic modeling
Road Work and Structure Replacement -
Unnamed Tributary of Williams Creek
Spring Mill Road, South of 106th Street
Carmel, Indiana
Dear Mr. McBride:
Due to the revisions to the horizontal and vertical alignment, structure, path and lack of
hydraulic information from the Christopher Burke stream modeling, additional work is
proposed for this project.
Please find attached our summary of the proposed added work, estimated design costs
and man-hour justification breakdown. Upon your approval we will finish the plans and
prepare a sub-agreement with USI for the stream modeling so they can complete the
hydraulic analysis for the permitting.
If you have any questions or comments please call me anytime at 317-216-7705,
extension 209 or 317-372-7308 (cell).
If email is preferred: csimsZ,,firsteroupengineerine.com
Sincerely,
ilak 97/1
Chuck Sims, Vice-President
Transportation Design Services
First Group Engineering Inc. m
STREETS—HIGHWAYS—TRAFFIC—STRUCTURES—WATER—SEWER—SURVEYING—RIGHT-OF-WAY SERVICES
ACTIVE MEMBERSHIPS:
.°� wowusaaerr INTERNATIONAL
mt.
®T.NAO[i�TOK n ua.WE2 )GFislaffeoWL , 7RI OIWAY
20 OFV1m5 G.1._lg•��. ����• UNO SI#NEYMI9.IML.
p. Road and Drainage Structure Work for
,"1!t •, Unnamed Tributary of Williams Creek South of 106th Street
. rti0 IQ>7/2.,.. City of Carmel, Indiana
January 14, 2013
SUMMARY
The proposed work items below are for a supplemental for realigning Spring Mill Road to minimize right of
way taking,additional channel survey for stream modeling of the tributary under Spring Mill Road,stream modeling
for the tributary under Spring Mill Road and adding an off roadway multi-use path along Spring Mill.
The proposed work would include:
• Additional Topographical Survey up and down stream of the proposed Structure for stream modeling
• Approximately 890 feet of horizontal and vertical realignment of Spring Mill Road and add path
• Approximately 200 feet of vertical realignment of the private drive just south of the unnamed tributary east
side of Spring mill Road.
• Revise location of concrete culvert under Spring Mill Road
• USl to prepare stream modeling for tributary
Estimated Design Costs:
First Group Engr:
Plan revisions and survey $10,500.00
USI Consultants:
Stream modeling, structure size and type
and coordination with Christopher Burke(CB) $6,500.00
Coordination with County for determination of floodway storage (if requested by City) $1,000.00
Additional coordination with the County $1,000.00
If base model is NOT provided by CB (if needed basis) $3,000.00
TOTAL $22,000.00
See attached man hours fees and email from UST identifying their portion of the work to complete.