HomeMy WebLinkAboutKREAGER BROTHERS EXCAVATING -001937 -5/31/2011 ` Transmittal Sheet Page 1
Carmel Redevelopment Comm
Kreager Brothers Excavating Check: 1937
PO Box 80157 Date: 5/31/2011
Fort EWayne, IN 46898 Vendor: KREAGER1
Prior
Invoice P.O. Num. Invoice Amt Balance Retention Discount Amt. Paid
4 21 147,400.00 9,597.19 0.00 0.00 9,597.19
PAC Feb 2008
5 21 138,054.23 13,805.42 0.00 0.00 13,805.42
App 5
6 21 950.00 95.00 0.00 0.00 95.00
application 6
7 21 6,572.13 657.21 0.00 0.00 657.21
App 7 on PAC
10 21 7,270.00 363.50 0.00 0.00 363.50
application 10
11 21 859.09 859.09 0.00 0.00 859.09
Adjust to retainage
13-2 -25,377.41 -25,377.41 0.00 0.00 -25,377.41
Adjust to account
14 1,889.89 1,889.89 0.00 0.00 1,889.89
App 14
277,617.93 1,889.89 0.00 0.00 1,889.89
APPLICATION AND CERTIFICATE FOR PAYMENT CONSTRUCTION MANAGER-ADVISER EDITION 2'1
AIA DOCUMENT G702/CMa (Instructions on reverse side)
1'AGI?ONE OF PAGES
To OWNER:City of Carmel Redevelop Comm' PROJECT:Carmel Performing Arts APPLICATION NO.: 14 Distribution to:
One Civic Square PERIOD TO: 07/30/10 ❑OWNER
Attn Les Olds PROJECT NOS.:2695-001 ❑CONSTRUCTION
Carmel, IN 46032 MANAGER
FROM CONTRACTOR:Kreager Brothers Excavating, Inc. CONTRACT DATE: ❑ ARCHITECT
PO Box 80187 ❑ CONTRACTOR
Fort Wayne, IN 46898 VIA CONSTRUCTION MANAGER:
CONTRACT FOR: VIA ARCHITECT:
CONTRACTOR'S APPLICATION FOR PAYMENT The undersigned Contractor covered that this the best of the Payment Contractor's knowledge,c feted
matian and belief the Work covered by this Applic:nion for 1':q'ment has been complete(:
Application is made for payment, as shown below, in connection with the Contract. in accordance with the Contract Documents, that all amounts have been paid by the
Continuation Sheet, AIA Document G703, is attached. Contractor for Work for which previous Certificates for Payment were issued and pay-
t. ORIGINAL CONTRACT SUM a 444,000.00 ments rec. ed from the Owner, and that current payment shown herein is now due.
105,250.07 Kre ger Brothers Excavating, Inc
2. Net Change By Change Orders 250.07 CONT ACTT k: 6________,549,250.07 By: ._.Q,t , i Date:
07/30/10
3. CONTRACT SUM TO DATE (Line I ± 2) $
4. TOTAL COMPLETED & STORED TO DATE 549,250.07 state of: IN
(Column G on G702) County of: Allen
Subscribed and sworn to before
5. RETAINAGE: 0.00 30th
me this day of July, 2010
a. % of Completed Work $
(C)lumns D + l: on (470)3) 0.00 Notary Public: %9 1- �G
b. 0 % of Stored Material $ 01/09/14
(Column F on 6703) My Commission expires:
'I roll Retainage (Line 5a + 5b or 0.00
'I,)tal in Column I of 6703) $ CERTIFICATE FOR PAYMENT
6. TOTAL EARNED LESS RETAINAGE $ 549,250.07 In accordance with the Contract Documents,based on on-site observations a d the data
(Line 4 less Line 5 'Idol) comprising this application, the Construction Manager and Architect certify to the Owner
7. LESS PREVIOUS CERTIFICATES FOR PAYMENT that to the best of their knowledge, information and belief the Work has progressed as
547,360.18 indicated, the quality of the Work is in accordance with the Contract Documents, and
(Line 6 from prior Certificate) 5 the Contractor is entitled to payment of the AMOUNT CERTIFIED.
8. CURRENT PAYMENT DUE $ 1,889'89 1 AMOUNT CERTIFIED $ t•
9. BALANCE TO FINISH, INCLUDING RETAINAGE (Attach explanation, it tomato,certified di/ rs jr,of the toomait applied jar. Initial
�� all figures on this A))licatiori and on the C loom tior,Sheet that cba„' d to coi,/or iii
(Line 3 less Line 6) $ ./b // �'
to the amount c'- flied.)
CO -TRUCTIO f AN•v, 'R:
CHANGE ORDER SUMMARY ADDITIONS DEDUCTIONS , �/, / ®d n� I r
Total changes approved in By: /2 )>`� j Date: 'l, �i t
previous months by Owner 110,250.07 0 A IT!lbtal approved this Month -5000.00 TOTALS 110,250.07 -5001) 00 By: ;-A&lfr
^''ti" D:tte:.
105 250.07 This Certificate is not negotiable.The AMOUNT CERTIFIED is payable only to the Con-
NET CHANGES by Change Order tractor named herein. Issuance, payment and acceptance of payment are without
prejudice to any rights of the Owner or Contractor under this Contract.
1��10/� AIA DOCUMENT G702/CMa•APPLICATION AND CERTIFICATE FOR PAYMENT•CONSTRI'cnoN MANAGERAD\'ISER EDITION
n/a I'sEt EDITION•AIA"' • (c)l')7d •Till:AMERICAN INSTITI'TE OF ARCHITECTS, 1.'35 NEW YORK A\'ENI'E.NW..\r'ASHINGION. G702/CMa-1992
�;__ I).(:.,(VIII'-5p)O•WARNING:Unlicensed photocopying violates U.S.copyright laws and will subject the violator to legal prosecution. •
Director of Redevelopment '/4{6 0 0 7 X Of-
Application and Certificate For Payment -- page 2 .
To Owner: City of Carmel Redevelop Comm Application No: 14 Date: 07/30/10 Period To: 07/30/10
From (Contractor): KREAGER BROTHERS EXCAVATING Contractor's Job Number: 073169
Project: CARMEL PERFORMING ARTS Architect's Project No:
Work Completed '
Materials Completed and
Item Scheduled Previous Presently Stored Stored to Date Balance to Finish
Number Description Value Application This Period % Retention Memo
01 MOBILIZATION 0.00 0.00 0.00 0.00 0.00 0 00 0.00 0.00
01-01 LABOR&EQUIPMENT 10,700.00 10,700.00 0.00 0.00 10,700.00 100.00 0.00 0.00
01-02 MATERIAL 9,300.00 9,300.00 0.00 0.00 9,300.00 100.00 0.00 0.00
02 EROSION CONTROL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02-01 LABOR&EQUIPMENT 2,300.00 2,300.00 0.00 0.00 2,300.00 100.00 0.00 0.00
02-02 MATERIAL 1,500.00 1,500.00 0.00 0.00 1,500.00 100.00 0.00 0.00
03 MAINTAIN EROSION CONTROL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03-01 LABOR&EQUIPMENT 9,500.00 9,500.00 0.00 0 00 9,500.00 100.00 0.00 0.00
04 STONE LAYDOWN AREA 0.00 0.00 0.00 0.00 0.00 000 0.00 0.00
04-01 LABOR&EQUIPMENT 6,500.00 6,500.00 0.00 0.00 6,500.00 100.00 0.00 0.00
04-02 MATERIAL 17,900.00 17,900.00 0.00 0.00 17,900.00 100.00 0.00 0.00
05 MASS EXCAVATION 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05-01 LABOR&EQUIPMENT 291,000.00 291,000.00 0.00 0.00 291,000.00 100.00 0.00 0.00
06 STORM SEWER 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06-01 LABOR&EQUIPMENT 5,600.00 5,600.00 0.00 0.00 5,600.00 100.00 0.00 0.00
06-02 MATERIAL 6,200.00 6,200.00 0.00 0.00 6,200.00 100.00 0.00 0.00
07 WEEKLY SWEEPING OF ROADS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07-01 LABOR&EQUIPMENT 14,400.00 14,400.00 0.00 0.00 14,400.00 100.00 0.00 0.00
08 PORT-O-LETS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08-01 LABOR&EQUIPMENT 2,100.00 2,100.00 0.00 0.00 2,100.00 100.00 0.00 0.00
09 PROVIDE 30 CY DUMPSTERS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09-02 MATERIAL 7,500.00 7,500.00 0.00 0.00 7,500.00 100.00 0.00 0.00
10 TEMPORARY ASPHALT PAVEMENT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10-01 LABOR&EQUIPMENT 15,000.00 15,000.00 0.00 0.00 15,000.00 100.00 0.00 0.00
11 PLACE TEMP STONE PER CM DIRECT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11-01 LABOR&EQUIPMENT 6,000.00 6,000.00 0.00 0.00 6,000.00 100.00 0.00 0.00
Application and Certificate For Payment -- page 3 .
To Owner: City of Carmel Redevelop Comm Application No: 14 Date: 07/30/10 Period To: 07/30/10
From(Contractor): KREAGER BROTHERS EXCAVATING Contractor's Job Number: 073169
Project: CARMEL PERFORMING ARTS Architect's Project No:
Work Completed
Materials Completed and
Item Scheduled Previous Presently Stored Stored to Date Balance to Finish
Number Description Value Application This Period % Retention Memo
11-02 MATERIAL 6,000.00 6,000.00 0.00 0.00 6,000.00 100,00 0.00 0.00
12 ALLOWANCE-CLEAN-UP LABOR 23,500.00 23,500.00 0.00 0 00 23,500.00 100,00 0.00 0.00
13 ALLOWANCE-CLEAN-UP MATERIAL 5,000.00 5,000.00 0.00 0.00 5,000.00 100 00 0.00 0.00
14 TOPOGRAPHIC ASBUILT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
14-01 LABOR&EQUIPMENT 4,000.00 4,000.00 0.00 0.00 4,000.00 100,00 0.00 0.00
15-01 Change Order 1 18,415.70 18,415.70 0.00 0.00 18,415.70 100.00 0.00 0.00
15-02 Change Order 2 9,799.42 9,799.42 0.00 0.00 9,799.42 100,00 0.00 0.00
15-03 Change Order 3 8,355.76 8,355.76 0.00 0.00 8,355.76 100.00 0.00 0.00
15-04 Change Order 4 39,633.52 39,633.52 0.00 0.00 39,633.52 100.00 0.00 0.00
15-05 Change Order 5 10,809.83 10,809.83 0 00 0.00 10,809.83 100.00 0.00 0.00
15-06 Change Order 6 23,235.84 23,235.84 0.00 0.00 23,235.84 100.00 0.00 0.00
15-07 Change order 7 -5,000.00 -5,000.00 0.00 0.00 -5,000.00 100.00 0.00 0.00
Application Total 549,250.07 549,250.07 0.00 0.00 549,250 07 100.00 0.00 0.00
•
WAIVER OF LIEN
PARTIAL FINAL X
KNOWN ALL MEN BY THESE PRESENTS, THAT THE UNDERSIGNED
Christine George, Controller for Kreager Brothers Excavating, Inc.
FOR AND IN CONSIDERATION OF One Thousand Eight Hundred Eighty Nine &
89/100 Dollars $ 1,889.89 ... REPRESENTING THE ACCUMULATED AMOUNT
PAID TO THE UNDERSIGNED FOR Kreager Brothers Excavating, Inc PAY PERIOD
ENDING 07/31/10 , RECEIPT THEREOF IS HEREBY ACKNOWLEDGED, DOES
WAIVE, RELEASE AND SURRENDER ANY AND ALL LIEN OR CLAIM OF RIGHT OF
LIEN, TO THE DATE OF THIS WAIVER, FOR LABOR, MATERIAL AND/OR
SERVICES FURNISHED UPON THE PREMISES SITUATED IN THE COUNTY OF
Allen , STATE OF INDIANA.
DESCRIBED AS FOLLOWS:
Carmel Regional Performing Arts Center
Shiel Sexton Job #2695-001
Carmel, IN r'
BY: At(
TITLE: Controller
DATE: 07/30/10
Subscribed and sworn to before me this 30th day of July, 2010
County of Allen
N ota ry:-S ,
State of: Indiana
My Commission Expires : 01/09/14