Loading...
HomeMy WebLinkAboutCorres Conn, Angelina V From: Duncan, Gary R Sent: Tuesday, December 21, 2010 11:38 AM To: Eric Carter Subject: Turkey Hill Minitmart Eric, please find my comments for the Legacy Turkey Hill Minitmart. 1. Please indicate on Sheet C101 that the existing pavement edge shall be saw cut to a clean edge. 2. Sheet C102. Plan Note 14. City standard ADA ramps shall be utilized in the right-of-way and differentiated on the plans if different ramp details are proposed interior to the development. 3. Please indicate the types of ADA ramps to be constructed din the right-of-way. All ramps in right-of-way are referenced by plan note 14. 4. A recovery taper is required for the auxiliary lanes along River Road.This taper may be 100-feet in length and must have a 3-foot wide, 6-inch deep stone shoulder with a sub-surface drain. 5. The City Engineer does not support the proposed right-in entrance from River Road. Approval from the BPW is required for this curb cut and it will not be supported. 6. Please indicate any signage in the River Road right-of-way that needs to be relocated due to this project. 7. Will all BMP easements be granted at this time? Is the SWQ systems proposed within the limits of the storm water quality park proposed to be in one large easement? 8. Please label the existing and proposed rights-of-way (if different)for 146th Street and River Road. 9. The Department assumes that the pavement specification for the 146th Street auxiliary lanes and the River Road auxiliary lanes will be different. Please differentiate on the plans and make reference to the appropriate detail in the detail sheets. 10. The deceleration taper and deceleration lane for the southernmost River Road entrance may each be 100-feet in length. 11. Are any landscaping or tree preservation easements proposed to be established with this project? 12. Please confirm if the existing right-of way monument at the proposed southernmost River Road entrance will be reset 13. As we discussed,the Department requires confirmation that detention for this site exists within the limits of the future storm water park and that the fill in the floodplain proposed with this project has been mitigated. 14. Please indicate if grading is to occur between the Turkey Hill site and the proposed SWQ system. Who will perform this grading? 15. Please complete the Discharge Summary on Sheet C103. 16. Further review of the plans indicates that the site sits slightly higher than the adjacent roadway and most of the site drains towards river road and 146th Street. Please indicate why this is being changed and that the minimum 15-inches above the existing roadway cannot be provided. 17. Please establish the MLAG and MFPG elevations. 18. Please provide a note on the plans that requires all existing storm structures to be core drilled for new piping connections. 19. Is the casting at the northwest corner of the proposed intersection of the southernmost entrance and River Road to be replaced? 20. Please confirm that the gas service will be installed by trenchless method within the River Road right-of-way. 21. As discussed, please revise the piping between Storm Structures 206 and 205, 205-202, 204-203, 203-202 and 202-201A to be sanitary sewer grade pipe and gaskets. 22. Thank you for providing the note regarding no valves or castings in the pavement, walk, path and curb in the right-of-way. It appears that some water castings will be located within the limits of the proposed path. 23. Please review if the excavations of the lift station, car wash underground storage tanks and the grease trap need to be lined to protect the groundwater. 1 24. Is the water table and the 100-year base flood elevation of White River and maximum water surface elevation of the adjacent proposed storm water park an issue for the proposed lift station, grease trap,fuel tanks and car wash storage tanks? 25. Please verify that the proposed barrel taper length on 146th Street is appropriate for the posted speed limit. 26. Does the maintenance of traffic plan conform to the Work Zone Safety Manual? 27. Please move detail 10-16 from sheet C201 to a site layout detail sheet. 28. Please include the City ADA ramp details. 29. Please revise the heavy duty asphalt right-of-way pavement section detail to read "River Road". Please include the appropriate County detail for the 146th Street pavement. 30. If differing RCP bedding sections are proposed (the City detail is included with two Weihe Details) they must be differentiated on the plans 31. Paving specifications on Sheet C301. Please revise to require paving in the right-of-way to conform to the City Paving Policy. Please delete all curbing specifications from this section as all curbing shall conform to the City's curbing policy 32. Sheet SA1. Please indicate the total construction limits on this sheet. The stormwater basins are not included in the construction limits indicated. Also, please indicate the battery limits of the Turkey Hill work on this sheet. 33. Has the utility requested the force main to be located within the 146th Street right-of-way versus and easement within the Legacy property? 34. Sheet SA6. Is it not possible to match the pipe crowns at Structure 501? 35. A 21-inch pipe is indicated "by others" into Structure 505. Who is installing this pipe? 36. Structures 502 and 503 appear to be mislabeled in the right profile on Sheet SA6. 37. Please delete the "Storm Sewer Note"from the water main plan sheets. 38. The path location along River Road on Sheet SA8 does not agree with the layout presented on the Turkey Hill Plans. 39. Is cross section A-A on Sheet SP1 correct?The easternmost top bank is labeled as 748 but it appears that the top of bank is actually 752. 40. Does River Road and 146th Street presently overtop t o the east before it floods into the property? I cannot read the spot shots on the eastern pavement edge. If the right-of-way does drain into the property during the 100- year rain event, with the elimination of the right-in only entrance, is it possible to re-grade the eastern part of the site to bring the water south of the proposed building and provide more freeboard? 41. Has the on-site maximum water surface elevation with all inlets plugged been established? 42. Section 104.02 requires the building's lowest entry elevation that is adjacent to and facing a road shall be a minimum of 15 inches above the road elevation. Is it possible to adjust the pad grade so that it is 15-inches above the centerline of the adjacent roadways? Thanks so much! Gary Gary R. Duncan,Jr., PE Assistant City Engineer City of Carmel Department of Engineering One Civic Square Carmel, IN 46032 (317) 571-2441 (317) 571-2439 (fax) gduncan @carmel.in.gov Please consider the environment before printing this e-mail 2 Conn, Angelina V From: Duncan, Gary R Sent: Tuesday, December 21, 2010 11:25 AM To: Eric Carter Cc: Jamie Shinneman Subject: RE: Pilgrim and Turkey Hill Legacy Eric, I have completed my review and provide the following comments: 1. The deceleration taper, deceleration lane and recovery taper each may be 100-feet in length. Please provide a 3-foot wide, 6-inch deep gravel shoulder adjacent to these lanes with a sub-surface drain. • 2. Please contact this office to discuss compliance with the Thoroughfare Plan required by Section 2.09 of the Carmel Zoning Ordinance. 3. Please ensure the return radii of the entrance are 40-feet. 4. The City is not requesting any further improvements to 106th Street as part of this project. 5. Some areas are indicated as "future". Please indicate the construction limits on each sheet. 6. Please add the following note to each sheet: "No earth disturbing activity may take place without an approved storm water management permit" 7. Site Layout Plan, Plan Note 3. Paving in the right-of-way shall be asphalt for this project. 8. Site Layout Plan, Plan Note 7. Please indicate that the existing pavement shall be saw cut to a clean edge and tacked prior to placing new pavement. 9. Please show the path being constructed by others on all sheets. Please indicate ADA ramps (if needed) for construction with this project if the path is constructed before this project. 10. Are any landscaping or tree preservation easements proposed with this project? 11. The City standard commercial drive width is 30-feet. Please reduce the width of the entrance. 12. Please add the following note to the appropriate sheets in the plan set: "ALL PAVING WITHIN THE EXISTING AND PROPOSED CITY RIGHT-OF-WAY SHALL CONFORM TO THE REQUIREMENTS OF THE DEPARTMENT OF ENGINEERING. THE CONTRACTOR SHALL CONTACT THE DEPARTMENT OF ENGINEERING TO SCHEDULE A PRE-CONSTRUCTION MEETING TO REVIEW THE DEPARTMENT'S CONSTRUCTION REQUIREMENTS, STAFF NOTIFICATION REQUIREMENTS, REQUIRED INSPECTIONS FOR CERTAIN STAGES OF THE WORK AND TO REVIEW THE AUTHORITY OF THE DEPARTMENT AS IT RELA l'ES TO WORK WITHIN THE EXISTING AND PROPOSED RIGHT-OF-WAY" 13. Please confirm that all known underground and overhead utilities are indicated on the plans. 14. Please indicate the maximum water surface elevation of the on-site flood route. Does this impact the MFPG and MLAG? Specifically along the southern part of the building 15. Please establish and label the MFPG and MLAG elevations and add the appropriate definitions to the plans set. 16. There appears to be several pockets that might be poorly drained. There is a pocket in the right-of-way just east of the entrance and east of the easternmost rain garden. 17. What is the maximum depth of the water being stored in the dry detention pond? 18. Are there any legal drain easements on the property? 19. Please label the slopes of the pond bottom. 20. Please provide more detail for the grading of the deceleration taper and lane. It is not apparent how the lanes and the adjacent area in the right-of-way will drain. 21. Pleas indicate an underdrain in the SWQ system adjacent to the pipeline unless such an underdrain will inhibit the function of the proposed SWQ system. 22. Please confirm if the water meter and FDC are located within the proposed path along 106`" Street. 23. Underdrains are required in the pond bottom if the slope is less than 2%. The minimum pond bottom slope with underdrain is 1%. 24. Will the gas service be installed by trenchless method? 25. Thank you for providing the required drainage summary. If a 6-inch orifice is proposed for installation, please include the 10-year and 100-year flows with a 6-inch orifice. 26. Is detention of the fully developed adjacent right-of-way provided in the proposed system? 27. It appears that repair of the path will be required for the sanitary sewer connection. Please indicate on the plans. 28. Sheet C106, Maintenance of traffic Notes Number 1. Lane reductions require approval from the BPW. 29. Does.the Maintenance of traffic plan conform to the INDOT Work Zone Safety Manual? 30. Please label the approximate elevation of the creek bottom on Sheet C107. 31. Sheet C202. Is Detail 10-25 proposed with this project? 32. Please include the City Standard ADA ramp details if needed for where the 106t1i Street path crosses the proposed entrance. 33. Please delete the Heavy Duty Concrete Right-of-Way paving section detail. 34. Sub-Surface Underdrain Tile detail on Sheet C203. Please indicate the pipe to be dual wall Hancor Hi-Q or equivalent. 35. If differing RCP bedding sections are proposed (the City detail is included with two Weihe Details) they must be differentiated on the plans. 36. Paving specifications on Sheet C301. Please revise to require paving in the right-of-way to conform to the City Paving Policy. Please delete all curbing specifications from this section as all curbing shall conform to the City's curbing policy. Thanks so much! Gary From: Eric Carter [mailto:cartere @weihe.net] Sent: Thursday, December 16, 2010 3:09 PM To: Duncan, Gary R . Cc: Jamie Shinneman Subject: Pilgrim and Turkey Hill Legacy Hi Gary Turkey Hill 604 - Legacy We ran the calcs of the "offsite"watershed routing between the canopy and building and have come up with a critical 100 yr depth of 758.52. The Building Pad Elevation is 759.00. Are you ok with the Building not 2' above the 100 yr, as we discusses with ADA requirements and Turkey Hill's building design (no curb), 2' would be unreasonable. I also checked the building with the adjacent grades of River Road and 146th Street. These areas at their lowest spot is 15" above the "gutter" level. Pilgrim Lutheran Church Have you had a chance to speak with Mike yet regarding the 106th street improvements? I hope you will be able to talk with him prior to leaving on vacation. (just a friendly reminder !) 2 • Thank you, Eric kq]El WEIHE ENGINEERS Land Surveying l(Nil Engineering Landscape Ar; acture arrzPr! i'Fil, coaf? fritce Eric A. Carter, R.L.A., ASLA Project Manager,Commercial Development • Weihe Engineers,Inc. 10505 N. College Avenue Indianapolis, Indiana 46280 317846 - 6611 • 800 1 452 -6408 317 1 843 -0546 fax weihe.net This message and any files transmitted with it are confidential,may contain privileged information which is intended solely for the receipt,use and benefit of the intended recipient of this email.If you are not the intended recipient,be advised that dissemination,distribution,printing or copying of this message is strictly prohibited and may result in legal liability on your behalf.If you receive this message in error,or are not the named recipient,please notify the sender at either the email address or telephone number above and delete this email from your computer.Thank you. 3 December 14,2010 ITY i �fx. s DEL Mr. Eric Carter JAMES BRAINARD, MAYOR Weihe Engineers 10505 North College Avenue Indianapolis, IN 46280 RE: Turkey Hill Minit Markets Store#604-Project Review 41 Dear Mr. Carter: The City received your construction plans on November 19,2010. The project is scheduled for review at the December 15,2010 Technical Advisory Committee meeting. We offer the following comments: GENERAL INFORMATION 1. 'These comments represent the Department of Engineering's first review of the preliminary development plans for this project. 2. We request that all responses to our comments be provided in writing and be accompanied by a drawing reflecting the requested revisions. Failure to provide written responses may result in the delay of the review process. 3. It is critical that this office be made aware of all modifications made on the plans being re- submitted,particularly if any such changes are considered"new"or fall outside of our previous reviews. Please provide revised plans including all revisions. Please notify us of any changes and specifically state any changes,including changes resulting from Plan Commission,BZA or other committee meetings. 4. We have engaged Crossroad Engineers,4 to review all drainage plans and drainage calculations submitted to this office for review. If you have not already done so,please provide a set of drainage plans and calculations to their office for review.We will share Crossroad's comments as they are received. 5. Final drawings will not be approved for construction until: a. All Engineering Department and Utility Department and Hamilton County Surveyor issues have been resolved. b. All bonds and performance guarantees are posted. c. All Board of Public Works and Safety approvals and any other governing agency approvals(if required)are obtained. d. All off-site easements necessary to install utilities to serve the development are secured. e. SWPPP is approved. f. All fees are paid. 6. The Department reserves the right to provide additional comments based upon subsequent reviews. 7. An approved Storm Water Management Permit is required prior to commencing any earth disturbing activity. Please contact Mr.John Thomas regarding storm water quality requirements. 8. An approved right-of-way permit is required prior to commencing any work in the public right-of-way. 9. Hit will be necessary to relocate existing utilities,the costs for such relocation shall be borne solely by the developer. Any utility poles requiring relocation shall be relocated to within one-foot of the outside edge of the proposed right-of-way. 10. The Department requires that the construction drawings be developed in accordance with the City of Cannel digital submission standards and that all required submittals for primary plat, DEPARTuItNT OF ENGINEERING ONE Civic SQUARE, CARMEL; IN 46032 Orrice 317.571.2441 FAx 317.771,2439 EMAIL enginctringRcarmel.in.gov Mr. Eric Carter December 14,2010 RE: Turkey Hill Minit Markets Store#604-Project Review#1 Page 2of4 secondary plat,and construction drawings be made. The digital files must be submitted to the Department of Engineering prior to the approval of the construction plans. Please contact the City GIS Department for the requirements. 11. Jurisdictions: a. The project site is located within current City of Carmel Corporate Limits, b. Perimeter Street and Right-of-Way—City of Carmel (River Road), Hamilton County (146`h Street) c. Water—City of Carmel Utilities d. Sanitary Sewers—City of Carmel Utilities e. Storm Sewers/Drainage—City of Carmel. f. Legal Drains—Hamilton County Surveyor's Office. 12. Drawings submitted for approval: a. The design engineer must certify all drawings submitted for final approval. b. This office will require 9 sets of drawings for approval after all issues have been resolved. The drawings will be stamped as approved and signed by the City Engineer and by Carmel Utilities. The Owner will receive 3 sets,one of which must be maintained on the construction site at all times. If this project is subject to review and approval by the Hamilton County Surveyor's Office, a total of 11 sets will be required for final approval. 13. Cannel Utilities will provide separate reviews of this project for water issues. Please assure that copies of all drawings are sent to: Paul Pace Paul Arnone Carmel Utilities Distribution Carmel Utilities Collection 3450 West 131u Street 901 North Range Line Road Westfield,IN 46074 Carmel,IN 46032 14. Carmel Utilities subscribes to"Holey Moley"who should be contacted directly for all water main locations. 15. The following items will be sent electronically upon request regarding this correspondence and project: a. Project Approval Checklist b. Performance/Maintenance'Guarantees c. Utility Jurisdictions/Right of Way Permits d. Availability(acreage)Fees BOARD OF PUBLIC WORKS AND SAFETY 16. A schedule for Board of Public Works and Safety meeting dates and agenda deadlines will be sent electronically for your use upon request. Please use the Engineering Department deadlines for submissions to the Board. 17. Any submission to the Board requires prior approval by the Cannel Clay Plan Commission and/or the Board of Zoning Appeals(if applicable)and completion of review by the Technical Advisory Committee. All written requests to be placed on the Board's agenda must include the appropriate Docket Number and the date(or dates)of approval by the Plan Commission and/or the Board of Zoning Appeals(if applicable). 18. Water Availability and Sanitary Sewer approval from the Board will,be required. This is an EDU approval based upon the proposed use of the site. Reference Items#33 to#35 below for additional details/explanations. Please note that if an entryway or other irrigation system is planned for this development,additional Water Availability Approval from the Board will be required and additional Water Connection Fees will be assessed based upon the size and usage of the system as determined by the Director of Carmel Utilities. 19. Commercial Curb Cut Approval. Please provide 8l2.x 11 exhibits with the request for approval. Provide all pertinent information including lane widths,overall width, radii,lane markings, location of opposing drives or streets,relationship to the location of previous curb cut.etc. Mr. Eric Caner December 14,2010 RE: Turkey Hill Minit Markets Store#604-Project Review#1 Page 3 of 4 20. Temporary Construction Entrance Approval. It appears the planned construction entrance is located at the site of a permanent curb cut planned on Grand Boulevard. Therefore,a separate approval from the Board will not be required. 21. The installation of any permanent,privately owned and/or maintained improvement(signs, decorative street signs,walls,streetlights,etc.)within dedicated right of way or dedicated easements requires the execution of a Consent to Encroach Agreement between the Owner and the City of Carmel. Such agreements are executed by the Board of Public Works and Safety. The City Engineer may approve irrigation system agreements. 22. Secondary Plat approval if applicable. Ali performance guarantees must be posted prior to submission of secondary plats for Board of Public Works and Safety approval. 23. Dedication of right-of-way if not platted. This is based upon the City of Carmel 20-Year Thoroughfare Plan requirements. Dedication documents are available upon request. Please be advised that all Right-of-Way Dedications must be accompanied by a Sales Disclosure Agreement completed by the owner for the property being dedicated to the City. The dedication document cannot be recorded without a completed Sales Disclosure. The form is available upon request. 24. Any open pavement cuts of River Road,other than those required for the curb cut,will require Board approval. • BONDING REQUIREMENTS 25. Please contact Mr. Dave Barnes to review performance guarantee requirements. Please contact Mr.John Duffy to review water and sanitary sewer bonding requirements. 26. The amount of the Performance Guarantee is based upon a certified Engineer's Estimate for 100%of the cost of labor and materials to construct the individual improvements,to be provided by the design engineer. Please provide detailed Engineer's Estimates for each improvement including quantities, unit costs,pipe sizes,and materials,etc. 27. Upon completion and release of individual Performance Guarantees,a three-year Maintenance Guarantee will be required(see Street Sign comments above). The Maintenance Guarantee amount is based upon l5%of the Performance amount for Streets and Curbs and 10%of the Performance amount for all other improvements. 28. Performance Guarantees may be Performance or Subdivision Bonds or Irrevocable Letters of Credit. 29. Please reference the available enclosures for more detailed explanation of our procedures. RIGHT OF WAY PERMIT AND BONDING 30. Any work in the dedicated right-of-way will require an approved Right-of-Way Permit and a License&Permit Bond. 31. The bond amount is determined by our Right-of-Way Manager. However, if the work is included in the scope of work of a required and posted Performance Guarantee,the Performance Guarantee may be used to satisfy the bond requirements of the Right-of-Way Permit. 32. Please contact our Right-of-Way Manager,Fred Glaser,to arrange right-of-way permitting and bonding. AVAILABILITY AND CONNECTION FEES 33. We defer to Carmel Utilities regarding this issue. 34. If an entryway or overall site irrigation system is planned for this development, additional Water Connection Fees will be assessed based upon the size and usage of the system and upon the recommendations of the.Director of Carmel Utilities. 35. These fees are required to be paid prior to final approval of construction plans by Engineering and prior to issuance of building permits by Building Codes Services. Please confirm these fees and calculations with Carmel Utilities. Mr. Eric Carter December 14, 2010 RE: Turkey Hill Ntinit Markets Store#604-Project Review#1 Page 4 of 4 CONSTRUCTION DRAWING REVIEW.COMMENTS 36. General Comments a. This project is subject to the City's Storm Water Management and Storm Water Quality Ordinances. b. Please add the fol lowing note to the drawings: IF IT WILL BE NECESSARY TO RELOCATE EXISTING UTILITIES,THE EXPENSE OF SUCH RELOCATION SHALL BE THE RESPONSIBILITY OF THE DEVELOPER. ALL UTILITY POLES SHALL BE LOCATED WITHIN ONE FOOT OF THE PROPOSED RIGHT-OF- WAY." 37. Please add note stating"NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN APPROVED STORM WATER MANAGEMENT PERMIT"to construction set. 38. All swales on site must have sub-surface pipe installed. Pipe to conform to requirements of Storm Water Technical Standards Manual and shall be double wall, HI-Q pipe. 39. Please omit Sheet LI01,Landscaping Plan;Sheet L201,Landscape Details;Sheet SP2, Landscaping Plan;and Sheet SP3,Landscaping Details&Specifications from construction sets to be submitted for review by this department. The Department of Engineering does not have approval authority over landscape plans or photometric plans. 40. Sheet C 102. a. The word"signs"is misspelled in the note in the lower right corner of the sheet. 4I. The width of the entrance does not comply with the city standard, which is included on sheet C202. Please reduce the width of the entrance to a maximum of 30 feet. If you have questions,please contact me at 571-2441. Sincerely, Nicholas J. Redden, P.E. Plan Review Coordinator Department of Engineering cc: Angelina Conn,Department of Community Services John Duffy.Carmel Utilities Paul'Pace,Carmel Utilities Paul Arnone.Carmel Utilities Greg Hoyes,Hamilton County Surveyor's Office Greg llko, Crossroad Engineers, PC issvrapps l user datatessharcd\DHtLL['ROJRI VIO\TURKEY1IILLMINITMARKE!'SSTORE#60-4REV#I .., H .44, \ 1 juroN COUNTY O 71 %'... .. . t S� �� ATow"1144 1 =4 JPA Tk dam. �f T '4 4 41r1g_ P T$. O F %N�\ December 13, 2010 Eric Carter Weihe Engineers 10505 N. College Avenue Indianapolis, IN 46280 RE: Turkey Hill Minit Markets Store#604 Construction Plans S of 146th Street/W of River Road Clay Township Dear Joe: This letter serves to acknowledge receipt of a transmittal on November 19, 2010 containing the construction plans. After reviewing the plans the Highway Department has the following comments: 1. An Application for Project Review must be completed and the appropriate review fees paid prior to any approvals from this office. The application is available on the County Website_ 2. Please include the HCHD 146th Street Standard Drawings. Any activity within the 146th Street R/W must conform to the standards unless approved by this department. 3. Entrance and deceleration lane to maintain 2% of fall away from 146th Street to the R/W line. 4. Inlets to be added at the R/W line and connect to the 146'h Street storm. 5. The inlet that is affected by the deceleration lane is to be removed and a new inlet added at the curb. 6. All new pavement markings to be Thermoplastic. - Arrow with "ONLY" in the deceleration lane. - Arrow with "ONLY" in the exit lane. - Crosswalk—24" stripes with 24" spaces. 7. New RPM's are needed between the thru lane and deceleration lane. 8. Show a "No Left Turn" (R3-2) sign at the entrance. 1700 South 10"'Street Office(317)773-7770 Noblesville,In.46060 www.co.hamiiton.in.us Fax(317)776-9814 9. Show a "One Way" (R6-1R) sign in the center median of 146th Street at the entrance location. 10. ADA ramps are to be Type A "modified". 11. Is the "pork chop" to be raised or striped? 12. Further comments may be needed at a later date. If you have any questions or comments concerning this letter, please feel free to contact me at anytime. Sincerely, 1'7 David E. Lucas Staff Engineer DL:dI 12-13-10.a • • Cc: Carmel TAC members • G:I USERStdel\CommerciaRClay\turkeyhillminitmarket 12-13-10 t of G ( 444etedimmtA, \ City of Carmel :., \!NOtaeta,/ DEPARTMENT OF COMMUNITY SERVICES December 9, 2010 Mr. Eric Carter Weihe Engineers 10505 College Ave Indianapolis, IN 46280 RE: Turkey Mini Mart Store#604 Dear Mr. Carter: The following letter represents comments for this project specifically addressing the area of alternative transportation. I have reviewed the drawings submitted for the December 15, 2010 Technical Advisory Committee meeting and offer the following comments: ALTERNATIVE TRANSPORTATION REVIEW COMMENTS 1) Please see the City of Carmel's Parking Ordinance in order to determine appropriate locations, specifications and construction details for the above. 2) The City of Cannel's and the Legacy PUD's Bicycle and Pedestrian Plan requires the construction of a 10' path along the entire street frontages of 146th St and River Rd. Please revise the plans to include and label these facilities. 3) The City of Cannel's Bicycle and Pedestrian Plan and the Legacy Street Standards both require a minimum of five (5)foot sidewalks along all streets. Please revise the plans to include and label these facilities along Street A and B. 4) Exhibit 3:Bicycle and Pedestrian Plan in the Legacy PUD also shows a"primary walking path" along the south side of the site connecting to the River Rd path. Please revise the plans to include and label this facility. 5) Exhibit 6: Street Plan shows the south west corner of 146th St and River Rd as a "secondary point of connectivity." Please provide details of this. Page I ONE CIVIC SQUARE CARMEL,INDIANA 46032 317/571-2417 ��,�oF M'� /o ft k� F Q i�r fi a • rx ® 1 � d / DEPARTMENT OF COMMUNITY SERVICES 6) Please consider providing a direct connection from the multiuse path along 146`1'St to the site's internal sidewalks. We request that all responses to our comments be provided in writing. Failure to provide written responses may result in delay of the review process. It is critical that this office be made aware of all modification made on the plans being re-submitted, particularly if any such changes are considered "new"or fall outside of our previous reviews.Please provide revised plans indicating all revisions. Please notify us of any changes and specifically state any changes,including changes resulting from Plan Commission, Special Studies or other committee meetings. The Department of Community Services reserves the right to provide additional comments based on subsequent reviews. If you have questions,please contact me at 571-2417. Sincerely, David Littlejohn Alternative Transportation Coordinator Department of Community Services cc: Angie Conn, Department of Community Services Engineering Department Review Project File Page 2 ONE CIVIC SQUARE CARMEL,INDIANA 46032 317/571-2417 Conn, Angelina V From: Conn, Angelina V Sent: Wednesday, December 08, 2010 11:23 AM To: 'Jon Dobosiewicz' Cc: 'Charlie Frankenberger'; Hollibaugh, Mike P Subject: Turkey hill © Legacy- north elevation Jon— I spoke with Mike H about all the elevations, and yes, Turkey Hill will need to add more detailing to the north elevation that faces 146th Street because right now it looks like the back of a building.Adding some windows would be preferred, and if not that,then some spandrel and some of the cement fiber board.The east and west elevations are okay, generally. We can meet to discuss this further, after you respond to all the review comments and get us a floor plan,too. ...Just out of curiosity, why can't the building and floor plan closely match what was approved for the Range Line Rd & Carmel Drive location? Thank you, Angie Conn, Planning Administrator City of Carmel Planning &Zoning Division Dept. of Community Services 1 Civic Square, 3rd FIr. Carmel, IN 46032 0: 317-571-2417 I F: 317-571-2426 I E: aconnOcarmel.in.gov W: www.carmel.in.nov/services/DOCS/DOCSDOPZ.htm Please consider the environment before printing this e-mail 1 `v OF City of Carmel, Utilities T4pRTFERS�"� 760 3rd Avenue S.W.#110 Carmel, IN 46032 December 7, 2010 James K. Shinneman Professional Engineer Weihe Engineers RE: Turkey Hill Minit Market #604 Mr. Shinneman: The Carmel Sewer Department has reviewed the prints for Turkey Hill Minit Market and has.some questions andlor corrections listed below. As-built plans,which include both sanitary sewer lateral and water service connection measurements and profile plans,are to be turned into the Carmel Utilities office at the time that the water is due to be turned on. Please send those as-built plans to following address:760 3`d Avenue S.W., Suite 110 Carmel,IN 46032. We will need a set of paper/hard copy as-built plans as well as a copy of electronic as-built plans on a CD. These CD drawings must include streets,lots,water mains,valves,sewer mains,manholes,laterals and service lines. Sewer Comments: 1. Provide details regarding sizing and design of proposed grease interceptor. 2. Install tracer wire with proposed force main and ensure access to that wire in 500' intervals by providing marker posts along its path. 3. Connection to the existing sanitary sewer shall be a properly sealed,core-drilled installation. Should you have any questions regarding this letter or would like to schedule a meeting,please do not hesitate to contact.our office at 317-571-2645. Sincerely, Aaron Hoover Sewer Collections Inspector cc: Paul Arnone,Sewer Collections Supervisor Ed.Wolfe,Sewer Operations Manager John Duffy,Utility Manger r 4 \2- 7--°O�QPEL\F;-`\-� LETTER OF TRANSMITTAL �T 4 9� yr INC. :fi, STOEPPELWERTH & ASSOCIATES, N -.-ClatO" 7965 East 1:06u'Street 'j Fishers,Indiana 46038 Phone(317)849-5935 FAX(317)849-5942 DATE: December 7, 2010 JOB NUMBER: 55115PLA-S TO: Carmel City Utilities 760 Third Avenue SW Carmel, Indiana 46032 ATTENTION: John Duffy RE: The Legacy Corner WE ARE SENDING YOU I I tips I J Courier I I Other: Deliver COPIES SHEET DESCRIPTION NO. 1 Set • Construction Plans 1 Capacity Certification/Allocation Letter 1. IDEM Water NO! 1 Check No. 26150 for$150.00 1 Sanitary Sewer Construction Permit Application l Engineers Certification 1 List of Affected Persons (Labels) THESE ARE TRANSMITTED as checked below: I X l For Approval I I As Requested I 1 For Review and Comment I 1 For Your Use I I REMARKS: If you have any questions, please feel free to give me a call at (317) 570-4841. • Thank you, ___Z..#4 k/.. ''' Brett A..Huff Cc: Angie Conn Paul Pace Tim Walter BAaIhneb S:155I I5PLA-S1BIur_Book\Agency_( rrespondenceVl RANCa riuelttlilitiesDuf lyl2-06-f0.l)OC I, 26150 tiQeEtry` STOEPPELWERTH AND ASSOCIATES INC. HUN7INGTON I ,`o,a ��, ASSOCIATES, 7a7r74o h 3fZ4t. s PH.317-849-5935 '4112)0,ter► 7965 EAST 106TH STREET l c� . FISHERS,INDIANA 46038-2505 12/6/2010 f 1 PAY TO THE ORDER OF IDEM $ `*150.00 **#********************#*****************************'k'****************k*k***********k********* y1 One Hundred Fifty and 00!100 DOLLARS li i8 IDEM 100 North Senate Street Suite 1255 I Indpls. IN 46206-6015 STOEPPELWERTH AND ASSOCIATES,INC. MEMO , E ,, hr 0, 0 026b5011° 1:0 ?40000 ?EBo 0b5Sb6580El 1Il° i' STOEPPELWERTH AND ASSOCIATES, INC. IDEM 12/6/2010 2 615 0 149 • Reimbursable Expense 55115PLA-S - NOI WATERMAIN EXTN 150.00 Huntington National B 150.00 STOEPPELWERTH AND ASSOCIATES, INC. IDEM 12/6/2010 26150 149 • Reimbursable Expense 55115PLA-S - NOI WATERMAIN EXTN 150.00 Huntington National B 150.00 inDELUXE cony 1+800-328-0304 0037262 • may^, NOTICE OF INTENT TO CONSTRUCT A WATER MAIN EXTENSION State Form 49008(R/10-04) x„,:. � j tea; 'r Approved by State Board of Accounts,1998 ` . ' ailifiltCanstr'uct.661f rmit F6WI er Marralensfansd „R 7-1t.' 1.Title of proposed project 2.County of proposed project The Legacy corner Hamilton • 3. Location of proposed project(including nearest public intersection and nearest quarter Section,Township,Range) Southwest corner of the intersection of 146th Street and River Road. Northeast Quarter of Section 23, Township 18 North, Range 4 East. 4.Name,title,and firm of responsible person(as defined in 327 IAC 8-3.5-6) 5.Telephone number of responsible person Kenneth Brasseur, Vice President, Personal Investments, LLC (317) 818-2900 6.Address of responsible person 9757 Westpoint Drive, Suite 600, Indianapolis, Indiana 46256 7.Name of Public Water System(PWS) 8.PWS ID Number Carmel City Utilities 5229004 9.Address of PWS 10.Telephone number of PWS 760 3rd Avenue SW, Suite 110, Carmel,Indiana 46032 (317) 571-2451 11.Name and firm of professional engineer 12.Telephone number of professional Stoeppelwerth & Associates,Inc. engineer(317) 849-5935 13.Address of professional engineer 7965 East 106th Street, Fishers, Indiana 46038 14.Name of developer 15.Telephone number of developer Personal Investments, LLC (317) 818-2900 16.Address of developer 9757 Westpoint Drive, Suite 600, Indianapolis, Indiana 46256 • 17.Timing of construction(check one of the following): © The proposed construction of the water main will begin on February 2011 and be completed on February 2012 .(Cannot begin construction less than thirty(30)days after IDEM receives a complete and sufficient NOI.) ❑ The proposed construction schedule will be submitted separate from this NOI at least ten(10)working days before the commencement of the construction and will include a copy of the information on the first page of this NOI.(Cannot begin construction less than thirty(30)days after IDEM receives a complete and sufficient Not.) 18.Fee Schedule: THE COMPLETE NOTICE OF INTENT ALONG WITH ALL REQUIRED FEES El No fee,exempted under 327 IAC 8-3-7(a). MUST BE SUBMITTED BY CERTIFIED MAIL TO: No fee for water main extensions under 2,500 linear feet. DRINKING WATER BRANCH Indiana Department of Environmental Management $150 for water main extensions from 2,501 to 5,000 linear feet. 100 North Senate Avenue El $250 for water main extensions from 5001 to 10,000 linear feet. Indianapolis,Indiana 46204 ❑ $500 for water main extensions greater than 10,000 linear feet. Make checks payable to:I.D.E.M.(Acct.#3240-414000-140000). 19.Certifications: Responsible Person: "I certify that I have reviewed and understand the applicability and eligibility requirements of this rule and that the water main proposed with the submission of this NOI meets the applicability and eligibility requirements of this rule. I also certify that the design and construction of this project will be performed under my direction or supervision to assure conformance with 327 IAC 8-3.5 and will meet all local rules or laws,regulations and ordinances.The information submitted is, to the best of my knowledge and belief,true,accurate,and complete.I am aware that there are significant penalties for submitting false information,including the possibility of fine and imprisonment. Signature of responsible person %{`� "1 � ' Date signed(month,day,year) Kenneth Brasseur � —f�- `2 7 k :i� P December 6, 2010 Professional Engineer: "I certify under the penalty of law that the design of this project will be performed under my direction or supervision to assure conformance with 327 IAC 8-3.5 and that the plans and specification will require the construction of said project to be performed in conformance with this rule.The design of the proposed project will meet all local rules or law,regulations and ordinances.The information submitted is,to the best of my knowledge and belief,true, accurate,and complete.I am aware that there are significant penalties for submitting false information,including the possibility of fine and imprisonment." Signature of professional engineer Date signed(month,day,year) James 0. Rinehart IV December 6, 2010 (Continued on Page 2.) Page 1 of 2 Indiana Department of Environmental Management NOTICE OF INTENT TO CONSTRUCT A WATER MAIN EXTENSION „ Office of Water Quality 10-04 State Form 49008(R 110-04) Developer: "I certify under the penalty of law that the construction of this project will be performed under my direction or supervision to assure conformance with 327 IAC 8-3.5.The construction of proposed project will meet at local rules or laws,regulations and ordinances.The information submitted is,to the best of my knowledge and belief,true,accurate,and complete.I am aware that there are significant penalties for submitting false information,including the possibility of fine and imprisonment." Signature of developer: .- Date signed(month,day,year) Kenneth Brasseur ` ° - ;5.;;;. _; _.- December 6,2010 PWS Representative: "I certify under the penalty of law that I have agreed to fumish water to the area in which the water main is proposed. I acknowledge the public water system's responsibility for examining the plans and specifications to determine that the proposed water main meet local rules or laws and ordinances.I also acknowledge the public water system's responsibilities as outlined in 8-3.5-12. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment." Signature of PWS representative: Date signed(month,day,year) 20.Project Design Criteria: Alternative Technical Standards(327 IAC 8-3.2.20) • 21.Are any"Alternative Technical Standards"proposed to be used in this project? ❑ Yes,I have attached copies of the approval with the NOI. is No Public Water System Capacity Status 22.The PWS's Daily Production Firm Capacity: A. MGD B. GPM 23.The PWS's five(5)highest demand days in the previous two(2)years: „.1;11.tj'e lirrr�l Demand(MGD) Date ��` co0 14 aa° 1. �`Ci a j1STF9•�'per ▪ Qc No. aaGs 2. • 0 10200495 3. 7-030\ TATE OF a w S OD v 4 'rrSSO�A�tt ,`. e 5. 24.Average of five Peak Daily Demand(PDD)listed above: C. MGD 25.Ratio of PDD to PWS Daily Production Capacity=(Item D=Item Cl Item A x 100) D. 26.Anticipated Customer Demand of Proposed Water Main Residential Customers: E.Number of homes F.Average Daily Demand times Peaking Factor(at least 0.87 Total Average Daily Demand times Peaking Factor(G=E x F) -0- gpm/home) 0.87 G. gpm Other(Commercial and Industrial)Customers: Average Daily Demand(the"Safe Maximum Description(including size of domestic meter): Operating Capacity"of domestic meter) gpm gprn Sub Total: H. gpm Total Customer Demand of Proposed Water Main(gpm)=(Item G+item H) gpm 27.Ratio of total Customer Demand of Proposed Water Main(gpm)to the PWS Daily Production Firm Capacity J (gpm)(Item J=Item II Item B x 100) f0 Page 1 of 2 Indiana Department of Environmental Management 4471-0- , APPLICATION FOR SANITARY SEWER Otficeotl4+ater Quality—Pl�ail Code 65-42 Cam0.t la, c CONSTRUCTION PERMIT PER 327 IAC 3 Facilities construction section State Form 53159(1 i-Q7} 100 North Senate Avenue,Room N 1255 INSTRUCTIONS. Indianapolis,IN 46204-2251 f This form must be filled out completely. 2 Additional pages(attachments following this form)am part of this application form and must be filled out completely. 3 Submission of plans and specifications are part of the application 4 Submit the application form,additional pages,plans and specifications to the above address. 5. if you have any uestions regarding this a aication,call IDEM's Office of Water Quallt at(317 232-8670. M' 7 ;' ' APPLICANT' , APPLICANT'S ENGINEER OR LAND`SURUW CP: A Name Kenneth Brasseur Name James O. Rinehart IV, P.E. Company Name Personal Investments, LLC Company Name Stoeppelwerth & Associates, Inc. Address 9757 Westpoint Drive, Suite 600 Address 7965 East 106th Street Address Indianapolis, Indiana 46256 Address Fishers, Indiana 46038 Telephone number (317) 818-2900 Telephone number (317) 849-5935 NAME AND.=`LOCATION OF PROPOSED:FACILTY•-. `;.. ■ ,.... . 'W, ATTAC1-IMENTCHECKL1ST at,:,° , . , ;t, ., Name The Legacy Corner A Sanitary Sewer Design Summary Form:WrYes Location(Referenced to two existing streets) B Capacity Certification/Allocation Letter:0 Yes Location Southwest corner of 146th Street & River Road C. certificati n of Registered Engineer or Land Surveyor Letter:ill Yes Location D Plans and Speclficetions:0Yes City Carmel E. Identification of Potentially Affected Persons(see note below): Yes County Hamilton F M iiing Labels for Potentially Affected Persons: Yes Note Regarding item(E)above: Fully identify all persons,by name and address, who may be potentially affected by the issuance of this permit, such as adjoining landowners,persons with a propriety interest,andlor persons who have complained or submitted comments about your facility. Under IC 4-21..5- 3-5,MDEM fs required to notify potentially affected persons of its permit decision. .15.ERMIT APPLICATION FOR CONSTRUCTION,EXPANSIONS ,FUNDING : 4 , += "•" OR,MODIFICATION°OF, x ` 2 r ':, '' e (Check all that apply) ,,, • , �`•,,,,,,,,,,,,,,,,,.,,,„ A. Municipal Collection Facility: DYes I SRF Funding: Dyes ViNo B. Semipublic Collection Facility; ❑Yes C. New facility: ❑Yes D. Expansion or modification of existing facility: VA Yes - ,, a CERTIFICATION-AND SIGNATURE xr Application is hereby made for a Permit to authorize the activities described herein. I certify that I am familiar with the information contained in this application and to the best of my knowledge and belief such information is true,complete and accurate. Printed name of person signing Title James 0. Rinehart IV, P.E. Professional Engineer Si.natur- • •g„,....--- Date application signed (month, day,year) -- December 6, 2010 "Please refer to IC 13-30-10 for penalties of submission of false information* P, R i'OF STATE FORM 53109 (i 1-07) Dear Applicant: To complete your construction application, you must submit all of the necessary items.. If your application materials are incomplete, you will be sent a deficiency notice, and your application will be retained for 60 days If the information is not received within the 60 day period your application will be denied due to incompleteness. You can get a copy of this application package on the Internet at: www_in.gov/idem/permits/water/wastewater/construction/index.htmi or www.in.qov/idem/publications/forms/index.html#waterforms. Please complete the following steps (only one copy of the requested documents needs to be submitted): O Request that the utility to which you will be connecting your gravity sewer or force main complete the attached Capacity Certification/Allocation Letter. o A completed Certification of Registered Professional Engineer or Land Surveyor Letter must be completed by the professional engineer or land surveyor who designed and stamped the plans, A copy of this letter is attached. • Complete all the information on the sewer design summary and certify it with a professional engineer's stamp (or land surveyor's stamp for gravity sewer projects), signature and date. • Sign and date the application form and fill it out completely. Municipal projects must be signed by a city or town official_ Others, such as private projects, can be signed by the owner or a representative. • Submit one set of plans with profiles and bedding details. Every page must be stamped and signed by a professional engineer(or land surveyor for gravity sewer projects). • List all affected parties. This list should include: officials of affected counties, cities or towns; adjacent property owners; and all other potentially affected parties,their names and mailing addresses. A competed set of mailing labels with the mailing code of 65-42FC listed above each party on each label is required. • Please be advised that if your project will disturb one (1) or more acres of land area, coverage under 327 IAC 15-5 (Rule 5) is required. Rule 5 is the General Permit for Storm Water Runoff Associated with Construction Activity. You can review the Rule 5 web site for information at: www_in.gov/idem/permits/water/wastewater/wetwthr/storm/rule5.html and/or contact David Carr at 317/233-1864 for more information. Please send construction applications to: Indiana Department of Environmental Management Office of Water Quality- Mail Code 65-42 100 North Senate Avenue, Rm N1255 Indianapolis, IN 46204-2251 Attention: Don Worley Telephone: 317/232-5579 327 IAC 3.5.5 Wastewater Construction Permit Fees (There are currently no fees required for Sewer Projects, either private or public.) • Page 2 of 10 PART OF STATE FORM 53159 111-u7) SANITARY SEWER llg:sp SUMMARY Design Flow - ..Number of units 1 bedroom apartments 200 gpd/unit gpd 2 bedroom apartments 300 gpd/unit gpd Single family homes 310 gpd/unit ` gpd 3 Commercial lots 8,000 gPd gpd gpd Total average flow $ 000 gpd Peaking factor Peak flow 34,320 9Pd Sewer N " ft. 3-inch N/A (sewer type) ti,� rS-rE?4'; f f ft. 10-inch N/A No. 10200495 ft. .- STATE OF ft. s • ft. Total length of sewer `o,��U,�•.!NDiAP°° The new sewer will be connected to an existing 10" -inch diameter it i sanitary sewer at approximately 310'South(referenced to two existing (P.E.or L. .stamp, streets)of 146th Street and approximately 900'East of Community Drive. signature and date) December 6, 2010 Lift Station Type (wet/dry, submersible, wet-well mounted, etc.) Number of pumps —_ Capacity of pumps gpm TDH RPM HP Back-up power source ❑Yes ❑ No Average wet-well detention time I _ — Audio/visual alarm with self-contained power supply or telemetry system Force Main 2,232 feet of 2 -inch (type)A.W.W.A. S.D.R.-21 PVC Force main discharge elevation j 747.36 Waste Treatment Wastewater treatment will be provided by City of Carmel Waste Water Treatment Plant Inspection/Maintenance . . Inspection during construction will be provided by City of Carmel Utilities Maintenance after completion will be provided by City of Carmel Utilities Page 3 of 10 PART OF STATE FORM 53159 (1 i.n ) CAPACITY CERTIFICATION/ALLOCATION LETTER This from must be filled-out in its entirety. Name of applicant Personal Investments, LLC r Name of owner Personal Investments, LLC Name of project The Legacy Corner CERTIFICATION , representing the City of Carmel , in my capacity (Name of individual) (Name of city or town) as have the authority to act on behalf of the City of Carmel (Title) (Name of city or town) certify that I have reviewed and understand the requirements of 327 IAC 3 and that the sanitary collection system proposed, with the submission of this application, plans and specifications, meets all requirements of 327 IAC 3. I certify that the daily flow generated in the area that will be collected by the project system will not cause overflowing or bypassing in the collection system other than NPDES authorized discharge points and that there is sufficient capacity in the receiving water pollution treatment/control facility to treat the additional daily flow and remain in compliance with applicable NPDES permit effluent limitations. I certify that the proposed average flow will not result in hydraulic or organic overload. I certify that the proposed.collection system does not include new combined sewers or a combined sewer extension to existing combined sewers. I certify that the ability for this collection system to comply with 327 !AC 3 is not contingent on water pollution/control facility construction that has not been completed and put into operation. I certify that the project meets all local rules or laws, regulations and ordinances. The information submitted is true, accurate, and complete, to the best of my knowledge and belief. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment Gallons per day (Total Average Flow for Project) Wastewater treatment plant(Name of VWVTP) City of Carmel Waste ater reatment ' an Sewers(Owners of sewers) City of Carmel Utilities Signature Date Signed(rnonfh,day,year) I I (Please refer to IC 13-30-10 for penalties of submission of false information.) Page 4 of 10 PART OF STATE FORM 53159(,11_07) CERTIFICATION OF REGISTERED PROFESSIONAL ENGINEER OR LAND SURVEYOR LETTER This from must be filled-out in its entirety. Name of applicant Personal Investments, LLC • Name of owner Personal Investments, LLC Name of project The Legacy Corner CERTIFICATION I James 0. Rinehart IV , representing the project applicant, in my capacity as a registered (Name of individual) professional Engineer 10200495 certify the (Engineer or Land Surveyor) (Indiana registration number) following under penalty of law: The design of this project has been performed under my direction or supervision to assure conformance with 327 IAC 3 and the plans and specifications require the construction of said project to be performed in conformance with 327 IAC 3-6.The peak daily flow rates, in accordance with 327 IAC 3-6-11 generated from within the specific area that will be collected by the proposed collection system that is the subject of the application, plans, and specifications(when functioning as designed and properly installed), will not cause overflowing or bypassing in the same specific area serviced by the proposed collection system other than from NPDES authorized discharge points The proposed collection system does not include new combined sewers (serving new areas) or a combined sewer extension to existing combined sewers. The sewer at the point of connection is physically in existence and operational.. Based upon information provided by the owner of the Wastewater System, the ability for this collection system to comply with 327 IAC 3 is not contingent on downstream water pollution/control facility construction that has not been completed and put into operation The design of the proposed project meets applicable local rules or laws, regulations and ordinances. The information submitted is true, accurate, and complete, to the best of my knowledge and belief. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment. Gallons per day(Total Average Flow for Project) Wastewater treatment plant(Name of WWTP) City of Carmel Waste Water Treatment Plant Sewers(Owners of sewers) City of Carmel Utilities Date Signed(month,day,year) Signature December 6, 2010 (Please refer to IC 13-30-10 for penalties of submission of false information.) Page 5 of 10 F.!='.I' (.?1=t "!'''•.l E Ffii?Pll 5315 {1'1-071 _.. , r, ' , CTER ,T AMATN.TARttEUVER Ntin SPAT.IKCFfECK SIT, , M ` M„ 1.Application Check here A Applicant's name and address 8 Applicant's Engineer:company name,engineer's name,address,telephone C Name and location of proposed sanitary sewer D Type of collection facility the project will connect to(municipal or semipublic) E.Signature of applicant or authorized agent including date signed • 2.Sanitary Sewer Design Summary _ -- `.Check here A Design flow 1 Multiply number of units by recommended average flow for that type of unit Refer to 327 IAC 3-6-11 design flow rate requirements for collection systems and water pollution treatment/control facilities This is a section of the Article 3 Administrative Code and Is available on the Internet at �( www.in.gov/leeis lative/iac/T03270/A00030.PDF You would need to click under Water and took for Title 327 IAC 3 or Article 3. 2_ Total all average flow and enter total average flow 3. Enter peaking factor.If peaking factor and factor is unknown,a factor of 4 is usually sufficient,however, an exact factor may be calculated from the following equation: Peaking factor= 18+IP Where P is the population in thousands. 4+/F'_ 1. Multiply total average flow by peaking factor and enter product as peak flow 13 Gravity sewer Length and type Please include the length,diameter, and type of sewer pipe with applicable SDR and ASTM specifications, and type of bedding. C Certifiers seal Sanitary Sewer Design Summary should be sealed and signed by a registered professional y( engineer or a land surveyor if no lift station is involved. b� D.Connection Point _ V 1 Diameter of existing sewer at connection point(unless connection point is at a lift station) V 2 Location of connection point relative to an intersection of two(2)streets,i.e.so many feet west and so �{ _ so many feet north of the intersection of street A and street B E Lift station:enter all proposed lift station information,or enter N/A if no lift station Is involved. (if an existing lift station is being directly affected,enter existing lift station information and specify that it is an existing lift station and include its current load).__ I Number and capacity of pumps 2 Provide design calculations for TDI-1 and wet-well detention time {11 3 Provide a graph of the pump curves 4 Specify highest elevation in the force main. 5. Specify force main length,diameter and material(ASTM and SDR),and bedding. �J S. Specify an audio and visual alarm with self contained power supply and telemetry. 7 Specify nature of back-up power source for lift station,if any �] F Waste treatment:enter the name of semipublic or municipal treatment facility which the project will be connecting to:if there is more than one treatment facility in the municipality or sanitary district,please specify which one. G Inspection/Maintenance:please specify name of company,individual or party responsible for inspection during the construction of the project and maintenance of the project after construction is complete. ^_ W 3.Capacity certification/allocation letter Check'hen?... Provide the utility that is treating the wastewater the attached capacity certification/allocation letter,This letter must be filled out in its entirety. 4.Plans and specifications :Check here A. Every page of the plans should be signed and sealed,as well as the cover page for any specifications. 1 Professional engineers who are registered within the state of Indiana are eligible to certify plans and specifications for all types of projects. 2 A land surveyor who is registered within the state of Indiana may certify plans and specifications for gravity type sanitary sewers pny,and may not certify plans and specifications involving lift stations and force mains. Page 6 of 10 IDE STATE FiDir,`I,.i r ::i'iiif i i I..11_. 4.Plans and specifications(continued) Check here • B. The following items are usually necessary for proper technical review of sanitary sewers and lift stations: 1 Plan view of the sewers including minimum ten foot horizontal separations of sewer and water mains, and connection point of the proposed sanitary sewer. 2. Profile view of the,sewers including: slope,invert elevations,existing grade,proposed grade,distances from manhole to manhole,existence of special features,and a minimum of 18-inch vertical separation of sewer and water mains. 3. Where applicable,details of all appurtenances including manholes,drop manholes,inverted siphons,etc • 4 Bedding details for installation of Sanitary Sewer/Force Main: a Rigid pipe:should be class A, B or C as described in ASTM C 12 b Flexible pipe:should be class!,II,or Ill as described in ASTM D 2.321 of 5 Minimum three foot cover depth above the crown of the sanitary sewer force main 6 Automatic Air Relief valves to be placed at all relative high points in the force main to prevent air locking 7 Mechanical joints should be specified for all aerial,river or lake crossings. " Note:construction within a floodway(river,lake,etc)must receive approval from Indiana Department of Natural Resources,Division of Water. 5.A List of names and addresses of all persons or parties who may be potentially affected.by the issuance :. of this project. Please be aware that failure to properly identify and notify these people.could have the..? Check he re.. result of voiding any decision made regarding this permit. A. The applicant must take full responsibility for proper identification of all potentially affected persons or parties. B. The following are the minimum recommendations made by this office made as to who should be included in this list: • 1 All landowners adjacent to the property where the proposed construction is to occur 2 All persons with a substantial and direct proprietary interest in the issuance of this permit,such as, nearby businesses that could have their business in some way affected by the issuance of this Construction Permit. 3 Anyone who is known to have complained or otherwise expressed an interest in this particular project or projects in this specific area. 4 Anyone else whom the applicant may feel that might be potentially affected by the issuance of this cif permit. 6.The Application form must be signed and dated by the applicant or his duly authorized-agent. .. ' Please note that this checklist is only designed to expedite the review process.by assisting the applicant in submission for sanitary sewer construction permits,and In no way is intended to replace the technical review process,nor is it a substitute for the actual Construction Permit. Page 7 of 10 1.1,.1-%1 01- I,•:,,rE 57.;159 j! i 072 IDENTIFICATION OF POTENTIALLY AFFECTED PERSONS Please list any and all persons whom you have reason to believe have a substantial or proprietary interest in this matter, or could otherwise be considered to be potentially affected under law. Failure to notify a person who is later determined to be potentially affected could result in voiding our decision on procedural grounds. To ensure conformance with Administrative Orders and Procedures Act (AOPA), please list all such parties. The letter on the opposite side of this form will further explain the requirements under the AOPA, Attach additional names and addresses on a separate sheet of paper, as needed. Please indicate below the type of agency action you are requesting. Name Please see attached list. Name Address(number and street) Address(number and street) City City Stale ZIP ��— State ZIP Name Name Address(number and street) Address(number and street) City City — State ZIP Slate ZIP Name Name Address(number and street) Address(number and street) City City State ZIP -- State ZIP Name Name Address(number and street) Address(number and street) City City State y� ZIP State ZIP CERTIFICATION I certify that to the best of my knowledge I have listed all potentially affected parties, as defined by IC 4-21.5-3-5. Proposed facility name Printed Name The Legacy Corner James O. Rinehart IV City Carmel — -- Signature `' County Hamilton e(month, day, year) December 6, 2010 Page 8 of 10 PART OF STATE FORM 53159 i'i r-9;1 IDENTIFICATION OF POTENTIALLY AFFECTED PERSONS (continued) To: Applicant Subject: Identification of Potentially Affected Persons The Administrative Adjudication Act. IC 4-21.5-3-5. requires that the Indiana Department of Environmental Management(IDEM) give notice of its decision on your application to the following persons: e Each person to whom the decision is specifically directed; o Each person to whom a law requires notice be given; • Each competitor who has applied to the IDEM for a mutually exclusive license, if issuance is the subject of the decision and the competitor's application has not been denied in an order for which all rights to judicial review have been waived or exhausted; a Each person who has provided the IDEM with written request for notification of the decision; a Each person who has a substantial and direct proprietary interest in the issuance of the (permit) (variance); a Each person whose absence as a party in the proceeding concerning the (permit)(variance) decision would deny another party complete relief in the proceeding or who claims an interest related to the issuance of the (permit) (variance) and is so situated that the disposition of the matter, in the person's absence may: (1) As a practical matter impair or impede the person's ability to protect that interest, or (2) Leave any other person who is a party to a proceeding concerning the permit subject to a substantial risk of incurring multiple or otherwise inconsistent obligations by reason of the person's claimed interest. Under IC 4-21.5-3-5 (f) IDEM is requesting your assistance in identifying potentially affected persons. IC 13-15-3-1 requires IDEM to provide notice of receipt of a permit application to the following: 1. The county executive of a county affected by a permit application, 2. The executive of a city affected by a permit application, 3. The executive of a town council of a town affected by a permit application. Under IC 13-15-3-1 (b) IDEM is requesting information necessary to provide such notice to the • appropriate officials. Page 9 of 10 PART OF STATE FORM 53159(11-07) IDENTIFICATION OF POTENTIALLY AFFECTED PERSONS (continued) Attention: Since June 17, 1999, mailing labels are required to be submitted with your project. Having these labels with your application is helpful to you as well as our office. These mailing labels need to have the names and addresses of the affected parties along with our mailing code (which is 65-42FC) listed above each affected party listing. For Example: 65-42FC JOHN DEERE 111 CIRCLE DR YOUR CITY IN 44444 Page 10 of 10 Easy Pee®Label, i A 02'-' 11 Bend along line to ■ r� ■ Use Avery Template 5160 reed Paper E..' „f"." expose Pop-Up Edgend ' ----. U 5 16U A 65-42FC 65-42FC 65-42FC Eartham College East Cannel, LLC Emil M. &Patrica Aim Spencer 13400 Allisonville Road 9757 Westpoint Drive, Suite 600 1318 East 126`11 Street Fishers, Indiana 46038 Indianapolis, Indiana 46256 Carmel., Indiana 46033 65-42FC 65-42FC 65-42FC Board ol'Commissioners Hamilton County Marvin B. & Sherry L. Klein. Melrock.Farms, LLC 33 North 9111 Street, Suite L-21 7718 East 146th Street 14740 River Avenue Noblesville, Indiana 46060 Noblesville, Indiana 46062 Noblesville, Indiana 46062 65-42FC 65-42FC Chester Kopinski Winding Way Mobile I-lane Court,Inc. 65-42FC 7678 East 1461h Street 14740.River Avenue sr;lt>hl-.n-snDLMNf,ticctabels I2/07/1 n Noblesville, Indiana 46062 Noblesville,Indiana 46062 • Etiquettes ladles a peter �� a-oliez ff to hachure arid de' www.averv.cO1n ' (rr r r 1 Sens de. Y'6i I f Utilise le gabarit AVERY- 5160® cttargr.rraerti+ ri tiler le rebord Pop-Up 1-800-GO-AVERY Conn, Angelina V From: Betsy Bredlau [mbredlau@Stoeppelwerth.com] Sent: Tuesday, December 07, 2010 1:56 PM To: Conn, Angelina V; Pace, Paul V; Tim Walter Cc: Brett Huff Subject: The Legacy Corner Attachments: CarmelUtilitiesDuffyl 2-07-10.pdf To all, Attached please find your copy of a submittal being delivered this afternoon. If you have any questions, please give Brett Huff a call at(317) 577-4841. Thank you, Betsy Bredlau STOEPPELWERT.H & ASSOCIATES, INC. Direct Line(317)570-4708 Direct Fax(317)570-4728 mbredlau@stoeppetwerth.com Please consider the environment before printing this e-mail E 1 Conn, Angelina V From: Thomas, John G Sent: Tuesday, December 07, 2010 11:09 AM To: Eric Carter Subject: The Legacy Corner Good morning Eric, I reviewed the Legacy Corner Plans/Turkey Hill Minit Market and have the following comments; 1. It is difficult to determine everything that is being built for this project based on the submitted plans. Please provide a master plan sheet that shows all intended areas of disturbance and the respective construction limits for everything that the developer is seeking approval. 2. This project lies within the 1 year time of travel of wells operated by multiple entities. Some of these entities may have more restrictive UST regulations than Carmel. The Hamilton County Wellhead Protection Committee has placed this item on their agenda for discussion at the next meeting in January. It will also be on the City of Carmel's Wellhead Protection Local Planning Team agenda in February. Please note that final SWPPP approval will be determined after the meetings and any findings may have a bearing on final SWPPP approval. 3. It appears that portions of this project will impact the floodplain. None of the downstream Legacy master infrastructure has been installed and we have never approved the master plan upon which this project seems to be depending. Fill/ detention in the floodplain will need to be mitigated in the areas reserved for the mitigation. How will this be addressed? 4. Please submit the "Overall Drainage and Water Quality Master Plan" for Legacy that was referenced in the drainage report. 5. Are the storm structures sized large enough to contain the Snout w/Bioskirt BM Ps? 6. How will the Car Wash wastewater be handled? Are settling tanks proposed? If so, will these tanks be pressure tested or placed in an excavation with an impermeable liner? 7. Additional measures should be implemented to prevent leakage of stormwater from storm lines and storm structures. a. Can a sanitary grade pipe be used in lieu of traditional RCP between storm structures susceptible to fueling spills (bwt snout structures and stormceptor)? b. Can the snout structures and stormceptor be sealed and pressure tested or placed in excavations with an impermeable liner? c. Can an impermeable "ripley dam" or equivalent be used to seal off the storm sewer stone bedding at the end of the storm run (downstream of the stormceptor)? 8. Secondary containment will be needed on the USTs and piping since the fueling station is located in a one year TOT. Please verify this with the developer and indicate this in the SWPPP language, item #5 - Identification of Potential Discharge to Ground Water. 9. Please provide SWPPP plan sheets showing stormwater controls that address the proposed disturbance in the Williams Creek Plans. The SW PPP language will be reviewed after I receive plans sheets/ response letter addressing these comments. Sincerely, John Thomas, CPESC Stormwater Administrator City of Carmel Engineering Department (p)317-571-2314 1 December 7 2010 1" Submittal ! sr Mr. James K. Shinneman, PE D A 1 �� p D�� � �SCr{� Weihe Engineers �!,, �;• 10505 N. College Avenue IttiggSitOMI Indianapolis, IN 46280 4ENG9NEERS;1IP[; RE: Turkey Hill Minit Markets Legacy Corner-Store 14604 Technical Advisory Committee Engineering Review for Development Drainage Designs Dear Mr. Shinneman: The stormwater review of the proposed construction plans and drainage calculations for the above referenced project has been completed. The submittal is in need of additional information in order to be in compliance with the City of Carmel Stormwater Technical Standard Manual (the manual). Please revise the plans in accordance with the comments below. 1. Please provide a copy of Sheet 1 of 1, ALTA/ACSM Land Title Survey, as indicated on the Title Sheet. 2. It appears that there are leader lines for information / notes that are cut-off by the viewport on Sheet C101 (Weihe). Please review and revise as necessary. 3. Per Section 102.02.vii., please provide storm sewer plan and profiles in accordance with all requirements of this section for the on-site Turkey Hill storm sewer network (Weihe plans). 4. Per Section 102.02.xi., please revise the Grading and Drainage Plan, Sheet C103 (Weihe plans), to include the following information: c. One hundred (100) year floodpla ins, floodway fringes, and floodways, established or identified in accordance with the City of Carmel Flood Hazard Area Ordinance. Please note if none exist. g. 100-year overflow paths/ponding areas shown as hatched areas, along with associated easements. The 100-year overflow paths and associated easements shall be included for on- site storm, off-site storm, and constructed wetland areas. m. The Discharge Summary for the Turkey Hill Minit Market development on Sheet C103 (Weihe) should be revised to also include on-site post-developed release rates, actual post-developed curve number, time of concentration, etc. Also, please revise Sheet SA6 (Stoepplewerth) to include a Drainage Summary for the master planned Legacy - Eastern Basin detention system and Legacy Corner developments per this section. 5. Per Section 102.02.xiv., please provide a Structure Data Table for the off-site (Legacy Corner) storm sewer network(Stoepplewerth plans). 6. Per Section 102.03.i.d., please revise the drainage report to include the following information: i. Revise the "Storm Sewers" map within Section 3 of the report (Weihe) to add both runoff coefficients("C"values) and runoff curve numbers (CN) for each drainage basin. rurke} 1 Till NIluil Market-Legacy Corner Weihe Engineers December 7 2010 Page I o13 _ ._ _ . 3417 Sherman Drive o Beech Grave. Indiana 46107 a Tel 317.780.1555 ® Fax 317.780•6525 —- — — ii. Inlet grate design, including gutter spread calculations for the Turkey Hill on-site storm sewer system (Weihe). 7. Per Section 104.02, the building's lowest entry elevation that is adjacent to and facing a road shall be a minimum on 15 inches above the road elevation. Please review and revise as necessary. 8. The Rangeline Road removal notes on Sheet C101 (Weihe) should be removed as they are not applicable. 9. It appears that Str. #502 and 503 are mislabeled on the profile view on Sheet SAG (Stoepplewerth). Please review and revise accordingly. 10. Please verify if the Turkey Hill Minit Market developed will be platted, and if so, please submit a copy of the Secondary Plat. It appears that there are multiple drainage and access easements that need to be included for the development. Street 'E3' shall have an access easement to provide access to the proposed water quality easement. Also, it appears that the storm sewer system for the Turkey Hill Minit Market will be connected to the proposed Legacy Corner storm sewer system outside of the Turkey Hill property lines. Please provide verification of approval for connection to the proposed Legacy Corner storm sewer. And finally, please provide drainage easements for the storm sewer infrastructure within Street 'A' (in addition to the provided access and utility easement), for the constructed wetlands west of the site, and for the routed overflow path to the constructed wetlands (see Comment#14). I I. Per Section 501.01, there should be no less than 2.50 feet of cover along any part of the pipe from final pavement elevation or final ground surface elevation to the top of pipe. It appears that there are multiple on-site Turkey Hill storm sewer structures(Weihe) that are not in conformance. Please review and revise all structures as necessary. Any waiver request for this design standard shall be submitted directly to the City of Carmel Engineering Department. 12. Per Section 305.04, the maximum velocity resulting within any storm pipe flowing at full capacity shall be 10 feet per second. Please review and revise Str.#203 (Weihe) accordingly. 13. It appears that the "Proposed Weighted Watershed" calculations within Section 3 of the drainage report (Weihe) do not correspond to the acreages indicated on the table on Sheet C103 (Weihe)of the plans and within the "Proposed Conditions Weighted RC" calculations in the drainage report. Please review and revise accordingly. 14. Per Section 303.07, please indicate on the plans the ponding / overflow path throughout the development resulting from a 100-year storm event, calculated based on all contributing drainage areas, on-site and off-site, in proposed conditions with the storm pipe system assumed to be completely plugged. This overflow path shall be clearly shown on the plans and contained within a 30 feet permanent drainage easement along the centerline of the overflow path. It is anticipated that the resulting highest overflow / ponding elevations will be higher than the resulting peak 100-year elevations in the overall Legacy detention system; therefore, shall be the elevation used in MFPG and MLAG calculations. 15. It appears that there are no drainage / sizing calculations provided for the constructed wetland emergency spillway. Please provide drainage calculations for the proposed emergency spillway. Turkey hill Minit Market-Legacy Corner Weihe Engineers December 7 2010 Page 2 of 3 I 16. Please further discuss and indicate on the plans how the proposed storm sewer system will be conveyed downstream of the constructed wetland, and how all stormwater discharge within the Legacy development is conveyed to the overall master planned detention system. Please review and revise as necessary. Please include with your submittal, one (1) copy of the comments indicating the action taken or a written explanation for action not taken. Construction plans and drainage calculations are not to be re-submitted without implementing changes with respect to any and all review comments from the City of Carmel and the Hamilton County Surveyor's Office. The comments and plans may be submitted to my attention at the following address: CrossRoad Engineers, P.C. 3417 South Sherman Drive. Beech Grove, IN 46107 Please contact me at (317) 780-1555 ext. 140 with any questions. Sincerely, CrossRoad Engineers, P.C. William Hall, P. . Project Engineer copy: Gary Duncan, City of Carmel Assistant Engineer Greg Hoyes, Hamilton County Surveyors Office File Turkey 11111 N1init A4arkei-Legacy Corner \Vedic Engineers December 7 2010 Page 3 of 3 C1) of cannel Carmel Police Dep&ri rnent 3 Civic Square Carmel, Indiana 46 32 HECEIVED DEC -22010 DOCS November 30, 2010 Mr. Eric Carter Weihe Engineers, INC. 10505 N. College Avenue Indianapolis, IN 46280 RE: Turkey Hill Minit Markets Store #604 Job number: W090633 Dear Mr. Carter: The above mentioned project has been received and reviewed. At the present time, I see nothing in the plans that would hamper law enforcement efforts. If we can be of any further assistance to you, please contact us. Respectfully, Michael D. Foga Chief of Police MDF:vb cc: Dept. of Community Services (317) 5711-2500 A Nationally Accredited Law Enforcement Agency Fax(317)5711-2612 Conn, Angelina V From: Eric Carter [cartere @weihe.net] Sent: Monday, November 29, 2010 11:03 AM To: Mindham, Daren Cc: Conn, Angelina V;jond @NF-LAW.COM; Charlie Frankenberger; steve.tuller @minitmarkets.com; Tim Walter (E-mail);Jamie Shinneman Subject: RE: Docket No. Assignment: 10110012 DP/ADLS& 10110013 ZW - Turkey Hill @ Legacy Hi Daren.- See my responses below. Thank you, Eric A. Carter, R.L.A.,ASLA Project Manager, Commercial Development Weihe Engineers, Inc. 317 1 846-6611 weihe.net Original Message From: Mindham, Daren imailto:dmindham @carmel.in.00vl Sent: Tuesday, November 23, 2010 2:01 PM To:jond @NF-LAW.COM; Charlie Frankenberger; Eric Carter; steve.fuller @minitmarkets.com Subject: Docket No. Assignment: 10110012 DP/ADLS & 10110013 ZW - Turkey Hill @ Legacy Eric, The following email represents comments for this project specifically addressing the area of urban forestry. I have reviewed the drawings and offer the following comments: URBAN FORESTRY REVIEW COMMENTS L101+L201 1) I would like to have the attached Carmel planting details used in City of Carmel projects. However, the details submitted will suffice. - Noted. 2) Under Landscape Recommendations (Legacy PUD) - I am not sure where the 23F.11 requirement is referring to. Can you reference that for me? Ignore it.. It is referring the the Carmel Rangeline Overlay and we obviously missed removing it from this sheet. SP2+SP3 1) I see this wetland area as perfect place to showcase some bald cypress and River birch. I will have to veto the honey locust and the red maple cultivars when ideal natives would so thrive. The construction documents have been revised to include the requested species. (from Williams Creeki Otherwise, these plans look really well thought out. Please illustrate how these comments will be addressed by letter or revised plan. If you have any questions, feel free to contact me.Thanks. Sincerely, Daren Mindham Urban Forester City of Carmel Department of Community Services One Civic Square 1 Carmel, Indiana 46 032 Office:317-571-2283 ***The true meaning of life is to plant trees, under whose shade you do not expect to sit. —Nelson Henderson 2 • S NELSON & FRANKENBERGER A PROFESSIONAL CORPORATION ATTORNEYS AT LAW JAMES J.NELSON 3105 EAST 98TH STREET, SUITE 170 JANE B.MERRILL, CHARLES D.FRANKENBERGER INDIANAPOLIS, INDIANA 46280 Of Counsel JAMES E.SHINAVER LAWRENCE J.KEMPER PHONE: 317-844-0106 JOHN B.FLATT FACSIMILE: 317-846-8782 JON C.DOBOSIEWICZ, FREDRIC LAWRENCE Land Use Professional JAMES A.NICKLOY CHRISTOPHER A.FERGUSON A November 19, 2010 4t4 Angie Conn 192010 City of Carmel D®C8 One Civic Square Carmel, IN 46032 Re: Turkey Hill Minit Market—7729 East 146th Street Dear Angie: Enclosed you will find applications for DP, ADLS and Zoning Waiver approval. The engineer has affected the TAC distribution, and our anticipated schedule is as follows: December 15 TAC January 18 Plan Commission Public Hearing February 1 Special Studies Committee February 15 Plan Commission (if forwarded out of February 1 committee) We will soon be conferring with you to discuss the Zoning Waiver request. Should you have any questions regarding this, please do not hesitate to call. Very truly yours, NELSON & FRANKENBERGER, P.C. Jon C. Dobosiewicz Land Use Professional Enclosures TH Legacy-Ltr to A Conn 111910 oriEuokra WFIIHFI ENGINEERS �A Land Sep/eying Clv:f Engincerinn Landscape ape AT,lntecturc __- RECEIVED ,tt ./, , r: ;{. ti ti c- Nov 192010 TRANSMITTAL DOCS To: Dept of Community Services(DOCS) Project Turkey Hill Minit Markets Store#604 One Civic Square, 3"1 Fir Job#: W090633 Carmel, IN 46032 Phone: 317-571-2417 Attn: Angie Conn/Christine Barton-Holmes Fax: 317-571-2426 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached❑ Under separate cover via Delivered the following items: ❑ Shop Drawings ❑ Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s) for Payment ® Sets Document Document Description ❑ Copies Date Number 2 Construction Plans These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis.IN 46280 wcihc.net 317 1 846-6611 300!452—6408 Fax:317 i 843-0546 Allan H.N'cihe,P.E.,1_.S.-President 1111 WEIHE ENGINEERS = :;d S urveynq, Civ Er n<erina Landsozpe A :Kai re • • TRANSMITTAL To: Vectren Energy Project. Turkey Hill Minit Markets Store#604 P.O. Box 1700 Job#: W090633 Noblesville, IN 46061 Phone: 317-776-5535 Ann: Chuck Shupperd Fax: 317-776-5553 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached❑ Under separate cover via UPS the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set 1 Digital File • These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review&Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 wcihc.net 317 1 846—6611 800 1 452—6408 Fax:317 1 843—0546 Allan H.Weibe,P.E.,t_.5.—President i x WEIHE ENGINEERS Land S!.il vE:i'iLiC:'CM: _ gi e;ii'g TRANSMITTAL To: Carmel/Clay Parks Department Project Turkey Hill Minit Markets Store#604 1411 E. 116th Street Job#: W090633 Carmel, IN 46032 Phone: 317-848-7275 Attn: Mark Westermeier Fax: 317-571-2468 Date: 19 November 2010 Re: TAG Construction Plan Submittal We are sending you®Attached❑ Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑Meeting Minutes ❑ Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set • These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review & Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis.IN 46280 weihc.net 317 1 846-6611 8001 453-6408 Fax:3171 843-0546 Allan H.Weihe,P.E.,I_.S.-President • C WFIHF, ENGINEERS Calf?Sur,:e^. 1`,€Civil _r;o net=tr nc! Landscapa ArthitE;cture TRANSMITTAL To: Carmel Clay Schools Project Turkey Hill Minit Markets Store#604 5201 East 131st Street Job#: W090633 Carmel, IN 46033 Phone: 317-844-9961 Attn: Ron Fanand Fax: 317-844-9965 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached❑ Under separate cover via Delivered the following items: n Shop Drawings n Prints n Copy of Letter ❑ Product Data ❑ Specifications ❑ Meeting Minutes n Samples n Change Order(s) .❑ Inspection Report ❑ n Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description n Copies Date Number 1 Construction Set These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use n Approved as Noted ®For Your Review&Comment ❑Not Approved,Revise and Resubmit n As Requested ❑Action Not Required n For Your Records ❑Action Indicated on Item Transmitted n For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis.IN 46380 weihc.net 317 1 846-6611 8001 452-6408 Fax:3171 843-0546 Allan H.Weihe,i'.E.,f_.5.-President WEIHFI ENGINEERS Land Suirveyin' Civil EngineedI q Landscape \uch ii ctu re ''VTC ■T 1 RA SM TTAL To: Carmel Engineering Dept Project Turkey Hill Minit Markets Store#604 One Civic Square, 1st Fl Job#: W090633 Carmel,IN 46032 Phone: 317-571-2441 Attu: John Thomas,Storm Water Administrator Fax 317-571-2439 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached ❑Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑Product Data ❑ Specifications ❑Meeting Minutes ❑ Samples ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set 1 Drainage Calculations and O&M Manual These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required .❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By:Eric Carter cc: • 10505 N.College Avenue Indianapolis,IN 46280 wcihe.net 317 1 546-6611 800!452-6408 ? Fax:317 I 843-0546 Allan FL\Veihe,P.E.,L.S.-President r WEIHF ENGINEERS Lane$urveyi ,_.i C--i._Engineering Lc.._i3Ca lie A rc rill e,. re TRANSMITTAL To: Carmel Engineering Dept. Project Turkey Hill Minit Markets Store#604 One Civic Square, 1st Floor Job#: W090633 Carmel, IN 46032 Phone: 317-571-2441 Attn: Gary Duncan/Nick Redden Fax: 317-571-2439 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ®Attached ❑ Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑Product Data ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 2 Construction Plans 1 Drainage Report and O&M Manual 1 Plan Certification These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review & Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 weihc.ntt 317 1 846-661 I 800 1 452-6408 : Fax:317 1 843-0546 Allan H.Weihe,P.E.,L.S.-President Ema wEIHE ENGINEERS Land Sur vey:n i Civi! Engine (inns La it S cape A-:',its 6 t i L „ .. 'r 'r;.7 r C TRANSMITTAL To: Carmel Street Department Project Turkey Hill Minit Markets Store#604 3400 W. 131 st Job#: W090633 Westfield, IN 46074 Phone: 317-733-2001 Attn: Dave Huffman Fax: 317-733-2005 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you®Attached n Under separate cover via Delivered the following items: n Shop Drawings ❑Prints n Copy of Letter ❑ Product Data n Specifications n Meeting Minutes n Samples ❑ Change Order(s) ❑ Inspection Report n Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set These are transmitted as indicated below: ❑Approved n For Your Review or Use n Approved as Noted ® For Your Review& Comment LI Not Approved,Revise and Resubmit n As Requested n Action Not Required ❑ For Your Records• n Action Indicated on Item Transmitted n For Your Approval n For Signature. Return Copies to Us Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Aeenue Indianapolis,IN 46280 w'eihe.net 317 1 846—6611 8001 452—6408 Fox:3171 843—0546 Allan H.W'cihe,P.F.,I_S.—President [. I WEIHE ENGINEERS _an,_�..ur;!ev ng`c .,. L., er(rlcl La: __ -Aron it ec ure TRANSMITTAL To: City of Carmel -Information Systems Project Turkey Hill Minit Markets Store#604 Three Civic Square Job#: W090633 Carmel, IN 46032 Phone: 317-571-2565 Attn: Terry Krueskamp Fax: 317-571-2568 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached❑ Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ❑ Sets Document Document Description Copies Date Number 1 Digital File These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 weihe.net . 317 1 546—6611 8001 452—6403 Fax:3171 843—0546 Allan H.Weihe,P.E.,L.S.—President ti E WFIHE I ENGINEERS Land Surveying; Eroineerinq Lei€dsc2pe Archiiectur Build uitfit. . Ci fir<c-!:c' • TRANSMITTAL To: Crossroad Engineers Project Turkey Hill Minit Markets Store#604 3417 South Sherman Drive Job#: W090633 Beech Grove, IN 46107 Phone: 317-780-1555 Attn: Gregory Ilko,PE Fax 317-780-6525 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you®Attached n Under separate cover via UPS the following items: n Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑ Meeting Minutes n Samples ❑ Change Order(s) ❑ Inspection Report ❑ n Sketches/Drawings n Application(s)for Payment ® Sets Document Document Description n Copies Date Number 1 Construction Set 1 Drainage Calculations and O&M Manual These are transmitted as indicated below: n Approved ❑ For Your Review or Use Fl Approved as Noted ®For Your Review& Comment ❑Not Approved,Revise and Resubmit n As Requested n Action Not Required n For Your Records ❑Action Indicated on Item Transmitted n For Your Approval n For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 1050=N.College.Avenue Indianapolis.IN 46280 weihe.nct 317 1 846-6611 800 1 452-6408 Fax:3171 843-0546 Allan H.Wale,P.E.,L.S.-President � 1 WEIHE ENGINEERS Land Sutveyi c Civii Enoi;eedna Landscape Architec ui c TRANSMITTAL To: Clay Township Regional Waste District Project Turkey Hill Minit Markets Store#604 10701 North College Avenue, Suite A Job#: W090633 Indianapolis, IN 46280 Phone: 317-844-9200 Attn: Ryan Hartman Fax: 317-844-9203 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached ❑Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑Product Data ❑ Specifications ❑Meeting Minutes ❑ Samples ❑ Change Order(s) ❑Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set These are transmitted as indicated below: ❑Approved ❑For Your Review or Use ❑Approved as Noted ® For Your Review &Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College.Avenue Indianapolis,IN 46280 wcihe.nct 317 1 846—6611 800 452—6408 Fax:317 1 843—0546 Allan H.■ cihc,P.E.,L.S.—President WEIHE ENGINEERS Land Slj :'eying(C:Ivii Encirieerincl r ds_,pe Architecture i. ... / i,h c0 n./.1 d.. .:c TRANSMITTAL To: Deputy Building Commissioner Project Turkey Hill Minit Markets Store#604 One Civic Square Job#: W090633 Carmel, IN 46032 Phone: 317-571-2444 Attn: Bill Hohlt Fax 317-571-2499 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ® Attached ❑ Under separate cover via Delivered the following items: n Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑Meeting Minutes n Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment • ® Sets Document Document Description ❑ Copies Date Number 1 Construction Plans These are transmitted as indicated below: ❑Approved ❑For Your Review or Use ri Approved as Noted ® For Your Review&Comment Fl Not Approved,Revise and Resubmit ❑As Requested n Action Not Required ❑ For Your Records n Action Indicated on Item Transmitted ❑ For Your Approval n For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis.IN 46280 weihe.net 317 1 846-6611 8001 452-6408 Fax:3171 843-0546 Allan H.Weihe,P.E.,L.S.-President WEIHF ENGINEERS Laid Surveyiii:i=M:Errcine;vr no LandE-cape Architecture TRANSMITTAL SMI l 1A1J To: Dept. of Community Services (DOCS) Project Turkey Hill Minit Markets Store#604 One Civic Square, 3`d Fir Job#: W090633 Cannel, IN 46032 Phone: 317-571-2417 Attn: Angie Conn/Christine Barton-Holmes Fax: 317-571-2426 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ®Attached❑ Under separate cover via Delivered the following items: n Shop Drawings n Prints ❑ Copy of Letter ❑ Product Data n Specifications ❑ Meeting Minutes n Samples ❑ Change Order(s) n Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 2 Construction Plans These are transmitted as indicated below: n Approved ❑ For Your Review or Use n Approved as Noted ® For Your Review&Comment n Not Approved,Revise and Resubmit n As Requested n Action Not Required ❑ For Your Records n Action Indicated on Item Transmitted ❑ For Your Approval n For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 weihe.nct 317 1 846-6611 800 i 452-6408 . Fax:3171 843-0546 Allan H.Weihe,P.F.,L.S.-President WFIHF ENGINEERS Lan C....E na i!aia na Landscape Architecture TRANSMITTAL To: Urban Forestry-DOCS Project Turkey Hill Minit Markets Store#604 One Civic Square, 3'" Fir Job#: W090633 Carmel, IN 46032 Phone: 317-571-2478 Atm: Scott Brewer,City Forester Fax 317-571-2426 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached ❑ Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑Meeting Minutes ❑ Samples ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Plans These are transmitted as indicated below: ❑Approved ❑For Your Review or Use ❑Approved as Noted ® For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 wcihe.nct 317 1 846-6611 8001 452-6408 Fax:3171 843-0546 Allan H.Wolin:,P.E.,1_5.-Presidein � a WEIHE ENGINEERS Lend Surveyinc.)1CMI Engineering Landscape Architecture hitectur'e lid with c. J i f f TRANSMITTAL To: Duke Energy Indiana, Inc. Project Turkey Hill Minit Markets Store#604 WF500/27227 Central Ave. Job#: W090633 Columbus, IN 47201 Phone: 812-447-2351 Attu: Gary McNamee,Asset Protection Associate Fax: 812-375-2014 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached❑Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑Product Data ❑ Specifications ❑Meeting Minutes ❑ Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set These are transmitted as indicated below: • ❑Approved ❑ For Your Review or Use ❑Approved as Noted ®For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 weihc.net 317 1 846-6611 800 1 452-6408 Fax:3171 843-0546 Allan H.Wcihc,P.F.,L.S.-President omp WF.IHF, ENGINEERS Land Suriei irici Civil ` r laineerino La.ndsca '&. Architecture TRANSMITTAL To: Duke Energy Project Turkey Hill Minit Markets Store#604 16475 Southpark Drive Job#: W090633 Westfield, IN 46074 Phone: 317-896-6711 Attn: Shirley Hunter Fax: 317-896-6712 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ®Attached❑ Under separate cover via UPS the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter n Product Data ❑ Specifications (� Samples El Meeting Minutes ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description n Copies Date Number • 1 Construction Set 1 Digital File These are transmitted as indicated below: ❑Approved ❑For Your Review or Use ❑Approved as Noted ®For Your Review& Comment n Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 weihe.net ; 317 1 846—6611 8001 452—6408 Fax:3171 843—(1546 Allan H.Vkihc,P.E.,L.S.—President } 1111 WEIHE ENGINEERS Land :I 'feyi;;i i Civii!_ra`nc-;erift_, Landscape Archit_.oture 'TRANSMITTAL To: Office of Fire Chief, Fire Station#1 Project Turkey Hilt Minit Markets Store#604 Two Civic Square Job#: W090633 Carmel, IN 46032 Phone: 317-571-2600 Attn: Chris Ellison Fax: 317-571-2615 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached❑ Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑Change Order(s) ❑Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Plans These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 1050=N.College Avenue Indianapolis.IN 46280 weihc.nct 317 1 846-661 l 8001 452-64118 Fax:3171 843-0546 Allan H.Weihe,P.E.,L.S.-President OP WEIHF ENGINEERS _anti Surve ina Civil Engin e ring Landscape Architecture S1. ii;i 11.tt1. r:IITi;?r;, ._ c.. TRANSMITTAL To: Hamilton County Health Department Project Turkey Hill Minit Markets Store#604 One Hamilton Square,Suite 30 Job#: W090633 Noblesville, IN 46060 Phone: 317-776-8500 Attn: Jason Lemaster Fax: 317-776-8506 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ® Attached ❑ Under separate cover via UPS the following items: n Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data n Specifications ❑ Meeting Minutes n Samples ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings n Application(s)for Payment ® Sets Document Document Description n Copies Date Number 1 Construction Set These are transmitted as indicated below: n Approved n For Your Review or Use n Approved as Noted ®For Your Review& Comment n Not Approved,Revise and Resubmit n As Requested n Action Not Required ❑ For Your Records n Action Indicated on Item Transmitted ❑ For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 wcihc.nct ; 317 1 846-6611 800 1 452-6408 Fax:3171 843-0546 Allan H.Weihe,P.E.,L.S.-Presidcni I WEIR ENGINEERS Land ur,.evina CM:Engineeril-,Q Larldsc2pe A.t,hitecture TRANSMITTAL To: Hamilton County Highway Dept. Project Turkey Hill Minit Markets Store#604 1700 South 10th Street Job#: W090633 Noblesville, IN 46060 Phone: 317-773-7770 Attn: David Lucas Fax: 317-776-9814 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached ❑ Under separate cover via Delivered the following items: n Shop Drawings ❑Prints ❑ Copy of Letter n Product Data ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ® For Your Review& Comment n Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 • weihc.net 3171 846—6611 800 1 452—6408 Fax:31 7 1 843—0546 Allan H.Wcihe,P.F.,L.S.—President • WF.IHE ENGINEERS Lend Chi's iw:j OMi Engineering Landscape Architecture Landscape r.:7/.'e ;a'J, i i _ ail i fi P: , TRANSMITTAL To: Hamilton County Sheriff's Office Project Turkey Hill Minit Markets Store#604 18100 Cumberland Road Job#: W090633 Noblesville, IN 46060 Phone: 317-773-1872 Attn: Broke Gajawnik Fax: 317-776-9896 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ® Attached ❑ Under separate cover via UPS the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter H Product Data ❑ Specifications ❑Meeting Minutes n Samples ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description n Copies Date Number 1 Construction Set These are transmitted as indicated below: ❑Approved ❑Approved as Noted ❑ For Your Review or Use ® For Your Review& Comment ❑Not Approved,Revise and Resubmit n As Requested ❑Action Not Required n For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval n For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 ; wcihe.net 3171 846-6611 800 1 452-6408 Fax:3171 843-0546 Allan H.Weihe,P.E.,L.S.-President • gird IATEIH , ENGINEERS Land Surveying 1 Civii Engineering :_scow AIChi ec ure TRANSMITTAL To: Hamilton County Surveyor's Office Project Turkey Hill Minit Markets Store#604 One Hamilton Square,Suite 188 Job#: W090633 Noblesville, IN 46060 Phone: 317-776-8495 Attn Greg Noyes Fax: 317-776-9628 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you®Attached ❑ Under separate cover via UPS the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑Product Data ❑ Specifications ❑ Samples ❑Meeting Minutes ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set 1 Drainage Calculations These are transmitted as indicated below: ❑Approved ❑For Your Review or Use ❑Approved as Noted ®For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑For Your Records ❑Action Indicated on Item Transmitted ❑For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 w•cihe.net , 3171846-6611 8001452-6408 Fax:317 I 843—0546 Allan H.Weihc,P.F.,L.S.—President • • 1��-1 'F.IHF ��1 ENGINEERS Land Surveyi- t Civii Prigineerin9 A phifec ure: TRANSMITTAL To: Indianapolis Power and Light Company Project Turkey Hill Minit Markets Store#604 1230 W. Morris Street Job#: W090633 Indianapolis, IN 46221 Phone: 317-261-5497 Attn: Dan Davenport Fax: 317-261-5201 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you®Attached ❑ Under separate cover via Courier the following items: ❑ Shop Drawings ❑Prints ❑ Product Data ❑ Copy of Letter ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use ❑Approved as Noted ®For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑ For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 1050=N.College Avenue Indianapolis,IN 46250 weihe.nct 3171 846—6611 8001 452_6408 Fax:3171 843—0546 Allan H.\Vedic,P.E.,I_.S.—President , "s WE IHE ENGINEERS Land Sunievine Clvil Ert ineeerino Landscape Arch Itecture TRANSMITTAL To: Office of Police Chief Project Turkey Hill Minit Markets Store#604 Three Civic Square Job#: W090633 Cannel,IN 46032 Phone: 317-571-2500 Attn: Michael Fogarty Fax: 317-571-2512 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ®Attached❑ Under separate cover via Delivered the following items: H Shop Drawings n Prints ❑ n Copy of Letter Product Data ❑ Specifications ❑ Meeting Minutes n Samples ❑ Change Order(s) 11 Inspection Report ❑ ❑ Sketches/Drawings n Application(s)for Payment ® Sets Document Document Description n Copies Date Number 1 Construction Plans These are transmitted as indicated below: n Approved n Approved as Noted n For Your Review or Use ® For Your Review& Comment n Not Approved,Revise and Resubmit n As Requested n Action Not Required ❑ For Your Records H Action Indicated on Item Transmitted ❑ For Your Approval n For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 . wcilic.nct 317 I 846—6611 800 1 452—6408 Fax:3171 843—0546 Allan H.Wcihe,P.F.,L.S.—President rI a LII WEIHE ENGINEERS vey ' v Land Ur _,.nw i r;,-i! Frrineeru • Landscape Architecture �. w:, h confidence': TRANSMITTAL To: Carmel Post Office Project Turkey Hill-Minit Markets Store#604 275 Medical Drive Job#: W090633 Carmel, IN 46032-9998 Phone: 317-846-2489 Attu: Postmaster do Doland Wise Fax: 317-846-3135 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached n Under separate cover via Delivered the following items: ❑ Shop Drawings ❑ Prints n Copy of Letter ❑Product Data n Specifications ❑Meeting Minutes ❑ Samples ❑ Change Order(s) n Inspection Report ❑ n Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number Construction Set These are transmitted as indicated below: ❑Approved n For Your Review or Use El Approved as Noted For Your Review& Comment H Not Approved,Revise and Resubmit n As Requested n Action Not Required n For Your Records n Action Indicated on Item Transmitted n For Your Approval El For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46250 wcihe.net 317 I 846—6611 SOO!452—6408 Fax:317 1 843—0546 Allan H.Weihe,FE.,L.S.—President tVE WEIHF ENGINEERS Land surveying'Civil E^gi!ee ii is Li.riridscape Architecture TRANSMITTAL To: Carmel Clay Communications Project Turkey Hill Minit Markets Store#604 31 First Avenue NW Job#: W090633 Cannel, IN 46032 Phone: 317-671-2586 Attu: Bill Akers Fax: 317-571-2585 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you® Attached❑ Under separate cover via Delivered the following items: n Shop Drawings ❑Prints n Product Data ❑ Copy of Letter ❑ Specifications ❑Meeting Minutes ❑ Samples ❑Change Order(s)❑ ❑Inspection Report ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description Fl Copies Date Number 1 Construction Plans • • These are transmitted as indicated below: ❑Approved ❑For Your Review or Use n Approved as Noted ® For Your Review& Comment ❑Not Approved,Revise and Resubmit ❑As Requested n Action Not Required ❑ For Your Records n Action Indicated on Item Transmitted ❑ For Your Approval n For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46230 weihc.net ! 317 1 346—6611 8001 452—6403 Fax:317 I 543—0546 Allan H.Weihc,PE.,L.S.—President . ,. • NE WEIHF ENGINEERS _2nd ury Vinci Civil Engireei ilia Landscape Arch ite uie TRANSMITTAL T = . , ,i v i, !r. co rt i(le n FRA SMl l AL To: Brighthouse Networks Project Turkey Hill Minit Markets Store#604 3030 Roosevelt Avenue Job#: W090633 Indianapolis,IN 46218 Phone: 317-632-9077 x 291 Attn: Jason Kirkman Fax: 317-632-66311 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you®Attached ❑ Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑ Copy of Letter ❑ Product Data ❑ Specifications ❑Meeting Minutes ❑ Samples ❑Change Order(s) ❑Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 1 Construction Set 1 Digital File These are transmitted as indicated below: ❑Approved ❑ For Your Review or Use n Approved as Noted ® For Your Review&Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: • 10505 N.College Avenue Indianapolis,IN 46280 : wcihe.net ' 317 I$46—6611 800 1 452—6408 Fax:317 I 843—0546 Allan H.Weihe,P.E.,L.S.—President 4 , ■ r UB E WEIHE ENGINEERS Lend:_ur;ey:n.2 Ci!'ii Enoir,ee rirq i i r:dc_:' F Architecture 4:,1 i/7 M-it 1i !%!1 ii C'i, TRANSMITTAL To: Carmel City Utilities Project Turkey Hill Minit Markets Store#604 760 Third Avenue SW Job#: W090633 Carmel,IN 46032 Phone: 317-632-9077 x 291 Attn: John Duffy Fax: 317-571-2642 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you®Attached n Under separate cover via Delivered the following items: ❑ Shop Drawings ❑Prints ❑Product Data Copy of Letter ❑ Specifications ❑ Meeting Minutes ❑ Samples ❑ Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description ❑ Copies Date Number 2 Construction Plans • These are transmitted as indicated below: ❑Approved ❑For Your Review or Use ❑Approved as Noted ® For Your Review&Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted ❑ For Your Approval ❑For Signature. Return Copies to Us n Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 weihe.nei 317 I$46—6611 800 1 452—6408 Fax:317 I 843—0546 Allan H.Weihc,P.E..I_S.—I'residcm I / .416 topqq s WE THE ENGINEERS Land Sur, vine?Ci0 Er.cil eerin^ Landsc:Elpe Architecture TRANSMITTAL To: Transportation Systems Coor. -DOCS Project Turkey Hill Minit Markets Store#604 One Civic Square, 3`d Fir Job#: W090633 Carmel, IN 46032 Phone: 317-571-2417 Attn: David Littlejohn Fax: 317-571-2426 Date: 19 November 2010 Re: TAC Construction Plan Submittal We are sending you ®Attached ❑ Under separate cover via Delivered the following items: n Shop Drawings ❑Prints ❑ Copy of Letter n Product Data ❑ Specifications n Samples El Meeting Minutes ❑Change Order(s) ❑ Inspection Report ❑ ❑ Sketches/Drawings ❑Application(s)for Payment ® Sets Document Document Description n Copies Date Number 1 Construction Plans These are transmitted as indicated below: n Approved ❑ For Your Review or Use n Approved as Noted ®For Your Review&Comment ❑Not Approved,Revise and Resubmit ❑As Requested ❑Action Not Required ❑ For Your Records ❑Action Indicated on Item Transmitted n For Your Approval ❑For Signature. Return Copies to Us ❑ Remarks: Please call with any questions. Thank you. By: Eric Carter cc: 10505 N.College Avenue Indianapolis,IN 46280 wcihc.net 317 1 846—6611 800 1 452—6408 Fax:3 17 1 843—0546 Allan H.Weihc,P.E.,L.S.—Presidcnl