HomeMy WebLinkAbout13070084. Demo Plan1 1D,EMOLITION PLAN
NORTH
GENERAL NOTES - DEMOLITION
A. Refer to Project General Notes and Reference Specifications on sheet A001 for
additional information regarding demolition, existing conditioins and additional
associated project requirements.
B. Dashed lines indicate existing items to be removed unless otherwise indicated.
Contractor shall be responsible for the off-site disposal of all demolition items.
C. Following above ceiling demolition activity, the Contractor shall return the existing
suspended ceiling system to remain to like new condition. This shall include repair to
the ceiling grid, suspension system and all associated assemblies as well as the
replacement of damaged ceiling panels.
D. Refer to Demolition Plan for additional notes and demolition information.
E. Dimensions shown for existing construction to be demolished are approximate and
are intended to give a general scope of work to be removed or temporarily removed
to accomodate new construction. Coordinate demolition work with design intent of
new construction to provide adequate area for this work.
F. If applicable, refer to structural, mechanical, electrical, and plumbing documents for
additional demolition information.
G. Remove and reinstall all equipment or construction on walls receiving new finishes.
Coordinate with architectural finish plan and/or schedule.
H. Contractor shall verify any ductwork, piping or conduit penetrations through existing
wall construction. If penetrations occur where items are to be removed, opening
shall be filled flush with the same material as the surrounding wall. The contractor
shall maintain the integrity of rated wall construction.
J. The Contractor shall verify floor elevations on either side of walls being removed.
Floors shall be patched and filled with leveling compound where required for a level
floor condition.
K. Electrical, data or other associated devices or equipment are shown for reference
only.
L. The contractor shall remove existing floor finishes as indicated or as required for new
construction work. Remove floor finish adhesive and prepare slab as required to
receive new finish.
DEMOLITION LEGEND
1
2
3
4
5
6
Refer to general demolition notes for additional information.
� — �
Indicates existing partitions to be removed.
Indicates existing partitions to remain.
Dashed lines indicate portion of existing partition to be
removed for future construction.
� Indicates existing door/frame/hardware to be removed (or
'� door & sidelight if indicated as such). Note: Door systems
� � ma be re-used. Coordinate with Buildin Owner ossible
�/ t door re-use. Use only best condition doors for this purpose.
Refer to floor plans for possible new location.
Indicates new dooNframe/hardware.
Indicates area not in contract. Refer to floor plans for
additional information.
� KEYED NOTES - DEMOLITION
Demolish existing wall construction.
Remove door, frame all associated hardware. Salvage for reuse.
Remove door, frame, sidelight and all associated hardware. Salvage for reuse.
Demolish portion of wall for new window glazing. See A201 for more information.
Demolish portion of wall for new door location. See A201 for more inforamtion.
Existing cabinetry to remain. Not in project scope.
/�;��
i%,%,
�
,,,;
; ,'%i�
i� �
�r
/ �u f '
i ,,, „� �
, „ ,
,. , o� �
� ,
� � � �� �,,,�
�� ���
� ��.�� � � �
�
O
�
�
�
■�
V
�
�
_
■�
�
�
_
4�
>
■�
�
�
�
�
�
f�
L
�
�
�
�
J
STAMP:
�
�
�o
� N
N
W �'
��
� �
0
.�`�� NY °'�.
�.�.���......,q�� �.,
:,��Pr ����srER�o���2�:
' No.
,
,
! :11200176:
.
� STATE OF i
,��i�,,���•. �ND�AN � �: � ,,,,,�
�4 G .
���'''cH � ��•�``��•
� �.���
05/t
ISSUE: �
Tenant Review OS/�
DRAWING TITLE:
Demolition Plan
JOB NO. 1122
DATE: OS/I
SHEET NUMBER:
A101
COPYRIGHT 2013 CARSON DESIGN A',