HomeMy WebLinkAboutBen Hur Construction/CO1/CRC/2,228.40 increase/Palladium Steel Retrofit CITY OF CARMEL TO: Ben Hur Construction Co. CONTRACT CHANGE ORDER NO.: 1 P.O.Box 22345 DATE: 8.1.13 Indianapolis,IN 46222 PROJECT NAME: Palladium Steel Retrofit 2013(Investigative Work) CITY REQ. NO.: CITY PO NO.: CITY PO DATE: April 17,2013 1. You are directed to make the following changes in this Contract: SCHEDULED ADJUSTMENT ITEM AMOUNT (+)OR(-)DAYS Provide additional investigative services $2,228.40 0 as described in Ben Hurts letter dated August 1,2013(copy attached) The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ $12,377.00 Contract Price will be increased/decreased by this Change Order $ $2.228.40 New Contract Price including this Change Order $ $14.605 40 Contract Time Prior to this Change Order SEE CONTRACT was Project Substantial Completion Date Net increased/decreased resulting from this Change Order 0 Days Current Contract Time including this Change Order SEE CONTRACT is Revised Project Substantial Completion Date This Change Order is for full and final settlement of all direct,indirect,impact costs and time extensions incurred at any lime resulting from the changes to the Contract. The Above Changes Are The Above Changes Are Recommended: Accepted: / Appr ved: Shiel Sexton utw� t-ts...r Co.M5{Tutcs) Construction Manager Contractor Les Olds pp Executive Director 902 N.Capitol Ave. k:2 vo K 2 z$t!f Address (�Address • Indianapolis,IN 46204 S�4cO, k[Jt41ol ,_Lt./ c/L2L2 City/St�iej?ip Ciq'/State/L�p Phone: 423,4OOo Phone: B —(iv 3 Sega Date: 8, 5/3 Date: Ce) t t t S • • P.O. BOX 22345 • INDIANAPOLIS, INDIANA 46222 (317)635-8816 • FAX (317) 635-0898 BEN HUR CONSTRUCTION CO. August 1, 2013 TO: Shiel Sexton Co. 902 N. Capitol Ave. Indianapolis, IN 46204 Attn: Mike Anderson Re: Carmel Palladium Retrofit Additional Investigative Work Mike, During the installation process of the steel retrofit we were asked to do further investigative reviews by you and W. P. Moore. This work included: Exact measuring(to .0010" for the shims on the T4 truss; exact measuring of the brae conflict at the East end of T3 truss; assist with the development of installation procedures and coordinate with the inspection firm,._.etc.) Below are the costs associated with that work: Labor: 30 man hours @ $74.28/hour $2,228.40 We respectfully request that we be issued a change order to reflect these additional costs. Thank you for this opportunity to be of service. Very truly yours, BEN HUR CONSTRUCTION C Y A. Scott Scott A. Bullerdick Vice President • tf14„r ` AMC CERTIFIED ADVANCED STEEL ERECTOR• A °IORO' ST. LOUIS • INDIANAPOLIS CINCINNATI art NatlrtMd LNgn(inaLutprl