March 21, 20
JA.%ms BP MN_ARD, MAYOR
Mr. George Lukas
Landwater Group, Inc.
1414 Franklin Street
Columbus, IN 47201
RE: McDonald's Restaurant 750 East Carmel Drive remodel- Project Review #2
Dear Mr. Ochs:
The City received your construction plans on March 7, 2013 in response to the City's comment letter dated
August 30, 2012. We offer the following additional comments:
CONSTRUCTION DRAWING REVIEW COMMENTS
I. Previous Comment 4 of a letter dated August 30, 2012. Please omit Sheet C6.0p, Landscape
Plan; and Sheet C7.0p, Site Lighting Plan, from construction sets to be submitted for review
by this department. The Department of Engineering does not have approval authority over
landscape plans or site lighting plans. The Department repeats this comment. In
addition, please omit Sheet C6.1, Landscape Details.
2. Previous Comment 6 of a letter dated August 30, 2012. Please add the following note to the
drawings: "IF IT WILL BE NECESSARY TO RELOCATE EXISTING UTILITIES, THE
EXPENSE OF SUCH RELOCATION SHALL BE THE RESPONSIBILITY OF THE
DEVELOPER. ALL UTILITY POLES SHALL BE LOCATED WITHIN ONE FOOT OF
THE PROPOSED RIGHT -OF- WAY." The Department repeats this comment.
3. Previous Comment 7 of a letter dated August 30, 2012. Please add note stating "NO EARTH
DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN APPROVED STORM
WATER MANAGEMENT PERMIT" to construction set. The Department repeats this
comment.
4. Previous Comment 9 of a letter dated August 30, 2012. Please clearly mark all construction
limits. Please clearly mark the construction limits on all plan sheets.
5. Previous Comment 16 of a letter dated August 30, 2012. Please indicate a 50 -foot half right -
of -way along Carmel Drive consistent with the Thoroughfare Plan. The Department
repeats this comment.
6. Previous Continent 18 of a letter dated August 30, 2012. City standard Commercial Drive
entrances shall be provided. Please indicate on the plans and provide the City standard
Commercial Driveway and Depressed Curb details. The Department repeats this
comment.
7. Previous Comment 22 of a letter dated August 30, 2012. All sidewalks within the public
right -of -way shall meet the City standards. Please provide the City standard sidewalk detail.
The Department repeats this comment.
8. Previous Comment 23 of a letter dated August 30, 2012. All proposed ADA ramps within
the public right -of -way shall meet the INDOT specifications for ADA ramps. Please provide
the INDOT standard details. The Department repeats this comment.
9. Previous Comment 24 of a letter dated August 30, 2012. City standard curb is required for
all curbing. Please indicate on the site plan, include the appropriate City standard curb
details, and the City's Curbing Policy in the plans. The Department repeats this comment.
10. Previous Comment 26 of a letter dated August 30, 2012. Curb along Keystone Way shall be
demolished to the nearest joint during the construction of any new drives. The Department
repeats this comment. Please label on the site plan and demo plan.
DITAHT.1n:N7' ()r EN(,INETIZ1NG
ONr C1N 1C. Sail al(E, CAR.NIEL, IN 46032 Ohi:ici: 31-7,571.2441 F.�s 317.571.2439
E:NIA11, rr) nrErrin c;lrn el.in.guc
Mr. George Lukas
March 21, 2013
RE: McDonald's Restaurant 750 East Carmel Drive remodel- Project Review 42
Page 2 of 2
11. Previous Comment 27 of a letter dated August 30, 2012. Please ensure that all improvements
remaining from the previous entrance to the site off of Carmel Drive are removed. Please
call out this statement on the demo plan. The bollards should be shown as being
removed as well.
12. Previous Comment 28 of a letter dated August 30, 2012. Please include a Maintenance of
Traffic Plan, meeting all requirements of the Indiana Department of Transportation Work
Zone Safety Manual current edition, for the construction of the entrances. The Department
repeats this comment.
13. Previous Comment 33 of a letter dated August 30, 2012. Please provide the local flood
routing through the site (all inlets plugged during a 100 -year storm event). The Department
repeats this comment.
14. Previous Comment 34 of a letter dated August 30, 2012. Please provide the MFPG and
MLAG for the building. The MLAG has still not been provided. The MLAG shall be
equal to the MFPG for this site. The FFE shall be set 6 inches higher than the MLAG.
15. Note 17 on Sheet 1 of 2 of the land survey states, "Based on contact with the City of East
Point Right of Way Department there are no current or proposed changes in street right of
way lines ". This is an inaccurate statement.
16. All storm structures proposed to be constructed within the City right -of -way shall be
reinforced concrete pipe.
17. Please remove the standard concrete curb detail.
18. Please edit the "Concrete sidewalk wl monolithic curb" detail to meet the City's standard for
straight concrete curb with a 22 -inch depth.
19. Board of Public Works and Safety approval is required for the modification to the southern
curb cut.
If you have questions, please contact me at 571 -2441.
Sincerely,
Amanda Foley
Staff Engineer
Department of Engineering
cc: Angelina Conn, Department of Community Services
John Duffy, Carmel Utilities
Paul Pace, Carmel Utilities
Paul Arnone, Carmel Utilities
Greg Hoyes, Hamilton County Surveyor's Office
Greg Ilko, Crossroad Engineers, PC