HomeMy WebLinkAboutSouthwest Curb Cut email 3-27-20131
Conn, Angelina V
From:Foley, Amanda J
Sent:Thursday, March 28, 2013 10:30 AM
To:Conn, Angelina V
Subject:RE: McDonald's (southwestern curb cut)
We are approving the southern curb cut modification where it was already planned. A condition of the approval of the
curb cut modification however is that the City reserves the right to restrict the curb cut in the future (most likely to a right-
in/right-out only) when a public road is provided from AAA Way (The Fountains). This was part of our support letter to
the BPW.
Amanda Foley
Staff Engineer
City of Carmel
Department of Engineering
317-571-2309 (direct)
afoley@carmel.in.gov
From: Conn, Angelina V
Sent: Wednesday, March 27, 2013 4:12 PM
To: Foley, Amanda J
Subject: FW: McDonald's
Hi, Amanda –
Just checking in to see where the Engineering Dept. stands on the site’s traffic plan. Please give me an update. Thank
you.
Angie
From: Hollibaugh, Mike P
Sent: Monday, March 04, 2013 12:56 PM
To: Conn, Angelina V; Foley, Amanda J; McBride, Mike T
Subject: RE: McDonald's
If the site flow is reversed as a result, it should go back to PC. They spent a fair amount of time on that subject.
Do we really have a congestion or traffic flow problem there to restrict/manage access like that?
From: Conn, Angelina V
Sent: Monday, March 04, 2013 12:12 PM
To: Foley, Amanda J
Cc: Hollibaugh, Mike P
Subject: RE: McDonald's
Amanda ‐
I wish this would have come up during the Plan Commission review process… I am not sure if we need to send this back
to Plan Commission or not; I will run it past Mike H. It might be as simple as just adding a revised site traffic plan to the
plan commission file folder…
Are Blair and McDonald’s okay with the changes for that south entrance? Is he just concerned that he will need to go
back to the Plan Commission for their blessing?