Loading...
HomeMy WebLinkAboutRust Construction/ENG/CO1/-5,687.12/Wetland Mitigation Bray Homestead CITY OF CARMEL TO: Lisa Scott CONTRACT CHANGE ORDER NO.: 1 Engineering Admininstration DATE: December 23,2013 City of Cannel Indiana PROJECT NAME: Wetland Mitigation Site-Bray Homestead One Civic Square CITY REQ. NO.: Carmel, IN 46032 CITY PO NO.: 12-02 CITY PO DATE: I. You are directed to make the following changes in this Contract: a. This change order balances all of the pay items for the Carmel Project#12-02. This C 4114 change order is used to balance the contract value. SCHEDULED ADJUSTMENT ITEM AMOUNT - (+)OR(-) DAYS • II. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: W.D.C.NO.: Other: The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $ 76,444.00 Contract Price will be increased/decreased by this Change Order $ (5,687.12) New Contract Price including this Change Order $ 70,756.88 Contract Time prior to this Change Order Days 12/31/2013 Completion Date Net increased/decreased resulting from this Change Order. 0 Days Current Contract Time including this Change Order 12/31/2013 Completion Date This Change Order is for full and final settlement of all direct,indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Approved Recommended Accepted American Structurepoint, Inc. Rust Construction,Inc. ,d/ 7 ENGINEER coNTancrorz ames Brainard, Mayor • ' 7260 Shadeland Station 418 West State Road 258 Address Address • Michael Mc(B(�ide, ity Engineer Indianapolis, IN 46256 Seymour,IN 47274 i )iyf -I".f) toi):4 Candstate/Zip CitviState/Zip Mary Ann Burke%Me ber' By: ';I • , " - By: / Lori,3atson, Member ATTEST: Phone: 281-9563 Phone: SI2.-ki t7-2100 .._14/s./ - II- • • / Diana Cordray, Clerk-Treasurer Date: ) / 1 V�I+ Date: / - fc-/yf Date: -S1,7 Contract Modification 2/23/2013 12:53 PM City of Cannel Engineering _ FieMMManager 4.5a Contract: _Carmel 12-02,Wetland Mitigation Site Bray Homestead Cont. Mod. Revision Cont. Mod. Net Change Awarded Contract Amount Number Number Date 1 12/23/2013 $-5,687.13 $76,444.00 Route Contract Location SR238 and Hinkle Road Short Description Change Order#1 Description of Changes Balancing change order for the Bray Mitigation project-Carmel Contract 12-02. Increases / Decreases Project: 12-02,Wetland Mitigation Site Bray Homestead CNST Category: 1,Wetland Mitigation Item Description Item Code Prop.Ln. Item Type Unit Quantity Chg. Unit Price Dollar Value Erosion Control Blanket 3082 0004 ORIGINAL SYD - 112.000 1.50000 $168.00 Temporary Construction Entrance/Exit _3083 0005 ORIGINAL LS -1.000 3,000.00000 $-3,000.00 Temporary Mulching _3084 0006 ORIGINAL TON -5.875 435.00000. $-2,555.63 Temporary Silt Fence _0123 0007 ORIGINAL LFT -50.000 4.00000 $-200.00 • Geotextiles 3085 0008 ORIGINAL SYD 10.000 3.00000 $30.00 Riprap, Uniform 3086 0009 ORIGINAL TON -13.020 25.00000 $-325.50 Contract:_Carmel 12-02 Cont. Mod.: 1 Page 1 of 2 Contract Modification 2/23/2013 12:53 PM City of Carmel Engineering FieIdManager 4.5a • Increases / Decreases Project: 12-02,Wetland Mitigation Site Bray Homestead CNST Category: 1,Wetland Mitigation Item Description Item Code Prop.Ln. Item Type Unit Quantity Chg. Unit Price Dollar Value Mobilization and Demobilization for Seeding _0114 0010 ORIGINAL EACH -1.000 500.00000 $-500.00 Seed Mixture,Emergent Wetland _3089 0013 ORIGINAL LBS -1.200 100.00000 $-120.00 Plant, Deciduous Tree,Single Stem, 1.25 In. _3090 0014 ORIGINAL EACH 12.000 68.00000 $816.00 or Under Subtotal for Category 1: $-5,687.13 Subtotal for Project 12-02: $-5,687.13 FEDERAL PARTICIPATION -ACTION BY F.H.W.A. Approved Not Eligible See Letter Dated (Signature) (Date) • • Contract:_Carmel 12-02 . Cont. Mod.: 1 Page 2 of 2