HomeMy WebLinkAbout0267.98.45INDEX TO SPECIFICATIONS
00100.16
Contractor's Qualification Statement.
DISTRIBUTION OF DOCUMENTS:
found, report same to the Owner immediately, who will make a ruling on
each report and will notify all concerned bidders as to his
decisions. Should such conflict, uncertainty or discrepancy, be
01000.23
PERFORMANCE, MATERIAL AND LABOR BONDS:
A. When requested, provide performance bonds, labor and material
payment bonds to the Owner, prior to start of work.
INSTRUCTIONS
DIVISION 1
Section 01000
DIVISION 2
- Section
- Section
- Section
- Section
- Section
- Section
- Section
DIVISION 3
- Section
DIVISION 4
- Section
DIVISION 5
- Section
TO BIDDERS
- GENERAL REQUIREMENTS
Supplementary General Conditions
- SITE WORK
02110 Site Clearing
02200 Earthwork
02281 Termite Control
02513 Asphalt Concrete Work
02514 Asphalt Concrete Paving
02515 Exterior Portland Cement Concrete
02831 Chain Link Fencing and Gates
- CONCRETE
03010 Concrete Work
- MASONRY
04200 Unit Masonry
- METALS
05010 Structural Steel
00100.17
00100.18
00100.19
A. Only approved contractors as determined by the owner may obtain
drawings, specifications and Supplemental Bidders Package from the
Taco Bell Construction Manager. Drawings and specifications remain
the property of Taco Bell and are to be returned complete and in good
condition. Use by unauthorized persons for any purpose whatsoever is
strictly prohibited and is punishable under federal copyright laws.
CONDITIONS:
A. Submittal of a proposal by any Contractor constitutes full
acceptance by that Contractor of all conditions as herein stated.
BUILDING PACKAGE:
A. Contractor will receive a number of miscellaneous items and
install some as part of the General Contract. These items are found
through the drawings labeled "BY TACO BELL ". Allow three (3) weeks
notice for delivery. Be prepared to accept delivery of. these
miscellaneous items at the time of groundbreaking and furnish all
labor and materials required for the unloading, receiving, safe
guarding and installation of these items.
ALTERNATES:
A. Specific manufacturers for various Contractor furnished items are
noted on the Drawings. If approved alternate manufacture's products
are furnished, note this information on the Proposal. Additionally,
provide proposed substitutions of non - approved manufacturers in
01000.14
01000.15
01000.16
01000.17
discovered after signing of the Contract, call it to the attention of
the Owner and his decision in regard thereto is final.
PRECEDENCE OF DRAWINGS:
A. The order of precedence of drawings is as follows:
1. Taco Bell's drawings over Taco Bell's specifications.
2. Larger scale drawings over smaller scale drawings.
3. Figured dimensions over scale dimensions.
4. Supplementary General Conditions over A.I.A. General Conditions.
5. Architectural drawings over mechanical and electrical drawings.
6. Any addenda over all material of an earlier date.
7. Equipment drawings, as may be provided by the Owner, over
architectural and mechanical drawings of earlier dates.
SALES TAX:
A. Include in the proposal, the payment of all state and local sales
and occupational taxes as may be levied by the governmental agencies
regarding the work.
SUBSTITUTION:
A. Any substitution must be approved in ADVANCE OF CONSTRUCTION in
writing by the Owner after receipt and study of complete information
regarding same, including any credits or additional costs.
MATERIALS AND WORKMANSHIP:
A. Unless otherwise particularly stated, furnish and install ALL
materials and labor mentioned in these specifications and /or shown on
the drawings. Execute all work in a neat and skillful manner to the
entire satisfaction of the Owner.
01000.24
01000.25
CONTRACTOR'S QUALIFIED JOB SITE SUPERINTENDENT
A. Have the Contractor or his /her designated and qualified
representative /job superintendent, with full authority to act on
behalf of Contractor under the Construction Contract, in attendance at
the job site and supervising said work, at all times during the
progress of the work.
TEMPORARY FACILITIES:
A. Take charge of the premises from the start to the completion of
the project and furnish the following:
1. Laying out of oil work and establishing building lines and levels,
confirm this information with the Owner.
2. Temporary electric power, two telephone lines, and one Contractor
provided fox machine, during the period of construction. This does
not include portable generators for use of other trades.
3. Heating of building for working and drying purposes during the
period of construction.
4. Temporary ladders as required for access to all work.
5. Water for construction use.
6. Acceptance, unloading and storage of Owner's equipment delivered to
the site are the responsibility of the Contractor.
7. Temporary toilet facilities for works.
8. Two enclosed and secured trailers for storage of Owner supplied
items. The minimum length of said trailers is twenty -five feet,
but may range to forty -feet, at the discretion of the Construction
Manager as communicated in the bid documents.
U1
54 Fes.
1541 W
,_,., E. 04
Z
Z U Z
Q
a
�►
- Section
DIVISION 6
- Section
- Section
- Section
05500 Metal Fabrications
- WOOD AND PLASTICS
06100 Rough Carpentry /Glued Laminated Beams
06192 Prefobricoted Wood Trusses
06200 Finish Carpentry
00100.20
compliance with the respective section of the general conditions.
NOTICE TO PROCEED AND PRE - CONSTRUCTION MEETING
A. No work will be started without a pre- construction meeting
attended by the Contractor, or his /her representative, and the receipt
by the Contractor of a formal "Notice to Proceed" from Taco Bell
Corporate.
01000.18
SUB- CONTRACTS:
A. As required by the Owner, have the names of all proposed Sub-
Contractors approved by the Owner prior to award of the Contract. The
Sub- Contractor is bound by the specifications. No Contractor or Sub-
Contractor may sublet or assign his Contract or any part thereof
without the written approval of the Owner.
01000.26
INSPECTION AND TESTS:
A. Call for all inspections as may be required by local authorities,
allowing a minimum of two (2) day notice for inspections to be made.
B. Notify the Owner for inspection one week prior to the
installation of the items
specified in the "Invitation To Bid ".
C. The Owner has the right to order tests and /or laboratory
DIVISION 7
- Section
- Section
- Section
- Section
- Section
- Section
- Section
DIVISION 8
- Section
- Section
- Section
- Section
- Section
- THERMAL AND MOISTURE PROTECTION
07200 Insulation
07240 Exterior Insulation & Finish System
07510 Built -up Roofing System
07520 Flexible Sheet Roofing
07530 Single Ply Roofing System
07600 Sheet Metal and Roof Accessories
07900 Joint Sealers
-DOORS AND WINDOWS
08100 Steel Doors and Frames
08210 Wood Doors
08410 Aluminum Entrances and Windows
08700 Builders Hardware
08800 Glass and Glazing
00100.21
DIVISION 1
SECTION 01000
01000.1
01000.11
RECORD DRAWINGS
A. Prior to release of the final retention, furnish Taco Bell a
complete set of drawings red -lined with all deviations made during
construction plus the permit set of drawings and specifications
maintained at the site.
B. Provide Taco Bell with one (1) 4X6 jacket original and two (2)
microfiche duplicates of the "Record Drowing" set of drawings and
specifications prior to the release of the final retention payment.
END
- GENERAL REQUIREMENTS
- SUPPLEMENTARY GENERAL CONDITIONS
GENERAL:
DEFINITIONS:
01000.19
01000.20
01000.21
LAWS AND ORDINANCES
A. Comply in all respects with all laws and ordinances having
jurisdiction over the work and /or materials or methods employed in
performing same. No additional compensation will be allowed
Contractors for failure to familiarize themselves with all conditions
under which they will perform their work unless these conditions are
brought to the Owner's attention prior to signing of Contracts, and
provisions for adjusting costs are made at that time.
PERMITS, BONDS, LICENSES:
A. Take out and pay for all permits, bonds, licenses and similar
items. Should separate Contracts be awarded, each Contractor is
responsible for permits, fees, bonds, licenses, and similar items as
may be required by work covered under his /her portion of the Contract.
Turn over receipts for same to the Owner upon completion. At the
Owner's election, the Owner may obtain any of the Permits.
PROTECTION:
A. Barricade and /or shelter his work as to reasonably protect it
01000.27
01000.28
examination of any material or work used or performed on the project
should he suspect such material or work to be of lesser quality than
specified herein. The costs of all such tests will be paid by the
Owner unless they indicate work or materials to be of lesser quality,
in which case the Contractor pays the costs along with any expenses
incurred in correction of the work.
PRECEDING WORK:
A. Before starting work, examine work previously installed and
immediately report to the Owner any visible defects or conditions
which adversely affect the quality and /or completion of this work. It
is assumed all conditions ore acceptable if no such report is
received.
CUTTING AND FITTING:
A. Execute all cutting and fitting of work as may be required by
other trades so as to insure as near perfect fit of materials as
possible.
J
_ J
m
0
U
Q
_
t�
A. Owner: The Owner is defined as TACO BELL CORP., 17901 Von
Korman, Irvine, California, 92714, (714) 863 -3871, and the Region Taco
from damage. Arrange all barricades so as to insure a reasonable
visual and physical warning for workmen and the public. Proved
DIVISION 9 - FINISHES
- Section 09210 Stucco
- Section 09250 Gypsum Board
- Section 09300 Tile
- Section 09510 Acoustical Ceilings
- Section 09900 Painting
DIVISION 10 - SPECIALTIES
- Section 10000 Building Specialties
- Section 10155 Toilet Compartments
DIVISION 11 - EQUIPMENT
- Section 11400 Owner Furnished Equipment
DIVISION 15 - MECHANICAL
- Section 15100 General Mechanical Requirements
- Section 15300 Fire Protection
- Section 15400 Plumbing
- Section 15700 Heating, Ventilating and Air Conditioning
DIVISION 16 - ELECTRICAL
- Section 16100 General Requirements
- Section 16200 Products
- Section 16300 Execution
END
INSTRUCTIONS TO BIDDERS
00100.11 GENERAL
A. Bid the project exactly as drawn and specified. Complete all
proposals and include all work as shown and /or specified and as
required by all applicable building codes. The Contractor is held to
have fully examined all drawings and specifications, not only of
his /her particular concern but of allied trades as well, and to be
fully familiar with conditions under which he /she will assume his /her
work. Particular attention is drawn to the General Conditions and the
Supplementary General Conditions of the specifications. The Contract
is in the form of a single, lump sum of type of agreement.
00100.12 PROPOSALS:
A. Sealed proposals will be received by Taco Bell at such time and
Place designated. Submit proposals in accordance with the Taco Bell
Invitation To Bid . Sign proposals by legal authorized parties of
companies only and state titles of same. Taco Bell retains the right
to reject any and /or all proposals.
00100.13 ACCEPTANCE OR WITHDRAWAL OF PROPOSALS:
A. Any Contractor who has submitted a proposal to Taco Bell may
withdraw this proposal at any time prior to the scheduled time for
opening of same; however, once proposals are opened the Contractor
agrees to honor some for a minimum of thirty (30 days after scheduled
date of opening.
00100.14 DISCREPANCIES:
A. Should a bidder find discrepancies or ambiguities in, or
omissions from, the drawings and /or the specifications, or be in doubt
as to their meaning or intent, notify the Construction Manager for
Taco Bell in time to allow for issuance of clarification by means of
Addenda for delivery in sufficient time before proposals are due.
00100.15 QUALIFICATION OF CONTRACTORS:
A. Toco Bell reserves the right to require any Contractor submitting
a proposal to furnish any or all of the following information prior to
award of the Contract.
1. Performance record of project completed over the previous two (2)
years.
2. Address and description of plant or permanent place of business.
3. An itemized list of equipment.
4. Additional information as required to satisfy Taco Bell that the
Contractor is adequately prepared to fulfill all requirements of
the Contract, such as contained in A.I.A. document A305 -
01000.12
01000.13
Bell Corp. office through which the "Invitation To Bid: was provided.
The Owner's representative for administrating the Contract is the
Construction Manager.
B. Taco Bell Technical Consultant: The Taco Bell Technical
Consultant is referred to as "Consultant" for purposes of this
project. He /she may be an Architect and /or Engineer, or other
technical representative, responsible for assisting the owner's
representative, the Construction Manager, in administrating the
contract.
C. Contractor: The person(s), company(ies) or corporation(s) with
whom the Owner makes a direct Contract for the work or any portion
thereof, or for any materials or related services re uired thereto.
D. Sub - Contractor: Any person(s), company(ies�, or corporations)
with whom a contractor makes a Contract to furnish labor and /or
service and /or material in connection with the project. Within the
drawing and specifications, the term "Contractor" is interpreted to
mean Sub - Contractor where applicable unless further defined.
E. Project: The project is defined as the complete labor, materials
and services required for construction of a Taco Bell Restaurant and
all related work as described in the Contract documents.
F. Site: The property on which the project is located.
G. Contract Documents: The Contract documents consist of (1) The
Building Construction Contract, (2) The Drawings (3) The
Specifications, (4) Soils Report. Include the dates and revision
dates of all drawings and specifications on the proposal form.
GENERAL CONDITIONS:
A. The Standard Form of General Conditions published by the American
Institute of Architects (A.I.A.) form A201, latest edition, is binding
and the General conditions included herein are supplementary thereto.
In the event of conflict, the Supplementary General Conditions govern
over General Conditions, and the Taco Bell Construction Contract
governs over the Supplementary General Conditions.
B. Use the Taco Bell Construction Contract, Contractor's Draw
Schedule, Contract Change Order and Final Waiver of Lien. Copies of
the above forms are on file at the Owner's office.
C. It is accepted as a fact that all Contractors have inspected the
site prior to submitting their bid and no additional compensation is
allowed for failure to fulfill this requirement. It is to to be
construed however, that the Contractors have included in their bids
amounts to cover unforeseen conditions or obstacles other than those
indicated on the drawings or visually apparent at the site. Should
unforeseen conditions arise, notify the Owner immediately.
D. The following specifications are divided into chapters and each
Contractor is to figure on that portion with which he is concerned,
It is the responsibility of each Contractor to read and familiarize
himself with the General Conditions and Supplementary General
Conditions which are considered equally binding with the remaining
specifications.
E. Settle any controversy or claim arising due to a labor conflict
caused by the wording or assignment of these specifications in
accordance with local governing labor practice.
F. List alternates, whether specified by the Owner or suggested by
the Contractor, separately on the proposal. Indicate the cost of
materials and labor required to complete the alternate and the credit
due the Owner for any materials and /or labor not required due to the
alternate installation.
G The Area Construction Manager is the Owner's and Architect's sole
representatives during the administration of the construction
contract.
DRAWINGS AND SPECIFICATIONS
A. Execute all work according to the true meaning and intent of the
drawings and specifications which are intended to include everything
required and necessary for the proper and entire finishing of the
work, notwithstanding, that each and every item necessarily involved
in the work is not specifically mentioned. Deliver the completed work
to the Owner in a perfect and undamaged condition without exception.
B. The drawings and specifications are intended to be cooperative.
Furnish and perform the work or materials called for by the drawings
and not mentioned in the specifications or vice -versa in as faithful a
manner as though treated by both. The specifications are intended to
represent minimum design and are superseded by the drawings.
C. Before submitting an estimate carefully check the drawings and
specifications and should a conflict, uncertainty or discrepancy be
01000.22
flashing type blinkers around open trenches
B. The Contractor(s) is held responsible for any damage to his /her
work as may be due to negligence of the above, or as may be caused by
accident, wind, rain snow, freezing, riot, malicious mischief or labor
commotion, theft, or similar reasons, if due to his /her acts,
omissions or negligence. If such damage occurs, restore the work to
its previous condition at no cost to the Owner.
C. Protect all adjoining property from damage during the course of
the work. If required by local laws or ordinances, issue notices to
Owner of said property. No use of adjacent privately owned property
by a Contractor without written permission by its Owner is allowed.
D. Contractor is responsible for any damage or loss to Owner's
building package or equipment in said Contractor's possession. At
Owner's election, the cost of repair or replacement of any missing
items will be borne by said Contractor.
INSURANCE:
A. In general, maintain such insurance to protect Contractor, Owner
and the Owner's agents and representatives from any and all claims
under Workmen's Compensation Acts and from all claims for damages
because of bodily injury, including death, and all claims for property
damage arising from Contractors operations and /or the operations of
Sub - Contractors employed by him, in the amount stated herein. For Sub-
contractor(s) not covered by the Contractor(s) insurance, provide
similar insurance of their own. Obtain coverage from a company
holding a General rating of "A" or better as set forth in the most
current issue of Best's Key Rating Insurance Guide.
B. "Hold Harmless" Clause: Provide certificate stating that this
endorsement is included in the policy(ies).
C. This Contractor assumes the liability for all losses, damages
(including loss of use), expenses, demands and claims in connection
with or arising out of any injury or alleged injury to persons
(including death) or damages or alleged damage to property, sustained
or alleged to have been sustained, in connection with or to have
arisen out of the performance of the work by the Contractor, his Sub-
Contractors, and their agents, servants and employees, including
losses, expenses, or damages sustained by the Owner and the Architect.
The Contractor hereby undertakes and agrees to indemnify and hold
harmless the Owner and the Architect, their agents, servants, and
employees, from any and all such losses, expenses damages (including
loss of use), demands and claims, and defend any suit or action
brought against any of them, based on any alleged injury (including
death) or damage (including loss of use) and pay all damages,
judgments, costs and expenses, including attorney's fees, in
connection with said demands and claims resulting therefrom.
D. The above clause applies in all states unless restricted by state
statute. Should this be the case. Provide the maximum form of "Hold
Harmless" allowed by the law.
E. Provide Comprehensive General Liability Insurance including a
Broad Form endorsement and a Broad Form Property Damage endorsement
with limits not less than $1 million CSL (Combined Single Limit). If
appropriate, also maintain scaffolding and demolition insurance.
F. Provide Workers Compensation Insurance in accordance with
applicable state requirements.
G. Provide Employers' Liability Insurance in an amount not less thon
$100,000.
H. Provide Comprehensive Automobile Liability including owned, non-
owned and hire coverage in an amount not less than $500,000 CSL
(Combined Single Limit).
I. Satisfy any insurance requirements necessitated by any pertinent
governmental authority.
J. At Owners election, maintain Builders Risk insurance covering
the premises. Have such insurance written on an oil risk basis and
covering all the work until Owner's final acceptance of same.
K. Provide insurance policies immediately after award of contract
and prior to any work
being performed. Upon obtaining policies, notify the Owner and
file certificates and /or duplicate policies from insurance companies
with the Owner showing policy numbers, dates policies are in effect,
and all limitations and exclusion. Provide certificates stating that
the insurance company will notify the Owner by registered moil thirty
(30) days prior to the expiration or cancellation of any policy.
01000.29
01000.30
01000.31
01000.32
01000.33
01000.34
DAMAGED WORK:
A. Pay for replacement of any work damaged in connection with the
Contract, and perf orm such patching or replacement by skilled
personnel specializing in the particular trade so as to restore
damaged work to completely acceptable condition. Should
responsibility for damage be unable to be determined, prorate the cost
of repairing some among Contractors working on the job at the time the
damage occurred as determined by the Owner. The decision of the Owner
is final.
ADVERTISING:
A. No advertising is allowed.
COMPLETED WORK:
A. Deliver completed work as called for by the Contract to the Owner
free from liens, claims or encumbrances of any description whatsoever
against the Owner. Acceptance of such work is defined as approval of
final payout.
B. If Owner receives "notice of claim" to be filed or if a claim is
filed as a result of Contractor's non - payment, Owner possesses the
right under the Construction Contract to either settle the claim and
deduct same from the Contract sum or to require the Contractor to bond
over such small claims, including any associated expenses as defined
in the Construction Contract and to promptly defend to conclusion
Owner and Owner's interest against said claim of claims.
C. Completion of Work on the project requires the submission by the
Contractor of certain documentation in order for the Final Retention
Draw to be paid to the Contractor. The submission of these documents
is defined in the Construction Contract and is inclusive of the
following items: Record Drawings and Specifications including
microfiche copies: Lien Waivers from Contractor and Subcontractors and
Material men; List of all Subcontractors and Material men:
Contractor's Guarantee and Completion Affidavit; Final Signed Punch
List; any Work Orders and Associated Contract Change Orders;
Certificate of occupancy and any related public agency; Certification
of project completion; Copies of project Inspection Reports; Permitted
Set of Drawings and Specification; Al warranties; all certifications
noted in the drawings including civil drawings, the bid documents and
Construction Contract; and any required test and /or engineering
reports.
MAINTENANCE AND CLEANING:
A. Throughout the period of construction, be responsible for
satisfactorily maintaining the premises in a neat and clean condition.
This means removal of all refuse and debris from the premises.
B. Store all equipment and materials in a neat manner and protect
them from any damage from the elements. Maintain building in a
generally clean condition during the period of construction, and upon
final completion provide a professional service to thoroughly clean
all glass, floors, furniture and equipment.
GUARANTEE:
A Fully and unconditionally guarantee all labor, materials, and
equipment required by the Owner- contractor agreement(s) for a period
of one(1) year from the date of final acceptance or the date the
restaurant is opened for business by the Owner, unless otherwise
specified in specific chapters herein.
CHANGES:
A. The Owner, without invalidating the Contract, may order changes
in the work within the general scope of the Contract, consisting of
additions, deletions, or other revision. The Contract sum and the
contract time will be adjusted accordingly. A Taco Bell Contract
change order may be issued by a Construction Manager but must be
approved by the Director of Development Services prior to payment.
B. The cost or credit to the Owner resulting from a change in the
work will be determined by mutual agreement. Perform all work under
the applicable conditions of the Contract documents.
C. Obtain written authorization for changes in the work
(Construction Work Order) from the Construction Manager prior to
completion of the work.
U
O
�---
Q
-
�
-
U
L_L�
0_
U�
0
Q
O
Q
Z
z Q
0
W
Z
Z
Q
LLI
U)
T
U
G
T
Rows
DRAM BY. TIP
CHECKED BY: TH
BuRD" TYPE
K-50
FRAME
JOB NUMBER
g 12 5
PROTOTYPE ISSUE DATE
2/1/97.1
SHE NUMBER
spi